EAA Builders Log Website
EMail address:
Password:
- Lost my password
close
EAA Builders Log
(An EAA website).
Help
Contact Us
About
Sign Up
Login
Project:
wstoelting
-
Last 10 Project Activities / Entries :
(Please mouse-over any icon to get a description of that function).
Categories
Show All Entries
- (391)
Research
- (3)
Workshop
- (3)
Empennage
Fuselage
- (73)
Firewall
- (1)
Tail Feathers
- (5)
Wings
- (133)
Controls
- (6)
Avionics
- (7)
Lighting
- (2)
Instrument Panel
- (13)
Landing Gear
- (19)
Engine
- (41)
Propeller
- (5)
Fuel System
- (30)
Interior Finish
- (8)
Paint / Decals
- (22)
Inspection
- (2)
Tools
- (18)
Builder Name:
Wade Stoelting
-
Project:
Just - Highlander
-
VIEW REPORTS
Total Hours:
781.4
Total Flight Time:
Total Expense:
$68417.69
Start/Last Date:
Oct 09, 2019 - No Finish Date
Engine:
Yamaha Apex
Friendly URL:
https://eaabuilderslog.org?s=wstoelting
Home or Last Project Picture
Feb 26, 2024
Mounted Propeller
- (1 hour)
Category: Propeller
Installed propeller. Used hardware torque info from Kyiv Propeller USA website 18 ft-lbs. Set ground adjustable pitch with gauge provided by NR Prop. Installed propeller without nose cone backing plate for initial engine runups and then will retorque the pitch adjustment screws. Then remove hub to install backing plate.
20240226_160138.jpg
Feb 05, 2024
Vinyl Wrap Kickpanels and Turtledeck
- (4 hours)
Category: Fuselage
Ordered vinyl wrap for kickpanels and turtle deck from Amazon. The orange color and gloss may not match perfectly with airplane paint but adequate. ViVid brand. I am trying to minimize further painting effort due to current Temps, and no more paint booth.
20240206_151832.jpg
20240206_151933.jpg
20240206_152121.jpg
Jan 24, 2024
Installed Wings
- (4 hours)
Category: Wings
Moved plane and wings from garage to hangar. Installed wings after arriving at hangar. Still have a few hardware installation fixes but it sure looks like a plane now.
20240120_100243.jpg
20240124_164450.jpg
Jan 02, 2024
Electrical Supplies
Category: Instrument Panel
PIDG ring connectors, toggle switches, 20ga wire, 22ga wire, 2 conductor and 3 Co ductor shielded wire...
20240102_180754.jpg
Jan 01, 2024
Windshield
- (6 hours)
Category: Fuselage
Rough cutout the windshield. This is the second attempt as I undercut the first one. Afterwards, made further precision trimming and drilled mounting holes, sanded smooth edges.
20240101_090941.jpg
20240101_110002.jpg
Dec 26, 2023
Engine Cowling
- (9 hours)
Category: Fuselage
Fiberglassed inner lower Radiator ducting. Shortened up scoop inlet, clecoed in place, checked fit on airplane, then used epoxy to secure. Next up is finishing with filler then primer.
20231224_064407.jpg
20231225_053110.jpg
20231229_072038.jpg
Dec 15, 2023
Start your engine!
Category: Engine
Yahoo! Starting after 3 and half years. Video would not save. Saved to YouTube.
https://youtu.be/RITszWDpqu4?feature=shared
VideoCapture_20231215-094748.jpg
Dec 14, 2023
Battery Charger
Category: Tools
The Lithium Phospate battery requires a charger other than the traditional lead acid type.
20231214_155337.jpg
Dec 11, 2023
Panel Finishing
- (4 hours)
Category: Instrument Panel
Vinyl wrapped the dash, Dymo labeling. Fit radio chassis, EIS unit, cut holes for vents.
20231211_195331.jpg
20231210_140958.jpg
20231210_140946.jpg
Dec 03, 2023
Spider of Wires
- (3 hours)
Category: Instrument Panel
Continue to make Wire connections and route to panel. These wires are for Master, auto tune, ignition, fuel pumps, start, landing and heater. Still need to route Nav/Strobe and interior light.