Project: RV-6A   -  
            Listing for Category : Fuselage
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Nathan Schenk   -  
Project:   Vans - RV-6A   -   VIEW REPORTS
Total Hours:105.5
Total Flight Time:
Start/Last Date:Dec 05, 2021 - No Finish Date
Engine:Lycoming 0-320-A1A
 
Friendly URL: https://eaabuilderslog.org?s=RV-6A

Home or Last Project Picture

Dec 25, 2021     Front deck - (2 hours)       Category: Fuselage
I removed the 2024-T3 deck and installed the 6061-T6 deck. It does seem that the 6061 deck does fit a bit better, but it's got a tiny bit of surface corrosion and just looks dull. It also seems to be a bit softer. I need to reach out to some experts and make a decision of which one to use.

One big issue with the 2024-T3 deck is the rivet holes are countersunk. They are dimpled on the 6061 deck, and because of this, the framework underneath is also dimpled. I have a feeling that countersinks over dimples isn't the best idea.


 