Title: 40-2 3 Flap Systems step 1-6 and 1-4
Alignement of flap torque tube and flap crank. Clecoed using predrilled and matchdrilled 1/8. Bolted the flap crank to the torque tube and matchdrilled other holes installing second set of hardware. Matchdrilled using the Jig. Everything went fine on one side, unfortunately second side something went wrong with the alignment. After consultation with VANS they reccommended to wait until final rigging as the problem may be resolve with the adjustments. In any case i ordered another torque tube and another flap crank All the tubes have been primed internally. Same process on both sides.