Title: 9-14, 9-15 & 9-17: Right elevator proseal and counterweight
Got the tank sealant applied to the foam ribs and installed in the trim tab. Set in the clamps and riveted the end tabs. Moved on to the elevator and applied sealant to the foam ribs then coated the wedge pretty liberally again. Installed clecos in every hole then went between each cleco and gave a good squeeze with the vice grip clamps. Set the weights on the trailing edge and will let it cure for the rest of the week. Back to the Horizontal stabilizer. I did finish off the right side lead counterbalance weights too and installed them while proseal is curing. Nice to have AN bolt gauge I bought recently to confirm the AN3-13 bolts from the assorted pack of bolts Van's supplied. Order confirmation letter for the wing showed up today too. Looks like an October 4th crating date. Glad I ordered it when I did.