Project:   Vans - RV-6A   -   VIEW REPORTS
Total Hours:123.5
Total Flight Time:
Start/Last Date:Mar 01, 2019 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=cnordquist

Home or Last Project Picture

Jan 03, 2020     floors, rudder pedals, static - (19 hours) Category: Fuselage
Continued work on floors, installing nutplates, fitting rudder pedals, wiring for flaps, tubing for static lines.
 
Dec 11, 2019     electric flap motor cover - (2.5 hours) Category: Fuselage
With Larry Zahn and Rob Lennox continued enclosing the flap motor mechanism, made cardboard patterns for sides and cut the .016 parts for sides. Installed two wood spacer blocks for spars that Rob made.
 
May 25, 2019     skinning begins - (62 hours) Category: Fuselage
Working with Anthony Pumphery began skinning the aft tail after installing structural pieces in the fuselage.
 
May 05, 2019     Longerons - (40 hours) Category: Fuselage
Re-bent longerons and adjusted discrepancies in the bulkheads on the jig with the help of Larry Zahn. Assembled brake and rudder pedals and sticks.
 
Mar 23, 2019     moved to Riverside County       Category: history
Trucked the kit from Coto de Casa in Orange County to home in Jurupa Valley with the help of Andy Nordquist, Mark Beattie, Austin Jones, Ian Ballard and Demetrius. Moved the completed wings and engine mount and roll bar and canopy frame to Flabob Airport (KRIR).


 
Mar 14, 2019     transfer to Nordquist Category: history
Sale agreement this day from Robert McAnulla to Conrad Nordquist for RV-6A kit #25432
 
Oct 12, 2013     Bob McAnulla Category: history
Van''s license agreement shows Robert McAnulla authorized to continue use of the plans for the RV-6A
 
Nov 16, 2002     wings & tail feathers complete Category: history
Last entry in Ed Dillon photo log shows wings completed, empenage completed.
 
Nov 28, 1998     Horizontal Category: history
Photo log of Ed Dillon shows horizontal stabilizer skeleton. Construction begun 9/28, completed 11/28/98
 
Jul 30, 1998     earliest records on this kit       Category: history
Invoice this date from Van''s to Ed Dillon, Temecula CA: Empenage kit, later invoice from Phlogiston Products for spar assembly.
Invoice from Van''s dated 9/22/98 for Wing kit, RV6-A fuselage, slide kit, finish kit and other add-ons for $13,992.


 