Project: VelocityXLRG   -  
            Last 30 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Patrick Mayworm   -  
Project:   Velocity - XL/RG   -   VIEW REPORTS
Total Hours:1417
Total Flight Time:
Start/Last Date:Jul 28, 2001 - No Finish Date
Engine:Continental IO 550N
Propeller:Catto
Panel:Garmin
 
Friendly URL: https://eaabuilderslog.org?s=VelocityXLRG

Home or Last Project Picture

Jan 28, 2021     Nose Gear       Category: Fuselage
Test nose gear actuator, nose gear door hinges and cover for nose


 
Jan 27, 2021     actuator       Category: Fuselage
Remake the actuator connection bracket


 
Jan 26, 2021     Actuator       Category: Fuselage
Continue fitting and connecting actuator to main gear cables


 
Jan 25, 2021     Actuator       Category: Fuselage
Connect actuator to main gear cables, build up nose gear door hinges


 
 
Jan 15, 2021     Misc items       Category: Fuselage
Fresh air vent installation, flanges for main gear openings at fuselage, glass actuator brackets and micro wing tips on canard


 
Jan 15, 2021     Close main gear opening, storage       Category: Fuselage
Continue to glass main gear opening, create hinge for storage in door and glass actuator support bracket


 
Jan 12, 2021     Closing main gear opening, fabricate strake door       Category: Fuselage
Closing main gear opening, fabricate the door to the storage area in the strake on the door


 
Dec 18, 2020     Sanding & Actuators - (7 hours)       Category: Fuselage
Built doors and latches for storage compartment in doors; fabricated support flanges in keel access panel and continued to fabricate actuator support structure in keel


 
Dec 17, 2020     Canard Wing Tips, Actuator - (7 hours)       Category: Canard
Glassed other side of wing tips on the canard where I made the cut to reset them; glued and glassed in place the base plate to attach the actuator supports; micro the areas around the hinges and door compartment


 
Dec 17, 2020     Canard Wing Tips, Actuator - (7 hours)       Category: Canard
Glassed other side of wing tips on the canard where I made the cut to reset them; glued and glassed in place the base plate to attach the actuator supports; micro the areas around the hinges and door compartment


 
Dec 16, 2020     Glassed Spots on Canard - (7 hours)       Category: Canard
Cut wing tips and reset them so the trailing edge fit when elevator is in neutral position; filled holes around hinges in canard


 
Dec 15, 2020     Reset Elevator Hinges - (8 hours)       Category: Canard
Reset the hinges in the canard for the elevators and positioned the nose gear actuator


 
Dec 13, 2020     Actuators, Doors - (6 hours)       Category: Fuselage
Cut opening in the keel to hold the brace for the two actuators; prepared the storage space in the doors and attached the struts to the doors


 
Dec 12, 2020     Reset Elevator - (7 hours)       Category: Canard
Removed hinges from the canard and prepared to reset them; fabricated support for actuators; prepared hardware to attach door struts


 
Dec 11, 2020     Nose Gear Actuator and Landing Light - (7 hours)       Category: Nose Gear
Continued to fabricate the nose gear retract system and worked on the co-pilot side landing light


 
Dec 10, 2020     Nose Gear Actuator and Landing Light - (7 hours)       Category: Nose Gear
Began to pull together parts for the nose gear actuator; cut the leading edge of the wing for co-pilot side landing light


 
Dec 09, 2020     Retract System & Landing Lights - (7 hours)       Category: Main Gear
Prepared to install Linak actuators for landing gears, prepared to cut out wing hole for landing lights


 
Dec 06, 2020     Canard & Elevators - (5 hours)       Category: Canard
Sanded and filled elevator ends, canard wing tips and winglets


 
Dec 05, 2020     Canard & Wings - (6 hours)       Category: Canard
Glassed and micro filled elevator ends, canard wing tips and winglets at rudder


 
Dec 02, 2020     Door Gas Struts - (7 hours)       Category: Canard
Moved plane to new hangar; replaced hard point for door struts


 
Nov 20, 2020     Sanding and micro work - (7 hours)       Category: Fuselage
Micro work and sanding doghouse, wings and cowling


 
Nov 19, 2020     Sanding and micro work - (6 hours)       Category: Fuselage
Sanding and micro work on wings and cowling, repair doors


 
Nov 18, 2020     Cowling fit and micro - (7 hours)       Category: Fuselage
More work fitting the back of the cowling. as well as sanding area where cowling meets the wing; more filling and sanding the wing/strake area and doghouse as well.


 
Nov 17, 2020     Completed glassing cowling - (7 hours)       Category: Fuselage
Continued work on cowling building up the edges where the cowling meets the wing; more sanding and micro on doghouse and elevators


 
Nov 16, 2020     Fit cowling - (6 hours)       Category: Fuselage
Used aluminum tape to build edge with micro where cowling meets the wing; began to repair where the upper winglet on co-pilot side was damaged years ago when shipping


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.