Project: JSPatrol   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Jacob Carmer   -  
Project:   Bearhawk - Patrol   -   VIEW REPORTS
Total Hours:227.2
Total Flight Time:
Start/Last Date:Jun 27, 2020 - No Finish Date
Engine:O-360
Panel:GRT Avionics
 
Friendly URL: https://eaabuilderslog.org?s=JSPatrol

Home or Last Project Picture

Welded the right elevator mount bushings into the right stabilizer. Started fabricating the trim tabs and lower horizontal stabilizer strut mount and tack welded it.


 
Sep 11, 2020     Finished fabricating and tack welding the right elevator       Category: Empennage
Finished fabricating and tack welding the right elevator.


 
Sep 10, 2020     Made hinges for right elevator & match drilled holes for left elevator - (1.5 hours)       Category: Empennage
Made the hinges for the right elevator and match drilled the holes for the left elevator


 
Sep 09, 2020     Fabricated and tack welded the first elevator - (4 hours)       Category: Empennage
Fabricated and tack welded the first elevator


 
Added cross supports in the vertical and horizontal stabilizers and laid out the lines for building the elevators.


 
Sep 07, 2020     Tack welded together the vertical stabilizer - (4 hours)       Category: Empennage
Tack welded together the vertical stabilizer! It's looking more and more like an airplane


 
Sep 06, 2020     Finished making the horizontal stabilizer mounts - (2 hours)       Category: Empennage
Finished making the horizontal stabilizer mounts


 
Sep 04, 2020     Finished welding send horizontal stab and fabricated mounting brackets - (4 hours)       Category: Empennage
Finished welding the second horizontal stabilizer. Started fabricating the mounting brackets for the horizontal stabilizers. Hung them, temporarily, just to see how they will look.


 
Sep 03, 2020     Fabricated second of the horizontal stabilizers and finished welding of first - (4 hours)       Category: Empennage
Finish welding on the first horizontal stabilizer and tack welded the second horizontal stabilizer together. Compared two stabilizers to make sure they are identical.


 
Sep 02, 2020     Fabricated one of the horizontal stabilizers - (4 hours)       Category: Empennage
Fabricated one of the horizontal stabilizers


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.