Project: I-CAVS     -     Entry

Apr 16, 2022 2 OP 60 ADHARS Support Installation Category: Fuselage
Prepared a pre drilling installation plate checking dimension for the two GARMIN ADHARS GSU25. The two ADHARS will be installed vertically under the support with the connectors on the outer side and the air connection in central position.
Installation has 1�lerance for the yaw axis, while pitch/roll axis have a 30�lerance.

Pre installation of the ADHARS support to the central fuselage stiffener and to the F-1007 Bulkhead.