EAA Builders Log Website
EMail address:
Password:
- Lost my password
close
EAA Builders Log
(An EAA website).
Help
Contact Us
About
Sign Up
Login
Project:
jbrenneise
-
All Modified Project Activities / Entries :
(Please mouse-over any icon to get a description of that function).
Categories
Show All Entries
- (48)
Research
- (1)
Workshop
- (41)
Empennage
- (3)
Fuselage
- (1)
Firewall
Tail Feathers
Wings
- (1)
Controls
Avionics
Lighting
Instrument Panel
Landing Gear
Engine
Propeller
Fuel System
Interior Finish
Paint / Decals
Inspection
Tools
- (1)
Builder Name:
John Brenneise
-
Project:
Vans - RV-8A
-
VIEW REPORTS
Total Hours:
317.75
Total Flight Time:
Start/Last Date:
Jun 22, 2022 - No Finish Date
Friendly URL:
https://eaabuilderslog.org?s=jbrenneise
Home or Last Project Picture
Aug 22, 2023
Started new practice mule for dialing in countersink cages
- (0.75 hour)
Category: Tools
Adjusted depth of first cage.
IMG_20230822_194520139.jpg
Apr 27, 2023
Quick Build Wings for RV-8A Ordered from Van's
Category: Wings
Made a down payment on QB wings.
Apr 30, 2023
Practice Drilling Out Rivets
- (3 hours)
Category: Empennage
On 2023-04-23, Murlin brought over some rivet practice cards.
So, I secured the vise to a piece of 2x6 and made some wooden jaws to replace the steel ones.
I'm learning how to steer the drill bit to get it back onto center.
IMG_20230430_215906122_HDR[1].jpg
5883.jpeg
Apr 27, 2023
Quick Build Fuselage for RV-8A Ordered from Van's
Category: Fuselage
Down payment made on Fuselage.
Apr 12, 2023
Plywood for Lower Shelves Cut and Placed.
- (1.5 hours)
Category: Workshop
Plywood for shelves is ready to be secured with screws.
IMG_20230411_214858548_HDR[1].jpg
Apr 10, 2023
Nearly finished with work tables.
- (2.5 hours)
Category: Workshop
Except for 5 screws that attach the retractable casters, the plywood for the lower shelves, and the sliver protection molding, the work tables are complete.
IMG_20230410_203530592_HDR[1].jpg
Apr 09, 2023
Entering the Home Stretch on Work Table Construction
- (9 hours)
Category: Workshop
Sans the plywood for the lower shelves, Tables #1 through #3 are complete. Table #4 still need legs, doublers, and lower shelf frame.
IMG_20230409_183636077_HDR[1].jpg
Apr 02, 2023
First Work table nearly complete.
- (7 hours)
Category: Workshop
First work table is upright. 'still have to add molding and shelf.
IMG_20230403_181937818_HDR[1].jpg
IMG_20230403_215139347_HDR[1].jpg
Apr 04, 2023
Work Table #2 of 4 Top Frame ready for legs.
- (2.5 hours)
Category: Workshop
Built top frame and attached 3/4" plywood for Work Table #2
Mar 05, 2023
Workshop is Ready for Final Inspection.
- (4 hours)
Category: Workshop
Cut out sheetrock for attic access, and built mitered trim to hold sheetrock plug.
Installed sheetrock on door frame.
IMG_20230305_200952762[1].jpg
Mar 03, 2023
Garage buttoned up.
- (16 hours)
Category: Workshop
Built access hatch into attic from garage wall.
Installed sheetrock patch next to it.
Garage is now put back together.
IMG_20230303_184806212_HDR[1].jpg
Mar 01, 2023
East wall of garage re-rocked and door installed on garage sub-panel chase.
- (16 hours)
Category: Workshop
IMG_20230226_193033987_HDR.jpg
IMG_20230223_192944587.jpg
Feb 19, 2023
Door installed on panel chase.
- (6 hours)
Category: Workshop
Located hinges and hung door.
IMG_20230219_173502399[1].jpg
Feb 16, 2023
Lights, receptacles, and breakers installation complete.
Category: Workshop
All lights and receptacles now work.
Installed spare cabinet from kitchen remodel of 2021.
Installed curtain rod and curtains.
The little green pixels in the nearly all black image are the LEDs from the GFCI receptacles.
IMG_20230216_211722803_HDR[1].jpg
IMG_20230216_193832302[1].jpg
Feb 16, 2023
Lights and breakers installed.
- (8 hours)
Category: Workshop
Installed light fixtures and breakers.
Only two receptacle boxes to investigate.
All other receptacles work as intended.
IMG_20230213_201548622_HDR[1].jpg
IMG_20230213_201601441_HDR[1].jpg
Feb 09, 2023
Finished installing the last of 54 receptacles.
- (2 hours)
Category: Workshop
Next: Install the light fixtures and circuit breakers.
Feb 04, 2023
33 more receptacles ready for taping.
- (3 hours)
Category: Workshop
Cut, stripped, and attached jumper wires for 33 more receptacles, which are now ready to be taped prior to installation.
IMG_20230204_211511585[1].jpg
Jan 31, 2023
14 wall receptacles installed. 3 ceiling receptacles installed.
- (4 hours)
Category: Workshop
Installed 17 20 amp receptacles. 33 remaining.
IMG_20230131_202257127[1].jpg
IMG_20230131_202229254_HDR[1].jpg
Jan 29, 2023
Sheetrock taped and mudded
- (4 hours)
Category: Workshop
Finished taping and mudding the walls today.
Jan 24, 2023
Sheetrock hanging completed.
- (4 hours)
Category: Workshop
The last piece of sheetrock for the first (and possibly only) layer has been hung.
IMG_20230124_205928545_HDR[1].jpg
Jan 17, 2023
Nearly finished with hanging sheetrock.
- (26 hours)
Category: Workshop
Finished hanging sheetrock on east and south walls.
Only two more pieces to hang on west wall.
IMG_20230117_203420816[1].jpg
IMG_20230117_203409517[1].jpg
Jan 08, 2023
Wall sheetrock started.
- (10 hours)
Category: Workshop
Pulled rear speaker cables through conduit.
Cleaned debris from ceiling installation.
Hung four sheets of drywall.
Jan 04, 2023
Ceiling sheetrock is up.
Category: Workshop
Had contractor install sheetrock on ceiling.
IMG_20230104_183410679[1].jpg
IMG_20230104_183413265[1].jpg
IMG_20230104_183415151[1].jpg
IMG_20230104_183418533[1].jpg
IMG_20230104_183421366[1].jpg
IMG_20230104_183423465[1].jpg
IMG_20230104_183432060[1].jpg
IMG_20230104_183435327[1].jpg
IMG_20230104_183436841_TOP[1].jpg
Jan 02, 2023
Ready for ceiling sheetrock.
- (10 hours)
Category: Workshop
Completed heat pump installation and started heat pump test. DIY unit works as advertised.
Installed R-30 ceiling insulation.
Installed GPS antenna.
Installed aircraft comm. antenna.
Sep 29, 2022
Electrical Prerequisites in Garage Part I
- (40 hours)
Category: Workshop
Mounted new electrical sub-panel in garage to receive circuits from the two existing sub-panels to be consolidated therein.
Disconnected the first of the two existing sub-panels from main panel.
Connected newly installed sub-panel to the main panel.
Moved all circuits from the first of the two sub-panels into the new sub-panel.
Jan 01, 2023
'almost ready for ceiling sheetrock.
- (72 hours)
Category: Workshop
Installed conduit for internet connection.
Installed conduit for rear channel home theater speakers.
Poured concrete slab for heat pump compressor and mounted compressor on slab.
Made electrical connections for heat pump.
Installed refrigeration line set and extension line set ('had to drive to Modesto to get correct extension line set) above ceiling joists.
Mounted heat pump air handler for test prior to ceiling sheetrock installation.
Nov 10, 2022
Installed wiring for center line workstations.
- (1.5 hours)
Category: Workshop
Put up cable stackers and wiring between the electrical boxes that run the length of the workshop along the center line.
Oct 26, 2022
Electrical work in workshop Part I
- (8 hours)
Category: Workshop
Installed sub-panel in workshop and wired one receptacle.
No more stringing an extension cord across the yard!
Oct 09, 2022
Electrical Prerequisites in Garage Part V
- (5 hours)
Category: Workshop
Replaced second legacy sub-panel with junction box and spliced in the feeder cable to the workshop.
Oct 06, 2022
Electrical Prerequisites in Garage Part IV
- (3 hours)
Category: Workshop
Secured feeder cable for workshop to garage wall from back wall to junction box location.
Oct 04, 2022
Electrical Prerequisites in Garage Part III
- (3 hours)
Category: Workshop
Finished consolidation of prior two sub-panels. All circuits moved from second sub-panel into new sub-panel in garage.
Second sub-panel is now free to be moved to the workshop.
Oct 03, 2022
Electrical Prerequisites in Garage Part II
- (2.5 hours)
Category: Workshop
Moved three circuits from second panel to the consolidation panel.
Aug 31, 2022
Unboxing and Inventory Part Two
- (2.0 hours)
Category: Empennage
I finished the inventory of the Tail Empennage Kit. Only one rivet missing, and that was from the practice project. Kudos to Van's Aircraft for getting this essentially right the first time. See it all here:
https://youtu.be/sUtM1QGDFT4
Shotcut_00_00_12_312.jpg
Aug 28, 2022
Tail Empennage Kit Unboxing and Inventory Part One
- (1.5 hours)
Category: Empennage
Now that the roof, door, and windows of my workshop are installed, I went ahead and took inventory of the smaller of the two boxes that comprise my RV-8 tail empennage kit. See video here:
https://youtu.be/nvyFuNM84Gs
Shotcut_00_11_04_071.jpg
Aug 10, 2022
Door is on. Roof is on. 'still painting...
Category: Workshop
TuffShed returned after the building inspector came yesterday.
Next step: Install the window.
IMG_20220810_175311395_HDR[1].jpg
Jul 22, 2022
Roof sheeting completed.
Category: Workshop
Roof sheeting and walls ready for inspection.
IMG_20220722_173944506.jpg
Jul 21, 2022
Shell installation. Day 1.
Category: Workshop
TuffShed came today and installed, sans the roof, the shell of the building.
IMG_20220721_130651450_HDR.jpg
IMG_20220721_192431625.jpg
IMG_20220721_192957379_HDR.jpg
IMG_20220721_193316862_HDR.jpg
IMG_20220721_193321464_HDR.jpg
Jul 13, 2022
Excavated soil and debris transferred to dumpster.
Category: Workshop
After concrete contractor removed the excavated soil and concrete, I took the pressure washer to the pavers in front of the slab.
IMG_20220713_204830270[1].jpg
IMG_20220713_204852491[1].jpg
Jul 05, 2022
Forms have been removed.
Category: Workshop
Concrete is dry enough that the forms could be, and were, removed.
IMG_20220705_122256237_HDR.jpg
IMG_20220705_122729126_HDR.jpg
Jul 01, 2022
Concrete poured and waiting to cure.
Category: Workshop
Last bit of re-bar installed. Concrete poured and surface smoothed. Sun shelter collapsed and back in its valise.
IMG_20220701_084354567_HDR.jpg
IMG_20220701_084414576_HDR.jpg
IMG_20220701_121806880_HDR.jpg
IMG_20220701_121818715_HDR.jpg
IMG_20220701_121907378_HDR.jpg
IMG_20220701_152916427_HDR.jpg
IMG_20220701_152944704_HDR.jpg
Jun 30, 2022
Almost ready for concrete.
Category: Workshop
Compaction finished. Rebar installation in progress.
IMG_20220630_164951645.jpg
IMG_20220630_164920987.jpg
Jun 29, 2022
Forms nearly complete
Category: Workshop
More progress on concrete forms. Gravel is in and is mostly compacted to level it up with the old slab.
IMG_20220629_161607444.jpg
IMG_20220629_161525911.jpg
IMG_20220629_161603859.jpg
Jun 29, 2022
Hot Iron Aircraft Shop Channel Introduction
Category: Research
A short video explaining my YouTube channel.
https://youtu.be/9Fqxh8ibtDA
Jun 28, 2022
More progress on concrete prep and forms.
Category: Workshop
Forms are beginning to take shape. Gravel brought to site.
IMG_20220628_155922114[1].jpg
IMG_20220628_155959673[1].jpg
Jun 27, 2022
Forms Begun.
Category: Workshop
More excavation. Construction of concrete forms begun.
IMG_20220627_181740785_HDR[1].jpg
IMG_20220627_181805366_HDR[1].jpg
IMG_20220627_181831563_HDR[1].jpg
IMG_20220627_181849630_HDR[1].jpg
Jun 24, 2022
Excavation for footers
Category: Workshop
Concrete prep continues.
IMG_20220624_201304676_HDR.jpg
IMG_20220624_201321076.jpg
IMG_20220624_201420426.jpg
IMG_20220624_201434434.jpg
Jun 23, 2022
Site prep for expanded concrete slab
Category: Workshop
Our concrete contractor's crew has been busy preparing the site for the expanded slab.
IMG_20220623_143037374_HDR.jpg
IMG_20220623_143058696_HDR.jpg
IMG_20220623_143102546_HDR.jpg
Jun 22, 2022
Demolition of old shed (to be replaced with new office/workshop).
- (40 hours)
Category: Workshop
My wife and I demolished our old shed (it was rotting away and wasn't large enough, nor was it climate controlled).
IMG_20220617_093749263_HDR.jpg
IMG_20220617_093807936_HDR.jpg
IMG_20220617_093818881_HDR.jpg
IMG_20220620_093452_01.jpg
IMG_20220620_110303_01.jpg
IMG_20220620_131009_01.jpg
IMG_20220620_180629416.jpg
IMG_20220620_200129693.jpg
IMG_20220621_195514_01.jpg
NOTE: This information is strictly used for the EAA Builders Log project within the
EAA organization
.
-
Policy
-
© Copyright 2024 Brevard Web Pro, Inc.