Project: Sling2   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:GARY WOLD   -  
Project:   The Airplane Factory - Sling 2   -   VIEW REPORTS
Total Hours:231.9
Total Flight Time:
Total Expense:N/A
Start/Last Date:Nov 01, 2019 - No Finish Date
Engine:Rotax 912iS
Panel:Garmin
 
Friendly URL: https://eaabuilderslog.org?s=Sling2

Home or Last Project Picture

Apr 15, 2024     Filler - (1.5 hours) Category: Wings
Finished sanding off excess filler from rivet heads - top right wing
 
Apr 14, 2024     Filler - (1.2 hours) Category: Wings
Sand off excess filler from rivet heads - top right wing
 
Apr 13, 2024     Filler - (1.0 hour) Category: Wings
Sand off excess filler from rivet heads - top of right wing
 
Apr 12, 2024     Filler - (6.1 hours) Category: Wings
After delay for vacation trip: Filled all rivet heads on top of both wings
 
Mar 11, 2024     Aileron - (1.1 hours)       Category: Wings
Sanded off excess filler from right aileron rivet heads. Aileron complete


 
Mar 09, 2024     Aileron - (1.0 hour) Category: Wings
Filled rivet heads of right aileron
 
Mar 02, 2024     Ailerons - (2.1 hours) Category: Wings
Finished riveting right aileron assembly. Removed and realigned left aileron hinge z-bracket. Reinstalled.
 
Feb 29, 2024     Aileron - (0.9 hour) Category: Wings
Riveting right aileron skin on ribs
 
Feb 28, 2024     Aileron - (1.0 hour)       Category: Wings
Cleco'd right aileron skin to ribs. Ready to rivet together


 
Feb 27, 2024     Aileron - (0.8 hour)       Category: Wings
Adjusted Z-bracket (hinge) in order to align attachment bolt holes. Completed assembly of ribs.


 