Met my goal of 21 hours for another week. Worked on the project every day. Had expected to work more than the actual 22.7 hours.
Continued working on wiring spreadsheet. I have now looked at and researched at least some of the connections for all the avionics. Spent time today wrapping up details related to CWS/Disc, TO/GA, and Pitot. Also changed fuel sensors to eliminate 2.2K pull-ups since a circuit without pull-ups is sufficient for a metal airplane per Garmin. Researched Glide Activate and decided to just use the G3X Touch interface instead of a dedicated Garmin button.
Researched methods to trim the FlyLEDs and found this helpful website:
https://www.youtube.com/watch?v=uBkPX_QhRI0The next major task on the spreadsheet is to decide on an electrical distribution architecture.