Project: MaggieMaeOfKS     -     Project Summary     - Optional PDF document function
Add entry descriptions           Project PDF with: -

Entry #CreatedTitleCategoryHours     Cost # Pictures
100     Mar 01, 2024 Moved into new shop Workshop 3 $0.00    0   
99     Jan 04, 2021 Intercom Avionics 1 $100.00    0   
98     Aug 01, 2020 Packed Up and Moved Out Workshop 4 $0.00    1   
97     Jul 07, 2020 Welding Controls 15 $400.00    3   
96     Jun 23, 2020 Cut control horns Controls 2 $183.00    1   
95     Jun 16, 2020 Drilled holes for cabane fittings Fuselage 3 $0.00    4   
94     Jun 16, 2020 Metal fittings Wings 2 $418.00    0   
93     Jun 15, 2020 Painted Fuel Tank Fuel System 2 $0.00    1   
92     Jun 14, 2020 Primed Fuel tank Fuel System 1 $0.00    1   
91     Jun 14, 2020 Tested Fuel Tank with Water Fuel System 4 $0.00    0   
90     Jun 10, 2020 Painted Inner Cabane Strut Fittings Fuselage .2 $0.00    0   
89     Jun 08, 2020 Bent Cabane Strut Fittings Fuselage 1 $0.00    2   
88     Jun 07, 2020 Painted Some Metal Fittings Fuselage 1 $0.00    0   
87     Jun 02, 2020 Attached Fuel Quantity Probe, Filler Cap, and Threaded Flanges Fuel System 4 $0.00    3   
86     Jun 01, 2020 Sealed Rivets Fuel System 4 $0.00    1   
85     Jun 01, 2020 Fuel Quantity Probe Fuel System 1 $189.00    1   
84     May 30, 2020 Bondo On Outside of Tank Fuel System 4 $0.00    1   
83     May 28, 2020 Assembled Fuel Tank Fuel System 6 $0.00    5   
82     May 25, 2020 Steel Fittings Fuselage 3 $0.00    3   
81     May 25, 2020 Finished Glove/Helmet Box Fuselage 1 $0.00    1   
80     May 19, 2020 Glove box Fuselage 2 $0.00    0   
79     May 19, 2020 Seat Harnesses Fuselage 4 $0.00    2   
78     May 18, 2020 Vent Tubes, Probe Flange Fuel System 1 $0.00    1   
77     May 17, 2020 Fuselage Side Art Paint / Decals 2 $0.00    1   
76     May 16, 2020 Fuel Probe Mount Fuel System 2 $9.75    2   
75     May 16, 2020 Turtle Deck, Front Seat Harness Attachments Fuselage 3 $10.00    1   
74     May 12, 2020 Turtle Deck, Seat Belts (5/10/20-5/12/20) Fuselage 24 $0.00    12   
73     May 05, 2020 Turtle Deck Fuselage 3 $0.00    1   
72     May 04, 2020 Made Gussets for Fuel Tank Sumps Fuel System 6 $0.00    1   
71     May 02, 2020 Riveted Top of Tank Fuel System 4 $0.00    1   
70     Apr 28, 2020 Steel Fittings, and More Fuel Tank Fuel System 5 $303.00    5   
69     Apr 27, 2020 Continued Fuel Tank Fuel System 5 $0.00    3   
68     Apr 26, 2020 Fuel Tank Fuel System 7 $0.00    2   
67     Apr 24, 2020 Trimmed Filler Strips Fuselage 5 $0.00    1   
66     Apr 23, 2020 Added Filler Strips Fuselage 4 $0.00    2   
65     Apr 22, 2020 Glued Gussets, Filler Strips Fuselage 6 $0.00    1   
64     Apr 21, 2020 Added Gussets Fuselage 6 $0.00    2   
63     Apr 20, 2020 Added Gussets Fuselage 3 $0.00    2   
62     Mar 10, 2020 Started Top of Fuel Tank Fuel System 3 $0.00    2   
61     Mar 02, 2020 Built Drain and Outlet Tubes Fuel System 5 $0.00    3   
60     Feb 26, 2020 Attached Flange Adapter to Fuel Filler Flange Fuel System 1 $0.00    2   
59     Feb 25, 2020 Turned Tubes And Fuel Cap Flange Adapter Fuel System 4 $0.00    1   
58     Feb 24, 2020 Match Drilled Bottom and Sides of Fuel Tank Fuel System 5 $0.00    4   
57     Feb 22, 2020 Marked Rivet Hole Locations Fuel System 1 $0.00    0   
56     Feb 19, 2020 Continued Fuel Tank Fuel System 4.5 $0.00    12   
55     Feb 18, 2020 Continued Fuel Tank Fuel System 4 $0.00    2   
54     Feb 17, 2020 Began Fuel Tank Construction Fuel System 5 $0.00    2   
53     Feb 11, 2020 More Fuel Tank Parts and Supplies Fuel System 1 $405.00    0   
52     Nov 27, 2019 More Parts Purchased Fuel System 1 $0.00    0   
51     Nov 21, 2019 More Fuel Tank Parts Fuel System 1 $100.54    1   
50     Nov 20, 2019 Fuel Tank Design Fuel System 6 $0.00    2   
49     Nov 14, 2019 Fuel Tank Parts Fuel System 1 $65.89    1   
48     Nov 12, 2019 Diagonal Braces Fuselage 2 $0.00    1   
47     Nov 06, 2019 Cut One Steel Part, Glued Six Cross Struts Fuselage 3 $0.00    2   
46     Nov 05, 2019 Steel Fittings Fuselage 5 $0.00    1   
45     Nov 03, 2019 Drilled Holes in Sheet for Engine and Wing Fittings Fuselage 2 $0.00    1   
44     Nov 01, 2019 Laid Out Sheet Metal Parts Fuselage 1 $32.25    1   
43     Oct 30, 2019 Glued Some Gussets Fuselage 1.5 $0.00    2   
42     Oct 29, 2019 Gussets Fuselage 6 $0.00    3   
41     Oct 23, 2019 Finished Seats Fuselage 6 $0.00    3   
40     Oct 22, 2019 Front Seat Fuselage 8 $0.00    1   
39     Oct 21, 2019 Rear Seat Fuselage 8 $0.00    2   
38     Oct 16, 2019 Built Seat Bottoms Fuselage 4 $0.00    1   
37     Oct 15, 2019 Girls Checked Out Floor Fit Inspection $0.00    1   
36     Oct 15, 2019 Trimmed Floor, Finished Tail Post Fuselage 5 $0.00    5   
35     Oct 14, 2019 Began Forming Tail Post, Glued Floor Fuselage 7 $0.00    3   
34     Oct 08, 2019 Glued First Cross Struts Fuselage 3 $0.00    1   
33     Oct 07, 2019 Set Up Fuselage Trusses Fuselage 2 $0.00    3   
32     Oct 02, 2019 Added Gussets to Insides of Trusses Fuselage 3 $0.00    3   
31     Oct 01, 2019 Added Wedges, Made Gussets Fuselage 6 $0.00    0   
30     Sep 24, 2019 Dismantled Truss Jig Fuselage 5 $0.00    1   
29     Sep 20, 2019 Zenith Homecoming & Corvair College #44 Research 20 $260.00    0   
28     Sep 18, 2019 Second Fuselage Truss Fuselage 2 $0.00    1   
27     Sep 17, 2019 Second Truss Fuselage 4 $0.00    1   
26     Sep 10, 2019 Second Side Truss Fuselage 1 $0.00    1   
25     Sep 09, 2019 Glued First Truss Fuselage 3 $0.00    1   
24     Aug 29, 2019 Bought Spruce Wood for Vert. Stab. & Rudder Engine 1 $139.09    0   
23     Aug 26, 2019 Built Fuselage Jig Fuselage 10 $0.00    1   
22     Aug 01, 2019 Moved Into Pleasant Valley Basement Workshop 6 $0.00    0   
21     Nov 15, 2018 Moved Out of Lawrence Hangar Workshop 8 $150.00    0   
20     Aug 04, 2018 Cut Struts and Braces Fuselage 4 $0.00    1   
19     May 01, 2018 Moved to Lawrence Workshop 8 $150.00    0   
18     Sep 29, 2017 Corvair College #40 Research 20 $350.00    0   
17     Jun 01, 2017 Bought Wood for Fuselage Fuselage 1 $1095.00    1   
16     May 01, 2017 Workbenches Workshop 2 $500.00    0   
15     Mar 05, 2017 Bought Distributor, Rear Oil Case, Other Parts Engine 1 $1151.35    0   
14     Mar 01, 2017 Bought Spruce Wood for Empennage Empennage 1 $363.40    0   
13     Mar 01, 2017 Bought Engine Mount Engine 1 $947.34    0   
12     Feb 24, 2017 Received Another Core Crankcase Engine 1 $0.00    0   
11     Feb 23, 2017 Continued Cleaning Engine Parts Engine 2 $0.00    0   
10     Feb 22, 2017 Continued Cleaning Engine Parts Engine 1 $0.00    0   
9     Feb 21, 2017 Continued Cleaning Engine Parts Engine $0.00    0   
8     Feb 18, 2017 Began Cleaning Engine Parts Engine 3 $0.00    0   
7     Feb 16, 2017 Continued Core Engine Disassembly Engine 5 $0.00    0   
6     Feb 15, 2017 Continued Core Engine Disassembly Engine 3 $0.00    0   
5     Feb 11, 2017 Continued Core Engine Disassembly Engine 3 $0.00    0   
4     Feb 04, 2017 Began Core Engine Disassembly Engine 6 $0.00    1   
3     Feb 01, 2017 Bought Plans from Pietenpol Family Research 1 $250.00    0   
2     Feb 01, 2017 Bought First Core Engine Engine 1 $360.00    1   
1     Jan 29, 2017 Decided to Build an Airplane Research 1 $0.00    1   
------------ -------------- -------------
Totals394.2    $7932.61    145   