Mar 18, 2022 Reality check Category: Wings
Approximately 20 months into the project and total expenses are close to 4500.00.
Not captured in the pie chart is 262.00 for Stewart Systems. But there are a few non-project household expenses included.
The total does include the 12 foot cap strip material and its expensive shipping.
But still a few hundred dollars yet to spend on wing materials and tools.
Time spent on the project so far is roughly 1440 hours, based on 18 good months (72 weeks) of 20 hours per week.
I'm 68 years old and in good health. Colleen and I live on Social Security and retirement savings.
The expenses so far have been pretty well covered by our monthly budget.
Looks like the entire airframe can be constructed at this slow pace and rate of expense.