Project: Firefly   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Scott Henderson   -  
Project:   Firefly   -   VIEW REPORTS
Total Hours:36
Total Flight Time:
Total Expense:N/A
Start/Last Date:Mar 09, 2023 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=Firefly

Home or Last Project Picture

Dec 02, 2023     Rudder Covering - (5 hours)       Category: Tail Feathers
Bryce and Scott took a run at covering the rudder—poly fiber and lightweight fabric. Curved top surface proved challenging. Also learned about reinforcing panels around connect points. Tightened at 320 deg. Pretty satisfied but not perfect by any stretch.


 
Dec 02, 2023     Ailerons complete—structure - (5 hours)       Category: Wings
Completed the modification to the ailerons, shortening chord length from 14 in to 11 in per Kolb recommendation. Tube bending and cutting plus shaping and riveting spars. Now ready for covering.


 
Oct 21, 2023     Vertical Stabilizer covering       Category: Tail Feathers
First part fabric covering


 
Oct 21, 2023     First part covered—vertical stabilizer       Category: Tail Feathers
We covered the vertical stabilizer using the poly fiber system. This is the first flight part after a couple workshops practicing. Bryce, Patrick, Jim, Dwayne and Scott doing the work.

Also got started on the aileron project to shorten the rib length from 14 in to 11 inches. Tube bending and rib shortening and fastener work.


 
May 19, 2023     A new engine for the Firefly       Category: Engine
We flew up to Arthur Dunn earlier this month and procured a Rotax 503 for the Firefly. Bigger than the baseline Rotax 447 but the reliability and added horsepower deemed a good trade.

Also calculated the fabric yardage (32 yards) so we can order fabric and chemicals to begin the covering job.


 
Apr 08, 2023     Tail feather hinge fitting - (2 hours) Category: Empennage
Today we had Jonathon, Brice, Kayne and Scott working rudder and elevator hinge fitting. Next step will be covering the rudder, horizontal stab, and elevators using Poly Fiber.

Also read ahead on aileron hinges which still need to be done
 
Mar 09, 2023     Firefly project first build day at KCOI - (8 hours)       Category: Research
Chapter 724 begins work on the Kolb Firefly project. Initial parts inventory, cleaning, and documentation review. Herb, Dwayne, Jonathan, Scott, Cane, and Tom working with help from Charlie


 
Mar 09, 2023     Firefly project first build day at KCOI - (8 hours) Category: Research
Chapter 724 begins work on the Kolb Firefly project. Initial parts inventory, cleaning, and documentation review. Herb, Dwayne, Jonathan, Scott, Cane, and Tom working with help from Charlie
 