Project: bhoward     -     Project Summary     - Optional PDF document function
Add entry descriptions           Project PDF with: -

Entry #CreatedTitleCategoryHours     Cost # Pictures
101     Mar 01, 2023 Fitted and drilled top skins Wings 4 $0.00    3   
100     Feb 18, 2023 Riveted left wing skeleton together Wings 10 $0.00    2   
99     Jan 26, 2023 Competed demurring Wings 4 $0.00    1   
98     Jan 22, 2023 Fitted and drilled wing ribs Wings 2 $0.00    0   
97     Jan 16, 2023 Prepare wing ribs Wings 24 $0.00    2   
96     Dec 16, 2022 Rivet rear spar together Wings $0.00    0   
95     Dec 11, 2022 Prepared the W-707G reinforcement fork Wings 4 $0.00    1   
94     Dec 10, 2022 Prepped rear spar Wings 12 $0.00    2   
93     Dec 04, 2022 Installed tie-down assemblly Wings 4 $0.00    0   
92     Dec 01, 2022 Fitted tie-down on the main spar Wings 8 $0.00    0   
91     Nov 30, 2022 Create W726 Wings 10 $0.00    1   
90     Nov 25, 2022 Spot prime and finish installing nut plates Wings $0.00    2   
89     Nov 24, 2022 Attach nut plates Wings 3 $0.00    0   
88     Nov 24, 2022 Finish counter sink per plans. Wings $0.00    0   
87     Nov 24, 2022 Counter sink for nut plates in main spar! Wings 3 $0.00    0   
86     Nov 15, 2022 Attach nut plates Wings 2 $0.00    0   
85     Nov 15, 2022 Finish counter sink per plans. Wings 3 $0.00    0   
84     Nov 12, 2022 Counter sink for nut plates in main spar! Wings 3 $0.00    0   
83     Nov 06, 2022 Identification of L/R main spars and inventory Wings 8 $0.00    1   
82     Oct 31, 2022 Received shipment of wing ... parts ... lots of parts! Wings 8 $9000.00    1   
81     Jul 03, 2022 Finished last rivets on the rudder Empennage 1 $0.00    3   
80     Jun 19, 2022 Actually riveted the leading edge Empennage 2 $0.00    0   
79     May 25, 2022 More rolling on the leading edge Empennage $0.00    0   
78     May 24, 2022 Rolled the leading edge Empennage 6 $0.00    0   
77     May 19, 2022 Riveting the trailing edge. Empennage 2 $0.00    0   
76     Apr 30, 2022 Record keeping Empennage 2 $0.00    7   
75     Apr 30, 2022 Set a few rivets Empennage 1 $0.00    1   
74     Apr 27, 2022 Riveted the counterbalance rib and skin Empennage 2 $0.00    0   
73     Apr 23, 2022 Finished the rudder skeleton. Empennage 2 $0.00    0   
72     Apr 20, 2022 Started building rudder skeleton Empennage 2 $0.00    0   
71     Apr 19, 2022 Rudder trailing edge prep Empennage 2 $0.00    0   
70     Apr 16, 2022 Started building the rudder Empennage 6 $0.00    0   
69     Mar 17, 2022 Installed stiffeners Empennage 3 $0.00    0   
68     Mar 16, 2022 Match drilled stiffeners… slowly Empennage 3 $0.00    0   
67     Mar 13, 2022 Finished stiffeners Empennage 2 $0.00    0   
66     Mar 12, 2022 Rudder stiffeners #2 Empennage 2 $0.00    0   
65     Mar 11, 2022 Trim cover plate Empennage 8 $0.00    1   
64     Mar 10, 2022 Removed flange on h stab Empennage 3 $0.00    1   
63     Mar 06, 2022 Installed rod end bearings Empennage 4 $0.00    0   
62     Mar 05, 2022 Rolled leading edge Empennage 5 $0.00    0   
61     Mar 03, 2022 Finished trim tab Empennage 1 $0.00    0   
60     Feb 26, 2022 Riveted the tab and installed Empennage 5 $0.00    1   
59     Feb 25, 2022 Finished prepping the tab Empennage 2 $0.00    0   
58     Feb 24, 2022 Drilled the tab spar Empennage 2 $0.00    0   
57     Feb 22, 2022 Continuing trim tab Empennage 2 $0.00    0   
56     Feb 21, 2022 Completed the trailing edge bend on the trim tab Empennage 1 $0.00    0   
55     Feb 13, 2022 Riveted the left elevator Empennage 5 $0.00    0   
54     Feb 10, 2022 Riveted the counter balance skin Empennage 1 $0.00    0   
53     Feb 08, 2022 Riveted the elevator skeleton Empennage 2 $0.00    0   
52     Feb 07, 2022 Bender the elevator tabs. Empennage 2 $0.00    0   
51     Feb 05, 2022 Preparing the trim spar Empennage 2 $0.00    0   
50     Feb 01, 2022 Deburred and dimpled the left elevator Empennage 4 $0.00    0   
49     Jan 28, 2022 Finished drilling the left elevator Empennage 5 $0.00    0   
48     Jan 27, 2022 Completed the right elevator Empennage 2 $0.00    1   
47     Jan 26, 2022 Riveted the skeleton together. Empennage 2 $0.00    0   
46     Jan 25, 2022 Finished left elevator prep Empennage 1 $0.00    0   
45     Jan 24, 2022 E709 prep- left elevator Empennage 1 $0.00    0   
44     Jan 21, 2022 Left elevator prep Empennage 2 $0.00    0   
43     Jan 20, 2022 Drilling counter balance for elevators Empennage 3 $0.00    0   
42     Jan 19, 2022 Working doublers and reinforcing plates Empennage 2 $0.00    0   
41     Jan 19, 2022 Bent trailing edge of the elevators - that was a “job” Empennage 3 $0.00    0   
40     Jan 17, 2022 Drilled and back riveted stiffeners Empennage 3 $0.00    0   
39     Jan 14, 2022 Finished stiffeners Empennage 2 $0.00    0   
38     Jan 13, 2022 Started elevator - began building the stiffeners Empennage 2 $0.00    0   
37     Jan 08, 2022 Riveted vert stab skin - completed vert stab! Empennage $0.00    1   
36     Jan 07, 2022 Riveted the vert stab skeleton Empennage 2 $0.00    0   
35     Jan 06, 2022 Clecoed the vertical stab skeleton Empennage 1 $0.00    0   
34     Jan 05, 2022 Finalized drilling vertical stab Empennage 2 $0.00    0   
33     Jan 04, 2022 Drilled the vertical stab skin Empennage 2 $0.00    0   
32     Jan 03, 2022 Continuing the vertical stab skeleton Empennage 2 $0.00    0   
31     Dec 31, 2021 Building the rudder skeleton Empennage 8 $0.00    0   
30     Dec 30, 2021 Fitting the Stiffeners to the Rudder skin Empennage 2 $0.00    0   
29     Dec 29, 2021 Fitting the Stiffeners to the Rudder skin Empennage 2 $0.00    0   
28     Dec 23, 2021 Fitting the Stiffeners to the Rudder skin Empennage 2 $0.00    0   
27     Dec 22, 2021 Drilling the V Stab Empennage 4 $0.00    0   
26     Dec 19, 2021 Drilling the V Stab Empennage 2 $0.00    0   
25     Dec 17, 2021 Riveting the H Stab Empennage 2 $0.00    1   
24     Dec 15, 2021 Riveting the H Stab Empennage 2 $0.00    0   
23     Dec 14, 2021 Riveting the H Stab Empennage 3 $0.00    0   
22     Dec 12, 2021 Riveting the H Stab Empennage 6 $0.00    0   
21     Dec 08, 2021 Riveting the H stab Empennage 2 $0.00    0   
20     Dec 07, 2021 Riveting the H Stab Empennage 2 $0.00    0   
19     Dec 04, 2021 Riveting the H Stab Empennage 2 $0.00    0   
18     Dec 01, 2021 Riveting the H-Stab Empennage 3 $0.00    0   
17     Nov 30, 2021 Preparing parts for assembly Empennage 6 $0.00    0   
16     Nov 16, 2021 Drilling the H Stab Empennage 2 $0.00    0   
15     Nov 15, 2021 Drilling the H stab Empennage 2 $0.00    0   
14     Nov 14, 2021 Drilling the H Stab Empennage 4 $0.00    1   
13     Nov 13, 2021 Drilling h stab Empennage 6 $0.00    0   
12     Nov 12, 2021 Preparing ribs Empennage 2 $0.00    0   
11     Nov 10, 2021 HS-411 assembly Empennage 2 $0.00    0   
10     Nov 07, 2021 Preparing ribs Empennage 3 $0.00    0   
9     Nov 04, 2021 Match drilling Empennage 1 $0.00    0   
8     Nov 03, 2021 HS710 Empennage 2 $0.00    0   
7     Nov 02, 2021 Match Drill Doublers Empennage 1 $0.00    0   
6     Nov 01, 2021 Front Spar Empennage 1 $0.00    0   
5     Oct 31, 2021 Front Spar Empennage 4 $0.00    0   
4     Oct 30, 2021 Elevator hinge brackets Empennage 2 $0.00    0   
3     Oct 28, 2021 Prepared HS-609PP Empennage 2 $0.00    1   
2     Oct 27, 2021 Prepare HS-609PP Empennage 2 $0.00    1   
1     Oct 26, 2021 Received and inventoried Empennage 2 $2440.00    1   
------------ -------------- -------------
Totals322    $11440.00    37   