Project: BearhawkZoo     -     Entry

Nov 12, 2020 2 Fuselage access covers Category: Fabric Cover
I finished fabricating, trimming, deburring, prepping, and priming the six access covers for the aft fuselage (one for each side of the forward stab tube, then an upper and lower on each side for the rear tube). I plan to cover these in the yellow Oratex just so they blend in as well as possible.

Following that, I began installing the rear heat box outlet under the floor, but realized that I fabricated it before installing the stringers, and now it interferes with the stringers. My backup plan is to just have the SCEET tube bend 90 deg to a flange screwed to the floor. This method will be lighter and a cleaner installation, but I will have some work to do filling in the existing hole in the floor.