Builder Name:Timothy Higgins   -  
Project:   Vans - RV-12iS   -   VIEW REPORTS
Total Hours:1446.1
Total Flight Time:
Total Expense:$121270.70
Start/Last Date:Mar 22, 2020 - No Finish Date
Engine:Rotax 912iS
Propeller:Ground adjustable 3 blade Composite
Panel:Garmin G3X and iPad
 
Friendly URL: https://eaabuilderslog.org?s=thiggins

Home or Last Project Picture

Mar 23, 2022     Installing landing lights - (2 hours)       Category: Wings


 
Mar 01, 2022     ordered finish kit and avionics - (2 hours)       Category: Wings
trying to head off price increases. still waiting for everything....


 
Jan 25, 2022     Running wires , aoa tube, stall switch done, working on landing lights - (4 hours)       Category: Wings
Since I'm waiting on back ordered Wing parts, the stub spars for the front of the wings, and my fuselage kit ( it will contain them) is very late with no delivery date, I'm skipping all over the place and doing all kinds of strange steps.


 
Jan 23, 2022     Flaperons done , wiring wings - (5 hours)       Category: Wings
See completed flaperons hanging overhead. Can't skin the wings without back ordered parts, so skipping around a bit. A little tricky as I could work myself into a corner. Been there, done that. Still waiting on a very late fuselage kit.


 
Jan 11, 2022     Right flaperon ready for nose skins - (4 hours)       Category: Wings


 
Jan 11, 2022     Right flaperon ready for skinning - (3 hours)       Category: Wings


 
Jan 10, 2022     Started the right flaperon       Category: Wings
I had to put some of the smaller parts on the spar just to convince my brain I was building the right flaperon, not the left!


 
Jan 09, 2022     Loctite the tie rod ends and hung the flaperon overhead - (3 hours) Category: Wings
 
Jan 06, 2022     Left flaperon ready for skins - (15 hours)       Category: Wings


 
Jan 03, 2022     Working left flaperon - (20 hours)       Category: Wings
Deburring, priming, drilling…


 
Jan 01, 2022     All ribs installed - (20 hours)       Category: Wings
Had a rough time getting rivets in between the inboard ribs, but finally made it happen.
Still missing stub spars, so moving on to the flaperons. Already drilled two holes in the 1st stainless counterweight. Scary.


 
Dec 26, 2021     Installing forward ribs - right wing - (5 hours)       Category: Wings
Working around backordered parts makes life “ interesting “.
Moving forward on faith stuff will show up.


 
Dec 21, 2021     Rear ribs attached on both wings - (40 hours)       Category: Wings
Had to replace only about 40 rivets…don't ask…(read those “Notes”!?!?) but finally have the rear spars on. Still waiting on spar doublers and stub spars. Dang it. Might move on to the flaperons instead.


 
Dec 15, 2021     Debur ribs - (60 hours)       Category: Wings
Finished deburring all wing ribs…whew…


 
Feb 04, 2021     Ordered wing kit from Vans - (2 hours) Category: Wings
deposit in the amount of $2405.88
 