Project: Les'BD-4     -     Project Summary     - Optional PDF document function
Add entry descriptions           Project PDF with: -

Entry #CreatedTitleCategoryHours # Pictures
44     Jan 21, 2024 Starting on wing ribs Wings 7 7   
43     Jan 02, 2024 Aileron support bracket and Bellcrank Controls 16 6   
42     Dec 04, 2023 Center tunnel and flap lever support Fuselage 4 6   
41     Oct 15, 2023 Controls and instrument panel Controls 8 3   
40     Aug 01, 2023 Virginia Patriot mod Empennage 6 4   
39     Jul 31, 2023 Completed horizontal stab Empennage 40 26   
38     Jun 28, 2023 Horizontal Stab work Empennage 16 10   
37     Jun 16, 2023 Aileron control cables fabricated Controls 16 17   
36     Jun 16, 2023 Rudder and control connection Tail Feathers 16 9   
35     May 15, 2023 Brief update Empennage 0   
34     Jan 05, 2023 Continued work on Vertical Stabilizer and Rudder Empennage 16 30   
33     Dec 16, 2022 Ongoing work on Rudder and Vertical Stabilizer Empennage 8 6   
32     Dec 09, 2022 Rudder time Empennage 8 5   
31     Nov 20, 2022 Final layout of Control column base Controls 8 5   
30     Nov 02, 2022 Control construction update Controls 40 1   
29     Jul 12, 2022 Aileron control cable routing Controls 4 6   
28     Jul 12, 2022 Horizontal Stabilizer Bracket Controls 16 9   
27     Jun 06, 2022 Main photo Tools 1   
26     Jun 06, 2022 Tig Welding! Tools 8 0   
25     May 02, 2022 Drawing control system routing Controls 2 1   
24     Mar 01, 2022 Control Yokes, brackets and brakes Interior Finish 20 7   
23     Dec 27, 2021 Seat supports, seat adjusters and boat seats. Interior Finish 24 0   
22     Nov 23, 2021 EIS screen creation Avionics 12 1   
21     Nov 23, 2021 More work on landing gear Landing Gear 6 6   
20     Sep 24, 2021 Starboard Landing Gear Landing Gear 4 5   
19     Jun 18, 2021 Back at it... Fuselage 4 3   
18     Jun 17, 2021 Look what I bought! Engine 0   
17     Feb 04, 2021 Keeping in touch.... Workshop 0   
16     Nov 25, 2020 Surgery, recovery and research Workshop 1 0   
15     Sep 01, 2020 Cleaning up Workshop 0   
14     Jun 18, 2020 Making Airplane Noises Interior Finish 8 4   
13     May 19, 2020 Seats Interior Finish 6 2   
12     Apr 18, 2020 Weekend Work Fuselage 1.5 2   
11     Apr 12, 2020 Working through the plans/assembly drawings Fuselage 8 4   
10     Mar 24, 2020 Completion of fuselage extension Fuselage 24 6   
9     Feb 25, 2020 Continuing with fuselage extension Fuselage 2 4   
8     Feb 22, 2020 Extending the fuselage Fuselage 2 2   
7     Feb 08, 2020 Beginning the cleanup Fuselage 2 3   
6     Jan 06, 2020 Making airplane noises Research 2   
5     Nov 07, 2019 More Wings Wings 2 0   
4     Oct 06, 2019 Cutting down Wing Panels to make Ribs Wings 2.0 3   
3     Sep 09, 2019 It's all mine! Research 1   
2     Sep 03, 2019 Saw horses! Workshop 2 4   
1     Aug 28, 2019 And so it begins..... Research 0 1   
------------ -------------
Totals369.5    212   





NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.