Title: Wiring and paint prep
Applied acid etching to all inspection panels and fairings. Rinsed thoroughly with water. Plan to prime and paint white tomorrow. Continued to wire wing lighting and power/ground wires at Station 3 terminal blocks. Ops checked landing lites and nav/strobe lights. All operating normally. Still need to tidy up wiring . Rerouted flap teleflex cables to final location.