Project: PhilVogel   -  
            Listing for Category : Wings
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Phil Vogel   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:143.7
Total Flight Time:
Total Expense:N/A
Start/Last Date:Nov 27, 2020 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=PhilVogel

Home or Last Project Picture

Mar 05, 2021     Flap and aileron bell crank - (2.5 hours)       Category: Wings
I completed the bell crank installation for both the aileron and flaps L wing. Safety wired securing cable around aileron bell crank, aileron bell crank safety wired and bolts torqued. Tele flex cable to flap bell crank installed and safety wired. Dean turns on the female tie rod, torqued to 15 inch pounds. Torque seal applied


 