Project: TerryS   -  
            Listing for Category : Fuselage
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Terry Shortt   -  
Project:   Vans   -   VIEW REPORTS
Total Hours:3270.7
Total Flight Time:
Total Expense:N/A
Start/Last Date:Sep 12, 2019 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=TerryS

Home or Last Project Picture

Oct 23, 2020     Longerons in process - (2 hours)       Category: Fuselage
trimmed the notches in the aft end of both longerons & after much measuring and checking against the aft deck & vert attach bars, cut the notches for the vert bars. NOTE- the print has a callout for the radius inside the notch for the vert bars to be 3/32 in both inside corners. This is confusing, because a 3/32 radius is derived from a 3/16" hole, which is the width of the slot. This would make teh slot more of a U shape rather than a rectangle with rounded inside corners.

Not sure if theres a typo on the print and they actually meant 3/64" radius or what, but the whole concept is to make the slots barely bigger than the 3/16" thick vert. attach bars, so I established the bottom of the slot/radius by drilling a 3/16" hole, but backed off from the actual bottom of the slot a bit, cut the slots with a hacksaw, then filed everything to fit.

I had left the aft end a little long until I could compare it to the tailcone, because a lot of stuff has to fit pretty precisely, but I shouldn't have bothered. It was all dead on. I only hope the front 1/2 matches the sidewalls & firewall as good!


 