Project: KMYARV12     -     Entry

Apr 12, 2021 2 Worked on multiple parts Category: Fuselage
Fuselage (Rebecca Colwell): Today we accomplished putting more stuff on the ribs and dimpling. We had some issues on the angle of the dimpler. Sophie and Harsh cut a small angle part using a Dremel tool. The mentors helped them with cutting that.
Lighting (Holden Glass): Worked on making the plexy glass covers the lights on the wing.
Parts Prep (Damion Cherney): I had to make 2 more nutplates for the lighting section since Vans only gave 2 of the 4 nutplates needed. Making these parts from scratch is rough.
Mentors: There is 2 depths on the dimper, one size was 120* which we don't really need on the plane. We labeled it and put this die in quarantine. Instead of using a dremel we can use a little nibbler tool to eat small pieces of metal out.