Project: Cozy4   -  
            Listing for Category : c99 to sort
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Preston Kavanagh   -  
Project:   Cozy - Mark IV   -   VIEW REPORTS
Total Hours:4433.6
Total Flight Time:
Total Expense:$33393.25
Start/Last Date:Sep 01, 2003 - No Finish Date
Engine:IO-360-A3B6D
Propeller:Hertzler Silver Bullet 66 x 78
Panel:Garmin G3X + ipad
 
Friendly URL: https://eaabuilderslog.org?s=Cozy4

Home or Last Project Picture

Jul 04, 2023     Oxygen - (24 hours)       Category: C99 to sort
The experienced Cozy flyers strongly recommend an O2 system - the plane does very well flying at altitudes of 8,000 - 16,000. Flying in the southern Rockies I learned that I get headaches starting at 8,000 and that was 20 years ago. So, some kind of O2 system goes with the airplane's mission.

I installed a cylinder bracket in the right side strake. The bracket is positioned so that an E / M-24 cylinder can be accessed and controlled by either copilot or by the pilot reaching across an empty seat. The bracket is secured by 10-32 clickbond studs, and the bottle is held to the bracket by 3" seatbelt webbing. I also have C / M-9 cylinders that can be carried in a shoulder bag and hung over the co-pilot headrest. Matched to a pneumatic conservator, the two sizes should be sufficient for 25 and 9 hours of supplemental O2, respectively. A fingertip device will track O2 saturation, and the flow rates will be adjusted to maintain saturation at or above 93.


 
Apr 22, 2023     Gap Seals - (1 hour)       Category: C99 to sort
Took me a while to find where to get gap seal tape. Turns out it's a multi-step process. See the attached pdf's.


 
May 13, 2022     stations for CG envelope and W&B - (4 hours)       Category: C99 to sort
An aircraft CG range is the designer's planned relation of mass to lift. The aircraft designer sets a datum plane typically forward of the nose of the spinner - that makes for convenient positive number arithmetic. He then measures the distance aft of the datum of the empty CG of the prototype, setting safe foreward and rearward CG limits by testing that prototype. No matter how closely the plans are followed, EAB airplanes are going to vary from the prototype. If the build varies in the location of lifting surfaces it has to affect CG range. That's why it makes sense to double check measurements.

Builders agree that for the Rutan-derived canards the important reference plane is the wing root leading edge ("WRLE"), since it is a fixed point as regards the wings and thus the center of lift. The plans assign that point FS 113.9 - conveniently it falls at the outmost corner of the strakes and can be measured wings off. Given the WRLE, what are the stations for the leading edge of the canard, our other lifting surface? And what are the stations for the main and nose gear (reference points of the scales), and the several stations at which weight can be added or removed (ballast, pilot & copilot, fuel and rear passengers)? Time to do some measuring.

First step, find someone smarter - in this case Marc Zeitlin and Joel Ventura. I distilled their work into a 3-step process. First, set the WRLE and define the location of the landing gear relative to it. Second, set the aircraft on scales and set the empty CG. Third, measure the actual arms for the stations of interest. Here's the step by step.

1. On a clean floor, level the plane. The first several steps involve measuring distances and can be done wings off.

2. Drop a plumb line from WRLE to the floor and mark the spot (right & left). The plans define this as 113.9 inches, and I used it as the reference point for all other stations.

3. Drop a plumb line from the center of the main gear axle, mark the spot and measure the distance forward of the WRLE (for me, 4.1 inches for both left and right axles, for a main gear fs of 109.8). The plans call for 110, and the template draft POH calls for 109.5 +/- .5. The result is between plans and the POH and within tolerance. The 0.2" bias will very slightly increase the moment arm of the engine relative to the gear, so I might rotate 1-2 KIAS faster than otherwise. The discrepancy has no effect in the air. The landing attitude might be a degree or two nose higher and 0-1 knot slower. I might need to be just a little bit more careful about tip back of the aircraft while moving around the hangar.

4. Drop a plumb line from the center of the axle of the fully extended nose wheel, mark the spot and measure the distance forward of the main gear on the center line. Plans say FS16, which is 97.9 forward of the WRLE reference line. Mine measured at 96.14 - I will fully extend the gear and remeasure.

5. Drop a plumb line from the leading edge of the canard at the side of the fuselage, mark the spot (left and right). The plans say 18.7 but the manufacturer provided draft POH calls for this to be at 18.6, +/- .54. This is 95.3 forward of the WRLE reference. Mine measured at 81.4 - I absolutely need to remeasure!

6. By now there is a lot of tape on the floor! Snap chalk lines and make the measurements. Measure twice. At the end is determining if the build is in conformity with plans, and if not, that the variance is known and not a flight hazard.

7. Now it is time for the scales. My EAA chapter has a set of vehicle scales that are not certified but accurate within a half pound. The airplane should be ready to fly - all standard equipment and normal oil. I hold that you need to have installed all standard equipment - the ELT, POH, et al. Add 5 gallons of fuel and drain all usable. (With aft fuel sumps, the higher risk is level flight - drain with the aircraft level.)

8. The next step sets the arm of the various stations where weight will come and go. The following sequence is keyed to standard definitions of empty weight and to keeping the plane safely on the scales. For each step, add a _known_ weight at the given station. Write it all down - each measurement includes each of the 3 scales + the weight added.
- Empty weight and CG. This may require 50 lbs on the nose wheel to avoid a tip back.
- Add 100+ lbs at the pilot station and remeasure.
- Move that 100+ lbs to the copilot station and remeasure.
- Move that 100+ lbs to the right rear station and remeasure.
- Move that 100+ lbs to the left rear station and remeasure.
- Add max weight (24 lbs) at the most forward ballast station and remeasure.
- Add 50 lbs at the standard ballast station (for me, forward of the nose wheel housing) and remeasure.
- Move that 100+ lbs to the right strake, centered on the fuel cap, and remeasure.
- Move that 100+ lbs to the left strake, centered on the fuel cap, and remeasure.

9. Do some high school arithmetic and determine the station arm for each of the points.

10. Develop a cg worksheet or modify the Zeitlin template. ***Test the worksheet*** before leaving the scales - does the calculated CG match the actual? If so, load the same into Foreflight.

Going forward, look at the placard above the start button. T/O = WT + CG + DA.


 
Sep 11, 2011     Wing Intersection Trim - (1 hour)       Category: C99 to sort
Wing Intersection Trim
John started this step by stuffing the gap between the wing and strake with blue foam and prepping the area for a layup. A 2-BID tape goes across this shelf. Once it cured, I cut a perfectly straight line across it with a hacksaw. The foam will get cut away and replaced with a flox corner later. This gives you a perfect seam between wing and strake.


 
May 28, 2009     Fuselage together - (6.5 hours)       Category: C99 to sort
OK, I actually spent a very long time on this step today, but for me it was a culmination of a LOT of past work that's been lying around the shop, just waiting to be used. Here's what I did today:

1. Installed elevators in canard. The pins are a little stiff from some micro stuck in there, so I didn't drive them home - I'll pull and clean them, then do that next time.

2. Installed canard in fuselage. I didn't bolt it in, since it will probably come out again shortly, but at least I can finish hooking up the controls.

3. Installed mains in fuselage - this should be the final installation, unless finishing requires something weird. I hope it is. The studs were VERY firm going in, and even with my slide hammer it could be an all-day job getting them out again. I'd rather not.

4. Deployed nose gear. Doesn't sound like that big of a deal, but now I can roll the plane around, for the very first time!

5. Installed wings. I used a shop crane to help with this step, and WOW. WOW. If I had known how useful this would be I would have bought one on the first day I started the build!

So all in all, the "plane" is more or less "together". I have a huge list of little junk to work on, mostly finishing various things that couldn't be finished until it was at this stage - rigging the last of the controls, getting the electrical and antennae wired up, installing and trimming all the fairings and other finishing items, doing the actual finishing, fixing the canopy hinges, etc. Oh, and I sort of need an engine and some instruments! But you can definitely see it coming together now!



 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.