Title: Instrument panel: Side panel installation & wiring
1. Tied up several wire harnesses under the fuel selector panel. 2. Prepped panel mount angle by painting its edge flat black. This will make sure it doesn't show at the top edge of the panel if there is a gap there. 3. Riveted left side instrument panel to the mount angle. 4. Installed both side panels, clecoing the right side panel in place temporarily. 5. Wired and plumbed all switches and controls on left side instrument panel. 6. Began wiring the right side instrument panel switches.