Builder Name:Benjamin Bott   -  
Project:   Vans - RV-14A   -   VIEW REPORTS
Total Hours:1416
Total Flight Time:
Total Expense:$193980.36
Start/Last Date:Jul 06, 2020 - No Finish Date
Engine:IO-390
Propeller:Hartzel
Panel:Dynon
 
Friendly URL: https://eaabuilderslog.org?s=

Home or Last Project Picture

Aug 16, 2023     Complete Fairings - (10 hours)       Category: Landing Gear
Aircraft completed. Fairings finished and new weight and balance accomplishef


 
Aug 10, 2023     Fairings - (15 hours)       Category: Landing Gear


 
Jul 29, 2023     Wheel Pants and Fairings - (10 hours) Category: Landing Gear
 
Jul 23, 2023     Nose Wheel Pant - (6 hours)       Category: Landing Gear


 
Jul 22, 2023     Nose Wheel Psnts - (6 hours)       Category: Landing Gear


 
Jul 08, 2023     Wheel Pant - (6 hours) Category: Landing Gear
Nose Wheel fit.
 
Jul 02, 2023     Wheel Pants - (4 hours)       Category: Landing Gear
Finished cutting and fitting and fit main wheel pants.


 
May 17, 2023     Wheel Pants - (4 hours)       Category: Landing Gear


 
May 15, 2023     Wheel Pants - (2 hours) Category: Landing Gear
 
May 09, 2023     Airworthiness Inspection       Category: Inspection
Passed AW Inspection. Daniel Bonita and Fred McMillian


 
Mar 10, 2023     Paint Cowl and Spinner - (7 hours)       Category: Paint / Decals
Applied white paint to prop spinner and cowling. Taped paint line in prep for green paint.


 
Mar 08, 2023     Prep & Prime Cowling - (6 hours)       Category: Paint / Decals
Completed fit of upper and lower cowling. Prepped and primed cowling and spinner


 
Feb 20, 2023     Engine Run 2 - (2 hours)       Category: Engine
Performed taxi testing and high power engine run after changing g out alternator field switch. Alternator now works. Prop RPM was limited at 2700 and MP was noted to be approx 28”.


 
Feb 11, 2023     Top Cowling - (6 hours)       Category: Engine
Continued work on inlet scoops on top cowling. Installed placards and data plate.


 
Feb 10, 2023     Engine Run/Pitot Static - (6 hours)       Category: Fuselage
Engine first start. No leaks. RPM double. Made adjustment in Dynon. Alternator field not closing. Had IFR pitot static system check and had airspeed checked for accuracy.


 
Feb 07, 2023     Weight and Balance - (2 hours) Category: Fuselage
Installed all panels on aircraft. Drained fuel tanks. Performed weight and balance with without wheel pants and fairings as aircraft will be initially test flown this way. The results are as noted.

Empty Weight: 1281
Moment: 102,944
CG: 80.6
 
Feb 06, 2023     Cowling - (8 hours)       Category: Engine
Installed heat Shield on cowling. Drilled bottom screw holes and installed nut plates on support bracket. Will drain fuel for weight and balance. All items installed on aircraft. Installed crotch straps on harnesses.


 
Feb 05, 2023     Weight & Balance Prep - (8 hours) Category: Fuselage
Installed all interior panel in prep for weight and balance. Cleaned up several misc items.
 
Jan 21, 2023     Cowling - (10 hours)       Category: Engine
Finished fit of cowl. Installed all hinges. Began install of top cowl fairing. Front intake of cowling requires minor fill around the seams.


 
Jan 19, 2023     Cowling - (8 hours)       Category: Engine
Installed hinges after coating inside of cowling fiberglass with resin to protect from oil penetration. Installed rear baffle seals. Will install remainder after fitting and installing cowling.


 
Jan 18, 2023     Fit Engine Cowling - (7 hours)       Category: Engine
Continued fit of cowling. Attached horizontal hinges.


 
Jan 17, 2023     Fit Lower Cowling - (8 hours)       Category: Engine
Continued sanding for proper fit.


 
Jan 15, 2023     Fit Lower Cowling - (8 hours)       Category: Engine
Fit Lower Cowling and repaired over cut oil access door corner tabs.


 
Jan 07, 2023     Upper Cowling - (6 hours)       Category: Engine
Continued upper fit of cowling. Began to drill and cleco. Checked for proper clearance between spinner back plate.


 
Jan 04, 2023     Cowling - (7 hours)       Category: Engine
Continued sanding for proper fit in cowling nose area.


 
Jan 02, 2023     Fit lower wing gap panels - (6 hours) Category: Wings
Bent lower fairing to fit bottom wing gap. Countersunk bottom nut plate holes to accept dimpled skin.
 
Dec 31, 2022     Upper Cowl and Lower Cowl Baffle Seals - (10 hours) Category: Paint / Decals
Finished upper cowl interior scoops. Drilled and fit the lower cowl rubber seals.
 
Dec 27, 2022     Fuel Flow Test - (2 hours)       Category: Wings
Performed fuel flow test of boost pump for left and right tanks. Measured FF corresponded to pumps rated unrestricted flow of 40 gph and was well above FAA recommended flow for engine HP. No debris noted from fuel system. Fuel also run thru engine pump and injectors to remove preservative oil prior to first start.


 
Dec 20, 2022     Fuel Tank Calibration - (6 hours)       Category: Wings
Added fuel to tanks for calibration and leak testing. Added in 2 gal increments until full. Started on left tank. Left full for several days to check for leaks. Then drained fuel to add to right tank for calibration. Ran fuel pump with restriction. Amperage and PSI were within limits. Flow check of both tanks to follow.


 
Dec 15, 2022     Avionics/Flight Controls - (8 hours) Category: Avionics
Replaced damaged flap position sensor. Calibrated flaps at -3, zero, 20 and 40 degrees. Tightened stick to wing aileron push rods. Swapped and depopulated some pins to allow flap POS12 and ADS B to work after consulting with AFS
 
Dec 13, 2022     Aileron Trim and Flight Controls - (5 hours) Category: Wings
Installed and calibrated aileron trim. Rigged ailerons and checked all control deflections within specified plans tolerances.
 
Dec 12, 2022     Flight Control Adjustments - (6 hours) Category: Wings
Adjusted rod end bearings and checked within tolerances.
 
Dec 11, 2022     Flight Controls and Avionics - (6 hours) Category: Avionics
 
Dec 09, 2022     Avionics/Misc - (12 hours)       Category: Avionics
Calibrated ADHRS heading. Programmed settings for Avidyne. Installed ailerons. Programmed flap setting. Flap sensor broken. Will need to order a new one. Called tech support for proper transponder settings.


 
Dec 07, 2022     Avionics/Misc - (8 hours) Category: Avionics
Configured avionics. Filed inside of right flap for fuselage clearance. Add 3m tape to top of trailing edge of wing in flap area to prevent chafing.
 
Dec 06, 2022     Avionics Power Up - (5 hours)       Category: Avionics
Powered up avionics for the first time. Updated software. Removed protective plastic from canopy.


 
Dec 03, 2022     Wing Install - (8 hours)       Category: Wings
Connected electrical. Installed flaps and left wing tip. Installed flap push rods. Adjusted flaps to Van's 7 degree reference position while in the up position.


 
Nov 27, 2022     Repaint Top of Wings - (4 hours)       Category: Paint / Decals
Sanded and refinished tops of wings. Added fuel placards to reflect useable fuel in each tank. 25 gal each.


 
Oct 15, 2022     Interior install, Prop Spinner - (8 hours)       Category: Engine
Installed leather interior from Flightline Interiors and finished nut plates on prop spinner.


 
Oct 13, 2022     Cowling Hinge Fit/Flight controls - (5 hours)       Category: Fuselage
Fit cowling hinges. Tightened up play in stick/elevator. Play was found ant rear push rod. Tightened and retorqued assembly. Installed placards.


 
Oct 11, 2022     Rudder - (8 hours)       Category: Fuselage
Painted and installed rudder. Connected wiring to tail light. Checked elevator up and down limits and rudder travel. Within Van's plans tolerances.


 
Oct 10, 2022     Elevators - (8 hours)       Category: Fuselage
Installed elevators after paint. Painted rudder. Installed cockpit panels and control sticks.


 
Oct 06, 2022     Canopy Install - (7 hours)       Category: Fuselage
Installed canopy gaskets and jettison handle connection. Front canopy harness wiring.


 
Oct 04, 2022     Final Assembly - (5 hours)       Category: Tail Feathers
Installed vertical and horizontal stabilizer. Installed canopy. Paint elevators and canopy


 
Oct 03, 2022     Avionics wiring - (12 hours)       Category: Avionics
Installed wiring to emags and tied up miscellanies wires from the EMS. Ran wires to the stall warning and fuel tanks. Painted tail feathers white undercoat.


 
Sep 17, 2022     Wiring - (12 hours)       Category: Avionics
Ran more EMS wires. Installed 60 amp alternator breaker and shunt in center console. Installed left and right avionics panels and connected harnesses.


 
Sep 10, 2022     Wiring - (7 hours)       Category: Engine
Installed CHT probes. Misc wiring. Safety wired alternator bolts after installing belt and tensioning it.


 
Sep 03, 2022     Propeller Installation - (2 hours)       Category: Engine
Installed Hartzell 74” CS Prop per manufacturer specs. Removed oil retention plug. Torqued bolts to required specs.


 
Sep 02, 2022     Heater Hoses/Propeller back plate - (6 hours)       Category: Engine
Finished installing heater hoses. Fabricated and mounted propeller spinner back plate and prepped for install.


 
Aug 27, 2022     Snorkel - (5 hours)       Category: Engine
Fit snorkel to fuel control and filter bracket.


 
Aug 02, 2022     Rear Engine Baffles - (6 hours)       Category: Engine
Installed rear baffles


 
Jul 26, 2022     Baffles - (7 hours)       Category: Engine
Began engine baffle assembly


 
Jul 24, 2022     Engine Cables - (7 hours) Category: Engine
Installed and adjusted prop throttle and mixture cables.
 
Jul 21, 2022     Cockpit Controls - (5 hours)       Category: Firewall
Installed alternate air cable attachments and heater control cables. Finished cowl flap cable adjustments.


 
Jul 19, 2022     Alternate Air, Cowl Flap, cabin Heat cables - (6 hours)       Category: Firewall


 
Jul 17, 2022     Prop Throttle Mixture Cables - (5 hours)       Category: Firewall
Installed all three cables along with cable bracket.


 
Jul 16, 2022     Engine hoses and Paint - (10 hours) Category: Firewall
 
Jul 09, 2022     Oil Cooler - (8 hours)       Category: Firewall


 
Jul 08, 2022     Alternator and Hoses - (8 hours)       Category: Firewall
Installed alternator and wiring and engine hoses.


 
Jul 06, 2022     Prop Governor and Hoses - (8 hours)       Category: Firewall
Installed prop governor and red cube and associated hoses.


 
Jul 04, 2022     Engine Installation - (6 hours)       Category: Firewall
Installed engine. Torqued all four mount bolts to Van's specifications.


 
Jul 03, 2022     Prep for engine hang - (6 hours)       Category: Fuselage
Installed fluid fittings on rear of engine.


 
Jul 02, 2022     Avionics - (6 hours)       Category: Fuselage
Wiring. Installed map box ribs for avionics.


 
Jun 18, 2022     Wiring - (8 hours)       Category: Fuselage
Cleaned up wiring in tunnel. Installed connections to Avidyne rack and ACM.


 
May 29, 2022     Antennas - (5 hours)       Category: Fuselage
Installed WAAS and two Com antennas and ELT.


 
May 22, 2022     Misc Items - (6 hours) Category: Fuselage
Modified lower cowling attach brackets for IO-390. Installed nut plates. Installed Dynon ACM. Worked on cowl flap and rerouted antenna wires.
 
May 12, 2022     Canopy Fairing - (5 hours)       Category: Fuselage
Sanded and applied microballoons then remanded and sprayed filler primer. Resandec.


 
May 01, 2022     Canopy Layup - (10 hours)       Category: Fuselage
CanopyFiberglass


 
Apr 14, 2022     Canopy and Rear Window - (8 hours) Category: Fuselage
Sanded fiberglass. Installed rear window permanently. Sealed with proseal. Installed rubber gasket on rear of canopy.
 
Apr 02, 2022     Canopy - (7 hours) Category: Fuselage
Riveted side skins and installed side hardware loosely. Prepped front portion of canopy for layup. Scuffed and taped area. Prepped rear canopy seal.
 
Mar 31, 2022     Canopy Prep - (10 hours)       Category: Fuselage
Installed defrost fans and canopy latch sensor. Mounted canopy in prep for fiberglass.


 
Mar 30, 2022     Canopy Interior Paint - (6 hours)       Category: Fuselage


 
Mar 29, 2022     Trim and fit canopy - (5 hours)       Category: Fuselage
Began fitting canopy.


 
Mar 27, 2022     Canopy FrMe - (4 hours)       Category: Fuselage
Continued fabrication by riveting forward structure.


 
Mar 25, 2022     Canopy Frame - (5 hours)       Category: Fuselage


 
Mar 23, 2022     L/R Canopy Rails - (4 hours)       Category: Fuselage
Fabricated left and right canopy rails


 
Mar 16, 2022     Firewall - (6 hours)       Category: Fuselage
Installed battery, master and starter relay and block for fuel and oil pressure sensors. Installed MAP SENSOR.


 
Mar 04, 2022     Rear Window - (3 hours) Category: Fuselage
Completed fit and drilling of rear window. Will install later.
 
Mar 03, 2022     Rear Window - (7 hours)       Category: Fuselage
Tapped 6-32 rear window at roll bar. Final drilled 27 and dimpled skin. Began counter sinking plexiglas for screws and dimpled skin.


 
Feb 02, 2022     Nose Gear and Canopy Locking Pins - (8 hours)       Category: Fuselage
Installed nose wheel. Worked on canopy jettison handle and canopy locking pins.


 