Project: MikeSVelo173FG     -     Project Summary     - Optional PDF document function
Add entry descriptions           Project PDF with: -

Entry #CreatedTitleCategoryHours     Cost # Pictures
40     Mar 08, 2024 Various Tools Tools $0.00    12   
39     Mar 08, 2024 Various Tools $0.00    0   
38     Mar 07, 2024 Starting on the fuselage Fuselage $0.00    5   
37     Feb 24, 2024 EAA 1475 group visit to the shop/project day Workshop $0.00    4   
36     Feb 24, 2024 Trimmed inboard ends ready for rib lay ups Wings $0.00    8   
35     Feb 18, 2024 Skinning the top of the left (pilot) side wing Wings 4.25 $0.00    9   
34     Jan 29, 2024 Left wing continued Wings 4 $0.00    8   
33     Jan 09, 2024 Left side wing prep for skinning comtinued. Wings $0.00    9   
32     Jan 04, 2024 Milestone moment! Wings $0.00    2   
31     Jan 04, 2024 Top Bolt Access Hole and reinforcement lay up Wings 4 $0.00    8   
30     Dec 17, 2023 More inboard end prep Wings 3 $0.00    8   
29     Nov 28, 2023 Inboard end of wing prep Wings 2 $0.00    6   
28     Nov 27, 2023 Skinning the top of the starboard wing Wings 4 $0.00    3   
27     Aug 11, 2023 Prepping the top of the right wing for skinning Wings 4 $0.00    11   
26     May 27, 2023 Skinning the wing! Wings 3 $0.00    10   
25     Jan 31, 2023 GLued on TE Cores Wings 1.5 $0.00    6   
24     Jan 02, 2023 Preparing TE cores Wings $0.00    3   
23     Dec 05, 2022 GLuing core to left wing Wings $0.00    5   
22     Dec 04, 2022 Started left wing Wings $0.00    5   
21     Aug 12, 2022 Elevator skinning continued Empennage $0.00    5   
20     Aug 12, 2022 My workbench for the winglets and elevators Tools $0.00    3   
19     Aug 08, 2022 Skinning the elevators Empennage $0.00    9   
18     Jul 20, 2022 More elevator work Empennage $0.00    3   
17     Jul 17, 2022 More elevator work Empennage $0.00    1   
16     Jul 15, 2022 Elevators Empennage 1 $0.00    1   
15     Jun 11, 2022 Finished skinning copilot side winglet Empennage 2 $0.00    2   
14     May 30, 2022 Winglet Outer Lay Up and NAV antennae Empennage 5 $0.00    5   
13     Apr 18, 2022 Second winglet Lay Up Empennage 2 $0.00    2   
12     Apr 08, 2022 Winglet Lay up cured Empennage $0.00    2   
11     Apr 07, 2022 Winglets Empennage 3 $0.00    2   
10     Mar 28, 2022 Final canard lay up's Empennage 2.5 $0.00    4   
9     Mar 23, 2022 Canard Upper Skin lay up Empennage 4 $0.00    10   
8     Mar 18, 2022 Canard lower skin lay up Empennage 4 $0.00    6   
7     Jan 30, 2022 Prep canard for skinning Empennage 5 $0.00    4   
6     Jan 05, 2022 Assembled winglets Wings 2 $0.00    1   
5     Dec 11, 2021 Started canard Empennage 5 $0.00    14   
4     Nov 27, 2021 Fuselage cradle Fuselage 3 $0.00    1   
3     Sep 01, 2021 Right wing Wings $0.00    3   
2     Jul 05, 2020 Started setting up shop Workshop $0.00    3   
1     Jul 04, 2020 Brought her home! Research 9.9 $0.00    1   
------------ -------------- -------------
Totals78.15    $0.00    204   