Project: u2drvr     -     Project Summary     - Optional PDF document function
Add entry descriptions           Project PDF with: -

Entry #CreatedTitleCategoryHours # Pictures
182     Apr 23, 2024 Complete Flight 6 0   
181     Mar 16, 2024 First Flight! Flight 3 3   
180     Mar 09, 2024 Pitot Static Instrument Panel 3 5   
179     Feb 29, 2024 Transponder Inspection 1 0   
178     Feb 28, 2024 Airworthiness Inspection 1 1   
177     Feb 27, 2024 Misc items Engine 6 0   
176     Feb 25, 2024 Filter Engine 4 0   
175     Feb 24, 2024 Engine run Engine 8 3   
174     Feb 23, 2024 Engine start attempt. Wings 7 1   
173     Feb 16, 2024 Flap position Wings 5 1   
172     Feb 14, 2024 Fuel & Brakes Inspection 8 10   
171     Feb 11, 2024 Fuel Flow and calibration Inspection 10 1   
170     Feb 08, 2024 Weight and Balance Inspection 6 2   
169     Feb 07, 2024 Complete! Inspection 8 9   
168     Feb 05, 2024 Complete Wings 9 2   
167     Feb 04, 2024 Wing Root Fairing Wings 6 4   
166     Feb 03, 2024 Fuel Lines Fuel System 7 7   
165     Feb 02, 2024 Flight Controls Wings 13 5   
164     Jan 19, 2024 POH Inspection 20 0   
163     Jan 12, 2024 Tug mods Landing Gear 2 3   
162     Jan 11, 2024 Wing install Wings 5 12   
161     Jan 09, 2024 Elevator final install Empennage 4 3   
160     Jan 07, 2024 SB-00043 Empennage 4 3   
159     Jan 07, 2024 Tail final assembly Empennage 8 5   
158     Jan 05, 2024 The big move Fuselage 2 11   
157     Dec 23, 2023 Punch List2 Interior Finish 10 3   
156     Dec 22, 2023 Punch List Fuselage 14 0   
155     Dec 20, 2023 Cowling Wrap Engine 18 4   
154     Dec 17, 2023 Upper Cowling Wrap Fuselage 8 7   
153     Dec 16, 2023 Upper intersection fairing Landing Gear 4   
152     Dec 09, 2023 Gear fairings Landing Gear 8 7   
151     Dec 02, 2023 Gear Leg Fairings Landing Gear 12 3   
150     Nov 30, 2023 Exhaust Engine 8 3   
149     Nov 28, 2023 Baffles Engine 12 9   
148     Nov 26, 2023 Gear leg fairings Landing Gear 6 3   
147     Nov 25, 2023 Cowling Engine 8 6   
146     Nov 22, 2023 Cowling Engine 21 27   
145     Nov 06, 2023 Misc Engine 3 7   
144     Nov 01, 2023 Completed wiring Engine 7 4   
143     Oct 31, 2023 Lots of stuff…mostly wiring Engine 16 9   
142     Oct 24, 2023 Prop install Propeller 12 15   
141     Oct 22, 2023 Yet more wiring! Engine 8 13   
140     Oct 17, 2023 Still more wiring Engine 8 17   
139     Oct 16, 2023 More wiring Engine 6 0   
138     Oct 15, 2023 Wiring Engine 7 9   
137     Oct 09, 2023 More wiring Engine 8 7   
136     Oct 08, 2023 More wireng Engine 6 5   
135     Oct 07, 2023 Plug wires Engine 6 4   
134     Oct 03, 2023 Baffles Engine 7 11   
133     Oct 02, 2023 Mounted! Engine 8 8   
132     Sep 29, 2023 Baffles Engine 4 3   
131     Sep 23, 2023 Baffles Engine 7 2   
130     Sep 22, 2023 wiring Engine 8 0   
129     Sep 21, 2023 more engine accessories Engine 8 7   
128     Sep 20, 2023 Engine components install Engine 8 8   
127     Sep 19, 2023 The engine finally arrived Engine 8 13   
126     Sep 05, 2023 Wrapped Wheel Pant Landing Gear 6 1   
125     Sep 02, 2023 Sunshade Fuselage 1 1   
124     Sep 01, 2023 Moved wings to hangar Wings 2 4   
123     Aug 31, 2023 Polished flaps Wings 10 6   
122     Aug 26, 2023 Polish Wings 6 3   
121     Aug 22, 2023 wiring canopy Fuselage 5 2   
120     Aug 20, 2023 Polished bottom of left wing Wings 6 2   
119     Aug 19, 2023 Polish Right Wing Wings 6 7   
118     Aug 18, 2023 Fiberglass done...on to polish Tail Feathers 40 21   
117     Aug 13, 2023 Rudder Empennage 8 6   
116     Aug 12, 2023 Sanding, filling, sanding, painting, more sanding, and wrapping Fuselage 19 12   
115     Aug 09, 2023 Rudder and Fairings Fuselage 6 7   
114     Aug 03, 2023 Sanding, Sanding, and More Sanding Fuselage 15 8   
113     Jul 24, 2023 Section 38 complete! Fuselage 6 3   
112     Jul 20, 2023 Canopy Installed Fuselage 11 2   
111     Jul 19, 2023 Canopy fairing Fuselage 4 3   
110     Jul 18, 2023 Sanding, sanding, and more sanding Fuselage 6 10   
109     Jul 15, 2023 Canopy Fairing Fuselage 12 16   
108     Jul 10, 2023 Canopy Fairing Fuselage 4 5   
107     Jul 06, 2023 canopy Fuselage 12 9   
106     Jul 01, 2023 Canopy Fuselage 6 4   
105     Jun 30, 2023 Gas Struts and tail faring Fuselage 2 6   
104     Jun 29, 2023 Canopy Fuselage 9 8   
103     Jun 28, 2023 Back Window Fuselage 12 11   
102     Jun 23, 2023 Heater hoses Firewall 4 2   
101     Jun 22, 2023 Back window Fuselage 3 4   
100     Jun 21, 2023 Canopy Latch Fuselage 5 4   
99     Jun 15, 2023 Completed Side Panels Interior Finish 6 2   
98     Jun 15, 2023 Side Panels Interior Finish 12 6   
97     Jun 05, 2023 Chocks Landing Gear 4 3   
96     Jun 04, 2023 Wheels Pants 2 Landing Gear 7 9   
95     Jun 03, 2023 Wheel Pants Landing Gear 14 18   
94     May 25, 2023 Fairing Empennage 5 9   
93     May 18, 2023 Misc firewall Firewall 6 5   
92     May 17, 2023 Fuel lines Fuselage 4 0   
91     May 15, 2023 Misc Fuselage 10 4   
90     May 12, 2023 elevator and brakes Landing Gear 9 4   
89     May 10, 2023 wing electrical Wings 7 8   
88     May 08, 2023 On the mains! Landing Gear 5 6   
87     May 07, 2023 Electrical Firewall 3 3   
86     May 03, 2023 Off the rotisserie Fuselage 10 8   
85     May 02, 2023 Misc Avionics 14 9   
84     Apr 26, 2023 Cowl Flap + Fuselage 15 5   
83     Apr 18, 2023 Interior Interior Finish 6 6   
82     Apr 05, 2023 More polishing Fuselage 6 4   
81     Apr 04, 2023 Polish, Polish, Polish Fuselage 8 9   
80     Apr 03, 2023 Misc Fuselage 3 3   
79     Mar 30, 2023 polish Fuselage 8 3   
78     Mar 28, 2023 Cables Fuselage 4 7   
77     Mar 22, 2023 more wiring Fuselage 10 0   
76     Mar 15, 2023 Avionics Fuselage 4 5   
75     Mar 14, 2023 Backup O2, Throttle Bracket Fuselage 5 5   
74     Mar 13, 2023 Oxygen System Fuselage 4 2   
73     Mar 07, 2023 More wiring Fuselage 5 6   
72     Mar 06, 2023 Wiring Fuselage 15 8   
71     Mar 01, 2023 Panel Fuselage 20 6   
70     Feb 16, 2023 Canopy Frame Fuselage 10 2   
69     Feb 13, 2023 Canopy Frame Fuselage 6 5   
68     Feb 07, 2023 Fuel system Fuselage 12 9   
67     Feb 02, 2023 Console Fuselage 8 8   
66     Jan 29, 2023 Throttle Quadrant Fuselage 2 4   
65     Jan 27, 2023 Seats Fuselage 5 3   
64     Jan 26, 2023 Interior finish Fuselage 8 6   
63     Jan 23, 2023 Polish and assemble wheels Landing Gear 24 6   
62     Oct 11, 2022 Complete! Fuselage 6 8   
61     Oct 10, 2022 Roll Over Structure Fuselage 8 4   
60     Oct 05, 2022 Rudder pedals and flaps Fuselage 6 5   
59     Oct 04, 2022 Rudder pedals Fuselage 9 1   
58     Oct 03, 2022 Baggage Floor and Flap Motor Fuselage 12 6   
57     Sep 26, 2022 Paint and push rods Fuselage 8 7   
56     Sep 21, 2022 Elevator Bell Crank Fuselage 4 4   
55     Sep 20, 2022 Paint Fuselage 4 3   
54     Sep 19, 2022 Masking Fuselage 4 2   
53     Sep 13, 2022 Fuel tanks Wings 6 0   
52     Sep 11, 2022 Fuel tanks & stick Wings 4 11   
51     Sep 10, 2022 Wingtip Wings 15 13   
50     Sep 02, 2022 Left wingtip Wings 8 10   
49     Sep 01, 2022 Wingtip Wings 4 8   
48     Aug 24, 2022 Lower wing skins, Wingtips, FlyLEDs. Wings 16 9   
47     Aug 10, 2022 Aileron trim, Wing skins Wings 4 4   
46     Aug 08, 2022 Aileron rigging and trim Wings 18 21   
45     Jul 22, 2022 Lots of stuff Wings 60 30   
44     Jul 08, 2022 Wiring Wings 8 2   
43     Jul 07, 2022 Fuselage attach Fuselage 15 10   
42     Jul 02, 2022 Fuselage join, access panels Fuselage 11 9   
41     Jul 01, 2022 Jumping around Wings 14 10   
40     Jun 28, 2022 Stall warning & access panel Wings 3   
39     Jun 27, 2022 Fuel Sender, Aileron & Flap gap seals Wings 9 7   
38     Jun 27, 2022 QB Wings, Rudder Pedals Wings 10 6   
37     Jun 03, 2022 Rudder Bottom Fairing Empennage 4 3   
36     Jun 02, 2022 Rotisserie Prep Empennage 6 5   
35     May 27, 2022 Fairings Empennage 6 5   
34     May 26, 2022 HS Rear Spar Empennage 9 3   
33     May 23, 2022 Quick Build Fuselage pickup Fuselage 3 2   
32     Mar 03, 2022 Update Empennage 0 0   
31     Sep 14, 2021 Elevator Attach/adjust Empennage 8 9   
30     Aug 29, 2021 More aft fuselage riveting Empennage 5 3   
29     Aug 25, 2021 Top of Aft Fuselage Empennage 6 7   
28     Aug 24, 2021 Restart Empennage 7 3   
27     Jul 01, 2021 On Hold Empennage 0   
26     Feb 26, 2021 Aft fuselage Empennage 5 1   
25     Feb 24, 2021 Aft Fuselage Empennage 15 11   
24     Feb 21, 2021 Aft Fuselage Empennage 6 6   
23     Feb 12, 2021 Aft Fuselage Empennage 7 5   
22     Feb 11, 2021 Elevators/aft fuselage Empennage 16 10   
21     Jan 19, 2021 Elevators Empennage 30 12   
20     Dec 30, 2020 Elevator Empennage 8 7   
19     Dec 13, 2020 HS Complete Empennage 5 7   
18     Dec 11, 2020 Riveting HS Empennage 6 4   
17     Dec 10, 2020 HS almost done Empennage 10 8   
16     Dec 09, 2020 HS Empennage 3 2   
15     Dec 06, 2020 Rudder Complete Empennage 4 7   
14     Dec 05, 2020 Rudder almost done Empennage 5 8   
13     Dec 04, 2020 HS and Rudder (finally) Empennage 3 4   
12     Dec 01, 2020 HS Spars Empennage 4 8   
11     Nov 30, 2020 HS Spars Empennage 4 5   
10     Nov 29, 2020 Horizontal Stabilizer Empennage 4 4   
9     Nov 24, 2020 HS start Empennage 3 2   
8     Nov 21, 2020 Rudder Empennage 3 2   
7     Nov 19, 2020 Rudder Empennage 6 3   
6     Nov 18, 2020 Rudder day 3 Empennage 6 2   
5     Nov 17, 2020 Rudder Day 2 Empennage 4 4   
4     Nov 16, 2020 Finished VS...Started Rudder Empennage 6 3   
3     Nov 15, 2020 VS day 2 Empennage 10 8   
2     Nov 14, 2020 Vertical Stabilizer Empennage 9 4   
1     Nov 09, 2020 Inventory Empennage 3 2   
------------ -------------
Totals1458    1054   