Feb 21, 2022 9 Feb 14,15,20,21 Sessions Category: Workshop
Slow progress due to delay of Flap Actuator decision, canopy fairing, Super Bowl and ice storm. Wings reinstalled and torque arms/tubes drilled per plans after Van's indicated actuator is OK to proceed. They suggested travel of flaps likely to be minimally affected and performance effect nil. Maggie and Garrett used a Vix bit to center the holes on the torque tube and removed and completed the hole drilling. Richard and Willem worked on the oil line placement, learning to safety wire and attache Adel clamps. After numerous tries (learning!) they have accomplished their tasks. Addison, Brady and Adam continued to sand the canopy.
We also reviewed the new Service Bulletin re the tail skin cracking and will be ordering the parts to comply.