Project: V-Twin   -  
            Listing for Category : research
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Paul Aplikowski   -  
Project:   Velocity - Twin   -   VIEW REPORTS
Total Hours:212.8
Total Flight Time:
Start/Last Date:Jul 13, 2023 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=V-Twin

Home or Last Project Picture

Nov 11, 2023     Parts Inventory - (3 hours) Category: Research
Unpacked and inventoried all items that came as part of the shipment. Organized and stored all items in my storage area. There appear to be a few items missing from the shipment.

Maing Gear Pivot Bolt Bushing 3/4" ID 4" long
9/16" ID x 2" long Aluminum Spacer
SS Nicopress Crimps
Main Gear Doors to Leg Brackets (Alum Angle 1"x1"x4")
Main Gear Cleveland Predrilled Spacer

I let Chad at the Factory know I had some items missing.
 
Jul 15, 2023     Head Start Program Payment Category: Research
 
May 28, 2023     Kit is being manufactured! Category: Research
Received word my kit is in production. I have opted to get some additional assistance from the factory to build the strakes and seal up the gas tanks. I will be in Florida from July 12-27 for my head start program. I will then be having Dan Fast of Fast Aircraft Movers bring the kit home to Minnesota where I will compete the build.
 
Dec 17, 2022     Delivery Update Category: Research
Received word from the Factory last month that my delivery date is likely moved up from July to June!
 
Jul 01, 2022     Still waiting Category: Research
Factory confirmed that my delivery date is still July 2023.
 
Feb 11, 2022     Put deposit on kit Category: Research
Traveled to Sebastian Florida to take a test ride and tour the factory. Also talked to a few builders working on their projects there. Put down deposit on a V-Twin kit. Now the wait for delivery begins.
 