Project: RiverBear   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Robert Bickle   -  
Project:   Bearhawk - "B"   -   VIEW REPORTS
Total Hours:136.1
Total Flight Time:0.1
Total Expense:$66002.95
Start/Last Date:Dec 21, 2021 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=RiverBear

Home or Last Project Picture

Jan 07, 2024     Install Firewall and Engine Mount - (6 hours) Category: Firewall
 
Oct 25, 2023     Install Brakes - (4.0 hours) Category: Landing Gear
Finish drilling through steel plates and mount calipers and plates. Mount tires and nuts. Need to mark and drill for cotter keys in castle nuts.
 
Apr 06, 2023     Pilot floor - (1.0 hour)       Category: Interior Finish
Measure and cut floor around fuel selector.


 
Apr 06, 2023     Gasulator Install - (1 hour)       Category: Fuel System
Assembled Gasulator and fuel select marked and drilled holes. Installed bolts to attach to airframe.


 
Mar 30, 2023     Landing gear - mains - (4 hours)       Category: Landing Gear
The axels were the wrong size. The wheel bearings became jammed. Needed to unassemble wheels, replace one bearing, measure the bearings and the axel, have numerous discussions with wheel and axel suppliers, hand sand the axel to correct diameter, repack bearings, reassemble wheels, and fit wheels. Still need to drill for cotter pin.


 
Mar 30, 2023     Trim and install floor under pilot - (1.0 hour) Category: Interior Finish
Install floor under pilot seat. Includes modifications to panel for fit
 
Mar 14, 2023     Fabricate and dry fit elevator control horn - (1 hour)       Category: Controls


 