Nov 30, 2020 2 Worked on empennage and control surfaces Category: Empennage
Stabilator Team: Prepped the stabilator sub parts and skins for riveting together. We got the horns onto the stabilator assembly(riveted).
Tailcone Team: Focused on getting the interior ribs and skins ready for riveting (deburring, cleaning, etc.) together to make the actual tail cone.
Vertical Stabilizer Team: Got the caps on the vertical stabilizer and rudder to final size. The fiberglass caps were not the correct size and did not fit.
Programming/Management Team: Continued programming, creating functions and mostly repasting and repurposing existing code. This process is slightly faster and development is going easier. Reorganized the way this builder's log was updated to make it more readable and specific. Each team was asked what they were doing so this update could be more accurate.

No pictures were taken today.

No Pictures found for this entry

NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.