1. Did some shop reorganization. Moved instrument panel to metal desk in preparation for building the Garmin interconnect harnesses. (1.2 hours, but not logged)
2. Began wire lacing of certain harnesses that are definitely complete, such as the ones from the Main fuse block.
3. Drilled a few more pass-through holes and added grommets in aft fuselage. Rerouted several wire runs. Finally got the transponder powers and grounds into place.
4. Installed the Skybolt quarter-turn fasteners in the access door in the aft baggage hat shelf.