Project: TerryS     -     Entry

Mar 30, 2021 6 Fuselage decks, elevator bell crank support, baggage bulkhead, seat belt anchors Category: Fuselage
Lots of stuff today- My AN426AD3-5 rivets came in today so I was able to finish the deck rivets, including the really hard to buck ones. I'm including a picture below of the 3 bucking bars that I had to use. It can be done!

Riveted the elevator bell crank support. The number escapes me right now Was it F-708? something like that. Anyway, one potential problem to look out for. The upper 4 rivets that are common to the cargo bulkhead need to be dimpled. I hadn't accomplished this yet. OOPs! fortunately, the two layers were both thin enough that I was able to dimple them as a stack with a hand squeezer. Came out okay.

Also laid out, the seat belt anchors. seems like it is a strange order but it was in teh plans to do it now so I just knocked them out.