Project: OneX-Hudson   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Johan Nielsen   -  
Project:   Sonex - OneX   -   VIEW REPORTS
Total Hours:131.1
Total Flight Time:
Start/Last Date:Aug 04, 2023 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=OneX-Hudson

Home or Last Project Picture

Apr 07, 2024     Glare shield complete - (3.8 hours) Category: Fuselage
 
Mar 16, 2024     Glare shield install - (0.55 hour) Category: Fuselage
 
Mar 04, 2024     Upper firewall and glare shield - (1.1 hours) Category: Fuselage
 
Mar 04, 2024     Firewall attachment. - (0.45 hour) Category: Fuselage
 
Feb 21, 2024     Initial fitting of glare shield - (1.5 hours) Category: Fuselage
 
Feb 21, 2024     Installation of flap handle detent - (1.05 hours) Category: Fuselage
 
Feb 18, 2024     Final assembly of elevator control surface - (1.25 hours) Category: Fuselage
After a very long wait for the elevator control horn weldment to finally arrive (back ordered), we got back to completing the assembly of the elevator. Fitting the elevator to the stabilizer resulted in the need for a slight adjustment in the hinge placement. For this exact reason, the holes for he hinges on the stabilizer had not been up-drilled so this gave us the opportunity to make the necessary adjustments. It now fits as it is supposed to and with equal gap on both sides.
 
Feb 16, 2024     Final fitting of elevator on horizontal stabilizer - (3.30 hours) Category: Fuselage
 
Feb 14, 2024     Initial fitting of elevator on horizontal stablizer. - (2.25 hours)       Category: Fuselage
Up-drilling of hinge holes allowed for necessary adjustment for perfect fit.


 