570     May 02, 2024 Bonded foam block Canopy 1.5 $0.00    6   
569     Apr 27, 2024 Cut foam blocks Canopy $0.00    6   
568     Apr 26, 2024 Prepped for canopy fairing work Canopy 3 $0.00    5   
567     Apr 22, 2024 Canopy guide blocks installed Canopy 1.5 $0.00    3   
566     Apr 15, 2024 Removed struts Canopy .5 $0.00    2   
565     Apr 15, 2024 Completed SB-00088 Service B's 3 $26.38    3   
564     Apr 15, 2024 Started on SB0000-88 Canopy 1.5 $0.00    3   
563     Apr 13, 2024 Riveted front of canopy Canopy 1.3 $0.00    3   
562     Apr 12, 2024 Ran out of screws Canopy 2.5 $0.00    3   
561     Apr 11, 2024 Resumed work on canopy Canopy 4 $0.00    2   
560     Apr 04, 2024 Polished the stabilator Empennage 3 $0.00    7   
559     Apr 02, 2024 Trimmed stabilator skin Empennage 3 $0.00    2   
558     Apr 01, 2024 Stabilator - Fairing interference Empennage 2 $0.00    2   
557     Mar 31, 2024 Drilling emp fairing to tailcone Empennage 1 $0.00    4   
556     Mar 29, 2024 Finished fairing assembly and checked rudder clearance Empennage $0.00    7   
555     Mar 28, 2024 Prepped emp fairing tabs Empennage 2 $0.00    4   
554     Mar 27, 2024 Drilled empennage fairings Empennage 1.5 $0.00    8   
553     Mar 21, 2024 Finished cutting emp fairings Empennage 2 $0.00    3   
552     Mar 16, 2024 Cut out the top emp fairing Empennage 1.5 $0.00    3   
551     Mar 15, 2024 More marking up the emp fairing Empennage 1.5 $0.00    3   
550     Mar 13, 2024 Finished VS and rudder fairings Empennage 3 $0.00    4   
549     Mar 07, 2024 Polished VS and rudder Empennage 4 $0.00    7   
548     Feb 26, 2024 Started on VS and rudder fairings Empennage 1.5 $0.00    4   
547     Feb 22, 2024 Taking everything apart again Empennage 1 $0.00    2   
546     Feb 05, 2024 More stabilator connections Empennage $0.00    6   
545     Feb 03, 2024 Stabilator attached!!! Empennage 1 $0.00    1   
544     Jan 31, 2024 How to waste another afternoon Empennage 2 $0.00    2   
543     Jan 30, 2024 How to waste an afternoon Empennage 3 $59.67    2   
542     Jan 10, 2024 Attached rudder Empennage 1.5 $0.00    1   
541     Dec 29, 2023 Completed service letter SL000068 Service B's 2 $0.00    3   
540     Dec 28, 2023 Prepped spacers etc Service B's 2 $0.00    2   
539     Dec 26, 2023 Started on Stabilator service letter SL0000-68 Service B's 2 $0.00    5   
538     Dec 25, 2023 SL-00070 Service B's .1 $60.33    0   
537     Aug 09, 2023 Added canopy blocks Canopy 2 $26.00    4   
536     Aug 08, 2023 Canopy latch odds and ends Canopy 1 $7.08    1   
535     Aug 05, 2023 Guide block nonsense Canopy 1 $0.00    1   
534     Aug 03, 2023 Painted skirts Canopy .5 $0.00    0   
533     Aug 02, 2023 Canopy work Canopy 4 $0.00    2   
532     Jul 27, 2023 Drilled canopy skirts Canopy 3 $0.00    3   
531     Jul 27, 2023 Drilled front and rear bows Canopy 2 $0.00    3   
530     Jul 25, 2023 Drilled front frame Canopy 2 $0.00    2   
529     Jul 24, 2023 Fit canopy Canopy 2 $0.00    3   
528     Jul 24, 2023 Complied with SB 00059 Service B's .1 $0.00    1   
527     Jul 02, 2023 Sealed rear window Finishing 2 $0.00    4   
526     Jun 27, 2023 Reinstalled window Finishing 1 $0.00    2   
525     Jun 01, 2023 Finished final adjustments to rear window Finishing 4 $25.00    4   
524     May 29, 2023 Window drilled Finishing 4.5 $20.46    3   
523     May 15, 2023 Now back to the window Finishing .5 $0.00    1   
522     May 08, 2023 Complied with Stabilator counterweight service bulletin Service B's 1.5 $15.00    3   
521     May 06, 2023 Painted canopy frame Canopy .5 $0.00    1   
520     Apr 27, 2023 Finished GPU installation Avionics 1 $0.00    1   
519     Apr 18, 2023 Made a bracket for GPU Avionics 2 $0.00    1   
518     Mar 16, 2023 Wired up White Lightning GPU Avionics 2 $0.00    4   
517     Mar 12, 2023 Riveted cockpit light bracket Lighting .1 $0.00    2   
516     Mar 10, 2023 Miscellaneous puttering Lighting 1 $5.16    2   
515     Mar 08, 2023 Finished trimming bottom cowling Engine 2 $0.00    2   
514     Mar 08, 2023 Complied with SB-00064-RV12 Service B's .5 $15.00    1   
513     Mar 07, 2023 Fitting bottom cowling Engine 1.5 $0.00    3   
512     Mar 06, 2023 Secured throttle cable Engine $0.00    2   
511     Mar 05, 2023 Mucking around the engine Avionics 1 $35.84    0   
510     Feb 15, 2023 Attached throttle lever plate Finishing 1 $0.00    1   
509     Feb 12, 2023 Set ECO stop Controls 1 $0.00    2   
508     Feb 07, 2023 SB fix kits arrive Service B's .1 $51.22    0   
507     Feb 06, 2023 Avionics are alive Avionics 2 $0.00    5   
506     Jan 29, 2023 Ground power unit Avionics .1 $536.83    0   
505     Jan 25, 2023 Closed up the panel Avionics 3 $11.33    7   
504     Jan 20, 2023 Sealed wire pass-through Avionics .2 $0.00    2   
503     Jan 17, 2023 Nutplate for fuel inspection cover and installed AP head Avionics 2 $0.00    5   
502     Dec 24, 2022 Completed right wing electrical connector fix Lighting .2 $12.03    0   
501     Dec 16, 2022 Prepped panel for MFD Avionics 1 $15.25    1   
500     Dec 12, 2022 Completed SB-00058 Service B's 2 $0.00    3   
499     Dec 11, 2022 Started on SB-00058 Service B's 1 $0.00    3   
498     Dec 10, 2022 Replaced right wing connector Wings $0.00    2   
497     Dec 05, 2022 Completed AOA installation, wire ID. Lighting 1 $117.85    8   
496     Nov 22, 2022 Let's wait some more! Wings .3 $0.00    1   
495     Nov 21, 2022 Reinstalled fuel line, autopilot servo and fuel tank Fuel System 3 $0.00    6   
494     Nov 21, 2022 Constructed new fuel line. Again Fuel System 1 $0.00    2   
493     Nov 19, 2022 Added missing rivets; pulled fuel line Fuel System 2 $0.00    3   
492     Nov 15, 2022 Removing AMP connectors Avionics .1 $0.00    1   
491     Nov 13, 2022 Preparing to undo stuff for a service bulletin Service B's .1 $0.00    1   
490     Nov 12, 2022 Cleaning up things in the tail cone Avionics 1 $0.00    3   
489     Nov 10, 2022 Discovering errors Avionics 2 $0.00    7   
488     Nov 10, 2022 Fitting panels Avionics 2 $0.00    2   
487     Nov 07, 2022 Sealing grommets Avionics 2 $0.00    4   
486     Nov 06, 2022 Installed platenuts for instrument panel Avionics 2 $20.00    2   
485     Nov 02, 2022 More AOA work Wings .3 $0.00    1   
484     Oct 31, 2022 More odds and ends Wings 1 $0.00    2   
483     Oct 26, 2022 AOA Retrofit Wings 4 $0.00    8   
482     Oct 23, 2022 Tidying up some wiring Avionics 1 $0.00    2   
481     Oct 22, 2022 My kingdom for a screw! Avionics $0.00    1   
480     Oct 20, 2022 Installed transponder bracket Avionics .2 $0.00    1   
479     Oct 17, 2022 Putting stuff back together and installing more avionics Avionics 3 $400.00    4   
478     Oct 16, 2022 Installed GEA 24 Avionics 1 $0.00    2   
477     Oct 15, 2022 Installed GTR 200 and GTX 35R racks Avionics $17.76    1   
476     Oct 13, 2022 Resurfaced hangar ramp Workshop .1 $0.00    21   
475     Oct 01, 2022 One step back Avionics 2 $0.00    2   
474     Sep 30, 2022 Building supports for COM radio Avionics 1 $0.00    3   
473     Sep 25, 2022 ProSealed rivet heads Avionics .5 $0.00    0   
472     Sep 23, 2022 Finished firewall drilling Avionics 3 $0.00    5   
471     Sep 22, 2022 Firewall drilling Avionics 1.5 $0.00    3   
470     Sep 20, 2022 Prepped more G3X pieces Avionics 1.5 $0.00    1   
469     Sep 18, 2022 Prepped G3X brackets Avionics $0.00    4   
468     Sep 18, 2022 Added instrument panel doubler Avionics 1 $0.00    1   
467     Sep 16, 2022 Moved autopilot servo ground wire Avionics .2 $0.00    0   
466     Sep 15, 2022 Installed autopilot pitch servo Avionics 1.5 $0.00    7   
465     Sep 14, 2022 Installed autopilot roll servo Avionics 1.5 $0.00    5   
464     Sep 12, 2022 Autopilot pushrods Avionics 2 $0.00    1   
463     Sep 09, 2022 Drilling of rear window aborted Finishing 1 $0.00    2   
462     Sep 07, 2022 Fitting of rear window Finishing 4 $0.00    4   
461     Sep 06, 2022 Installed gear leg covers. Started fit of rear window Finishing 2 $23.99    3   
460     Aug 30, 2022 More gear leg covers. This time with ProSeal Finishing 2 $0.00    2   
459     Aug 28, 2022 Gear leg cover prep and fit Finishing .5 $0.00    1   
458     Aug 27, 2022 Attached flaperon controls Finishing .3 $0.00    3   
457     Aug 25, 2022 Catastrophe averted Finishing 5 $0.00    7   
456     Aug 24, 2022 Riveted top skins Finishing 4 $0.00    4   
455     Aug 23, 2022 Prepped top baggage skins Avionics 3 $0.00    5   
454     Aug 22, 2022 Added chafing prevention to ADS-B IN antenna Avionics .3 $10.00    0   
453     Aug 19, 2022 Installed ADS-B IN router Avionics 2 $0.00    3   
452     Aug 17, 2022 Reinstalled fuel cutoff cable; Began ADS-B/XM installation Avionics 2 $0.00    5   
451     Aug 16, 2022 Routed new fuel valve cable Finishing .5 $174.91    1   
450     Aug 14, 2022 Connected ADHRS Finishing 1.5 $0.00    1   
449     Aug 13, 2022 Tail cone goes on Finishing $0.00    3   
448     Aug 12, 2022 It's time to put tailcone on Avionics .5 $0.00    1   
447     Aug 10, 2022 Not much of anything Avionics .1 $0.00    1   
446     Aug 09, 2022 Installing equipment in tailcone Avionics 2 $0.00    5   
445     Aug 08, 2022 Finished installing wiring bushings Avionics 3 $0.00    5   
444     Aug 07, 2022 Installing bushings Avionics .7 $0.00    3   
443     Aug 03, 2022 Crimped on connectors. Added Bushing brackets Avionics 2 $86.92    4   
442     Jul 24, 2022 Connected ELT, ran cockpit lighting wire Avionics 1 $0.00    1   
441     Jul 23, 2022 ELT, Fuel pumps, ADHRS et al connections Avionics 1.5 $0.00    6   
440     Jul 22, 2022 Snap bushings and wire routing Avionics 1.5 $0.00    2   
439     Jul 21, 2022 Two steps forward. One back Avionics .5 $0.00    1   
438     Jul 20, 2022 Flap motor wiring Avionics 3 $0.00    12   
437     Jul 20, 2022 Installed headphone jack and wing connectors Avionics 1.5 $42.21    4   
436     Jul 19, 2022 Connections to stick grip, installed OAT Avionics 1 $443.89    4   
435     Jul 15, 2022 Reinstalled fuel boost pumps (and more) Service B's $0.00    1   
434     Jul 13, 2022 Finished routing main harness Avionics .2 $0.00    7   
433     Jun 25, 2022 Routed wires on the pilot side Avionics 1.5 $0.00    1   
432     Jun 22, 2022 Began routing wires aft Service B's 1 $0.00    3   
431     Jun 21, 2022 GPS/XM wires routed Avionics 1 $0.00    4   
430     Jun 20, 2022 Secured fuse block wiring Avionics 1 $0.00    2   
429     Jun 18, 2022 Attached Generator A grounds Avionics 1 $0.00    2   
428     Jun 17, 2022 Connected relay wires Avionics 2 $0.00    6   
427     Jun 16, 2022 Connected G3x wires to fuse box Avionics 1 $0.00    2   
426     Jun 15, 2022 Rerouting wires Avionics 3 $0.00    6   
425     Jun 13, 2022 These instructions aren't very good Avionics .5 $0.00    4   
424     Jun 12, 2022 Connected coax to transponder antenna Avionics .2 $0.00    0   
423     Jun 10, 2022 Installed autopilot disconnect Avionics .5 $0.00    0   
422     Jun 07, 2022 Connected trim wires to connector Avionics .5 $0.00    2   
421     Jun 05, 2022 Routed fuel pump wires Avionics 1 $0.00    3   
420     May 26, 2022 Finished pilot-side wing pin sensor install Avionics 2 $14.99    2   
419     May 24, 2022 Mounted AV-6000 Avionics 1 $0.00    1   
418     May 23, 2022 Began plotting the wiring harness install Avionics .5 $0.00    2   
417     May 21, 2022 Completed stick wiring Avionics 1 $0.00    2   
416     May 20, 2022 Back to work on the stick grip wiring Avionics 1 $0.00    1   
415     May 18, 2022 Expanded forward access hole Avionics .2 $0.00    2   
414     May 17, 2022 Evaluated holes that need to be cut Avionics .1 $0.00    0   
413     May 16, 2022 Enlarged holes Avionics 4 $130.00    6   
412     May 15, 2022 The curse of the early fuselage kit Avionics 2 $0.00    3   
411     May 13, 2022 Installed ELT. Avionics $0.00    4   
410     May 12, 2022 Canopy lock sensor Avionics 2 $0.00    3   
409     May 11, 2022 Installed stick grips Avionics 3 $0.00    3   
408     May 10, 2022 Drilled hole in stick Avionics .5 $0.00    1   
407     May 09, 2022 Com and transponder antenna installed Avionics 1.5 $0.00    2   
406     May 09, 2022 CPU fans installed Avionics 1.5 $0.00    5   
405     May 05, 2022 Completed SB-53 Service B's 1.5 $0.00    4   
404     May 04, 2022 Started on SB-53 Service B's 3 $0.00    2   
403     Mar 10, 2022 Getting ready to start on SB-00053 Service B's .1 $36.29    1   
402     Dec 26, 2021 Fixed some wire connector issues Lighting 1 $0.00    1   
401     Oct 05, 2021 Cotter pins in wheel axles Finishing .1 $20.08    0   
400     Sep 15, 2021 Starting over on rear window Finishing $840.00    0   
399     Sep 13, 2021 Cut notches in rear window Finishing 2 $0.00    6   
398     Sep 10, 2021 More rear window fitting Finishing 1 $0.00    2   
397     Sep 07, 2021 Fit rear window Finishing 1 $0.00    2   
396     Sep 06, 2021 Fitting tail cone to the fuselage Fuselage 3 $0.00    2   
395     Sep 02, 2021 Prepping parts for mating fuselage Fuselage 2 $0.00    2   
394     Aug 27, 2021 Remade tank to vent fuel line Fuel System 4 $73.64    1   
393     Aug 10, 2021 Doing stuff I already did Finishing 3 $34.64    2   
392     Jul 01, 2021 Completed heating and cooling Engine 3 $0.00    5   
391     Jun 30, 2021 Heater cable installation Firewall 3 $15.73    5   
390     Jun 20, 2021 Heater vent assembly and installation Firewall 3 $0.00    3   
389     Jun 19, 2021 Vent hinges Firewall .5 $0.00    1   
388     Jun 16, 2021 Overflow bottle and air filter Engine 1 $6.37    4   
387     Jun 15, 2021 Attached throttle control cable Controls 2 $0.00    5   
386     Jun 12, 2021 Problem attaching throttle control Controls .5 $0.00    4   
385     Jun 07, 2021 Installed oil lines and Adel clamps Engine 3 $0.00    3   
384     Jun 06, 2021 Attached oil tank Engine 3 $0.00    2   
383     Jun 05, 2021 Radiator hoses attached Engine 3 $0.00    5   
382     Jun 01, 2021 Ordered avionics Avionics 0 $27997.12    0   
381     Jun 01, 2021 Installed oil cooler and radiator Engine 4 $0.00    3   
380     May 23, 2021 Assembling various fuse parts and priming engine component Fuselage 2 $0.00    1   
379     May 20, 2021 Complied with SB-00013 Service B's 4 $0.00    7   
378     May 15, 2021 Complied with SB-00023 Service B's 2 $674.13    5   
377     Mar 29, 2021 Prepped flap motor housing cover Controls 1 $0.00    2   
376     Mar 28, 2021 Primed, painted throttle quadrant sides Controls .3 $0.00    2   
375     Mar 23, 2021 Routing throttle and fuel shutoff cables Controls 2 $0.00    6   
374     Mar 21, 2021 Throttle system work Controls 2 $0.00    3   
373     Mar 05, 2021 Started on throttle control brackets Controls 1 $0.00    1   
372     Feb 28, 2021 Completed Section 47 Propeller 1 $0.00    2   
371     Feb 22, 2021 Set propeller pitch Propeller 1 $13.02    9   
370     Dec 08, 2020 Reinstalled muffler Engine .5 $0.00    2   
369     Dec 04, 2020 Reinstalled prop Propeller 2 $0.00    1   
368     Dec 01, 2020 Drilled for nutplates in spinner Propeller 2.5 $0.00    1   
367     Nov 28, 2020 Stalled on the muffler install Engine .5 $0.00    2   
366     Nov 26, 2020 Muffler/exaust installation Engine .5 $0.00    1   
365     Nov 20, 2020 Drilled more holes in spinner Propeller .5 $0.00    1   
364     Nov 19, 2020 Fabricated spinner cutout backup clips Propeller 2 $0.00    1   
363     Nov 18, 2020 Drilled spinner to aft spinner bulkhead Propeller 2 $0.00    2   
362     Nov 14, 2020 Drilled spinner to forward spinner bulkhead Propeller 1 $0.00    1   
361     Nov 13, 2020 Aligned spinner Propeller .5 $0.00    1   
360     Nov 09, 2020 Assembled muffler/heat muff assembly Engine 3 $0.00    7   
359     Nov 07, 2020 ProSealed the pitot bushing Propeller .1 $0.00    1   
358     Nov 07, 2020 Made spinner cuts and installed prop Propeller 2 $0.00    5   
357     Nov 04, 2020 Finished pitot tube routing, started on spinner Engine 1 $0.00    8   
356     Nov 02, 2020 Installed pitot tube. Trying to figure out routing Propeller 1 $0.00    4   
355     Nov 02, 2020 Started pitot tube installation Propeller 1 $0.00    1   
354     Nov 01, 2020 Fully finished SD-00001 Service B's .2 $0.00    1   
353     Oct 27, 2020 Mostly finished SD-00001 Service B's 1.5 $0.00    2   
352     Oct 26, 2020 Began SD-00001 fix Service B's 1.5 $245.08    3   
351     Oct 23, 2020 Attached oil door to top cowling Finishing 2 $0.00    2   
350     Oct 15, 2020 Finished inlets and added heat shield Finishing 2 $0.00    3   
349     Oct 13, 2020 Sanded NACA and airbox Finishing 2 $0.00    5   
348     Oct 12, 2020 Bonded air box and NACA vent to bottom cowling Finishing 3 $0.00    7   
347     Oct 11, 2020 Prepped filtered air box Finishing 2 $0.00    8   
346     Sep 13, 2020 Bonded NACA vent to top cowling Finishing 1.5 $0.00    4   
345     Sep 12, 2020 Filled gaps between cowling and vents Finishing 1.5 $0.00    1   
344     Sep 07, 2020 Epoxied cooling vents to top cowling Finishing .5 $0.00    2   
343     Sep 06, 2020 Cut out the cooling fins Finishing 1.5 $0.00    3   
342     Sep 02, 2020 Cowling closeout Finishing 3 $0.00    1   
341     Sep 01, 2020 Completed riveting cowling hinges Finishing 3.5 $0.00    5   
340     Aug 31, 2020 Start riveting cowling hinges Finishing 1.5 $0.00    3   
339     Aug 30, 2020 Fiberglassing work on cowling Finishing 2 $0.00    0   
338     Aug 29, 2020 Drilled the side hinges to the top cowling Finishing 3 $0.00    11   
337     Aug 28, 2020 Prepared to drill side hinges to top cowling Finishing 2 $0.00    1   
336     Aug 25, 2020 Drilled side hinges to bottom cowling Finishing 2 $0.00    8   
335     Aug 23, 2020 Drilled aft edges to hinges Finishing 1 $0.00    3   
334     Aug 22, 2020 Preparing to drill holes for hinges Finishing 2 $0.00    6   
333     Aug 13, 2020 Trimmed aft sides of cowling Finishing 5 $0.00    9   
332     Aug 03, 2020 Drilled top cowl and starting bottom cowling Finishing 3 $0.00    7   
331     Aug 02, 2020 More trimming and fitting of the top cowling Finishing 3 $6.00    11   
330     Aug 01, 2020 Spacers for spinner back plate Finishing 1.5 $0.00    1   
329     Jul 31, 2020 Fitting the top cowling Propeller 4 $0.00    12   
328     Jul 30, 2020 Finished cowling cutouts Finishing 1 $0.00    1   
327     Jul 28, 2020 Canopy trimming Finishing 6 $17.00    12   
326     Jul 27, 2020 Started the cowling Engine 4 $20.00    3   
325     Jul 26, 2020 Completed Section 46, except for one little thing Engine 2 $0.00    6   
324     Jul 26, 2020 Clamped ECU wires Engine 1 $0.00    1   
323     Jul 23, 2020 Mounted ECU Engine .2 $0.00    1   
322     Jul 22, 2020 Fuse box work Engine 2 $0.00    3   
321     Jul 20, 2020 Heat shield and fuse box Engine 4 $0.00    8   
320     Jul 19, 2020 Cut firesleeve Engine .5 $0.00    1   
319     Jul 17, 2020 Retorqued engine bolts Engine 1 $0.00    0   
318     Jul 16, 2020 Hung the engine Engine 2 $0.00    4   
317     Jul 16, 2020 Drilled second engine mount hole in firewall Engine 2 $0.00    3   
316     Jul 06, 2020 Solved CPS-1 and 2 mystery Engine 3 $0.00    3   
315     Jul 05, 2020 Engine mount bolted to engine Engine 4 $30.00    9   
314     Jul 04, 2020 Engine mount to engine Engine 2 $0.00    10   
313     Jul 02, 2020 Removed coolant hoses Engine .2 $0.00    1   
312     Jun 30, 2020 Completed Section 27 Engine 2 $24.82    2   
311     Jun 29, 2020 Reference pictures of the ROTAX iS Engine .1 $0.00    9   
310     Jun 27, 2020 Uncrated the ROTAX 912iS Engine 2 $70.00    5   
309     Jun 25, 2020 Started putting things on the firewall Engine 4 $0.00    4   
308     Jun 24, 2020 Fuel prefilter to fuel pump connection Fuel System 2 $0.00    7   
307     Jun 23, 2020 Fuel pump assembly Fuel System 2 $0.00    6   
306     Jun 22, 2020 Assembled fuel filter assembly Fuel System 1 $0.00    1   
305     Jun 20, 2020 Started work on fuel filter Engine 2 $0.00    1   
304     Jun 16, 2020 Powerplant kit arrives Engine 6 $0.00    4   
303     Jun 05, 2020 Engine shipped Engine 0 $35503.04    0   
302     May 27, 2020 Repainted rollbar. Primed canopy frame Fuselage 2 $249.98    4   
301     May 24, 2020 Prepped canopy frame and rollbar for painting Interior Finish 2 $0.00    2   
300     May 07, 2020 Primer and etching Interior Finish 0 $82.21    0   
299     Feb 08, 2020 Set breakout force on nosewheel Landing Gear 1 $0.00    1   
298     Feb 06, 2020 SB 19--08-26 Replaced nose gear Service B's 1.3 $390.00    5   
297     Feb 01, 2020 Reinstalled flaperon controls Service B's 2 $0.00    2   
296     Nov 15, 2019 Final holes drilled in flaperon Controls 1.4 $0.00    1   
295     Nov 10, 2019 Time to remove wings Controls 1 $0.00    1   
294     Nov 09, 2019 Drilled flaperon controls Controls 2 $0.00    6   
293     Nov 06, 2019 Attached wings Wings 3 $0.00    7   
292     Oct 20, 2019 Prepped flaperon brackets Controls 1 $0.00    0   
291     Oct 18, 2019 Attached flaperons to wings Controls 2 $0.00    1   
290     Oct 07, 2019 Stabilator service bulletin Service B's 1 $0.00    2   
289     Oct 06, 2019 Stabilator service bulletin - riveted gussets Service B's 1.5 $0.00    3   
288     Oct 04, 2019 Stabilator service bulletin Service B's 2 $0.00    1   
287     Oct 01, 2019 Started on service bulletin Service B's 2 $0.00    3   
286     Oct 01, 2019 Service Bulletin 18-02-02 Service B's 2 $0.00    5   
285     Sep 12, 2019 Canopy prep Canopy 2 $0.00    2   
284     Sep 08, 2019 Riveted side arms on canopy frame Canopy 2 $0.00    1   
283     Sep 07, 2019 Fluted canopy frame brackets Canopy 3 $0.00    3   
282     Aug 31, 2019 Mounted canopy frame Canopy 1 $0.00    1   
281     Aug 28, 2019 Gas struts to canopy frame Canopy 2 $0.00    2   
280     Aug 21, 2019 Started on canopy frame Canopy 1 $0.00    2   
279     Aug 18, 2019 Final touches on fairing Landing Gear 1 $0.00    1   
278     Aug 14, 2019 Finished (somewhat) nose gear fairing Landing Gear 2 $0.00    4   
277     Aug 13, 2019 Drilled hinge to gear-leg fairing Landing Gear 2 $0.00    1   
276     Aug 11, 2019 Drilled gear leg fairing Landing Gear 2 $0.00    3   
275     Aug 02, 2019 Started on nose gear leg fairing Landing Gear 1 $0.00    3   
274     Jul 31, 2019 Finished nose wheel fairing Landing Gear 2 $0.00    4   
273     Jul 30, 2019 Riveted nose wheel fairing brackets Landing Gear 1 $0.00    3   
272     Jul 28, 2019 Rivted side brackets to nose wheel pant Landing Gear 1 $0.00    4   
271     Jul 24, 2019 Oshkosh or no? Landing Gear 4 $0.00    6   
270     Jul 03, 2019 Finished right wheelpant Landing Gear 2 $0.00    3   
269     Jul 01, 2019 Fit right wheelpant Landing Gear 2 $0.00    2   
268     Jun 26, 2019 Fit right wheelpant Landing Gear 1 $0.00    5   
267     Jun 21, 2019 Started right wheelpant Landing Gear 2 $0.00    1   
266     Jun 20, 2019 Completed left wheelpant Landing Gear 4 $0.00    5   
265     Jun 15, 2019 Fixed left wheelpant problem Landing Gear 2 $0.00    4   
264     Jun 09, 2019 Identified left wheelpant problem Landing Gear 2 $0.00    3   
263     Jun 06, 2019 Installed left wheelpant bracket Landing Gear 2 $0.00    0   
262     May 31, 2019 Retired Workshop 0 $0.00    14   
261     May 23, 2019 Left axle work for wheelpant Landing Gear 1 $0.00    1   
260     May 22, 2019 Landing gear cutout Landing Gear 1 $0.00    1   
259     May 19, 2019 Sand forward half for mount fit Landing Gear 2 $0.00    1   
258     May 07, 2019 Adjust left wheelpant cutout Landing Gear 1 $0.00    1   
257     Apr 23, 2019 Trimmed wheelpant cutout Landing Gear 1 $0.00    2   
256     Apr 22, 2019 Started on wheelpants Landing Gear 1.5 $0.00    2   
255     Apr 19, 2019 Brake fluid added Finishing 1 $0.00    1   
254     Apr 16, 2019 Nose gear fork to nose leg Landing Gear .5 $0.00    1   
253     Apr 02, 2019 Bolted nose gear fork Landing Gear 2 $0.00    3   
252     Mar 24, 2019 Brake lines Finishing 2 $0.00    3   
251     Jan 13, 2019 Main gear installed Landing Gear 2 $0.00    3   
250     Jan 05, 2019 Left side axle Landing Gear 2 $0.00    3   
249     Jan 02, 2019 Finished left side gear leg Landing Gear 1 $0.00    2   
248     Dec 29, 2018 Landing gear work Landing Gear 4 $0.00    2   
247     Dec 16, 2018 Finished main wheel assembly Finishing 4 $0.00    0   
246     Dec 01, 2018 Main wheel and tire installation Finishing 1 $0.00    2   
245     Dec 01, 2018 Tired Finishing 1.5 $0.00    2   
244     Nov 24, 2018 Attached engine mount Finishing 1.5 $0.00    3   
243     Nov 23, 2018 Flap motor Finishing 1 $0.00    2   
242     Nov 22, 2018 Attached flap assembly control tubes Finishing 2 $0.00    2   
241     Nov 18, 2018 Riveted control arms and primed tube Finishing .5 $0.00    2   
240     Nov 17, 2018 Drilled rod end bearing males to control tubes Finishing 1 $0.00    0   
239     Nov 12, 2018 Bolted control rods to flap control mechanism Finishing 1 $0.00    3   
238     Nov 10, 2018 Tapped control rods Finishing 3 $0.00    2   
237     Nov 04, 2018 Begin yoke installation Finishing 3 $0.00    2   
236     Nov 03, 2018 Crontrol yoke bracket housing Finishing 2 $0.00    3   
235     Oct 28, 2018 Installed pulleys Finishing 1 $0.00    2   
234     Oct 27, 2018 Cable routing Finishing 1.5 $0.00    3   
233     Oct 21, 2018 Added clamps to rudder cables Finishing 1 $0.00    2   
232     Oct 20, 2018 Started working on flap mechanism Finishing .5 $0.00    1   
231     Oct 14, 2018 Installed control column Finishing 1.5 $0.00    1   
230     Oct 08, 2018 Prepped control rod and made support brackets Finishing 2.5 $0.00    2   
229     Sep 23, 2018 Completed fuselage subkit Fuselage 1 $0.00    1   
228     Sep 22, 2018 Riveted angle support to forward skin Fuselage 1 $0.00    1   
227     Sep 05, 2018 Added sealant to forward skin Fuselage 2 $0.00    2   
226     Sep 03, 2018 Riveted handle to supports Fuselage 1 $0.00    1   
225     Aug 22, 2018 Sealed side canopy rails Fuselage 2 $0.00    1   
224     Aug 21, 2018 Finished riveting forward deck Fuselage 3 $0.00    3   
223     Aug 20, 2018 Riveted canopy ribs on Fuselage 2 $0.00    4   
222     Aug 16, 2018 Rivet engine mount brackets Fuselage 1.5 $0.00    1   
221     Aug 11, 2018 Completed canopy ribs Fuselage 3 $0.00    3   
220     Aug 10, 2018 Adding remaining cowling hinge Fuselage 1 $0.00    1   
219     Aug 09, 2018 Began working on canopy ribs Fuselage 1.5 $0.00    3   
218     Aug 07, 2018 Installed upper firewall and sealed Fuselage 6 $0.00    5   
217     Aug 06, 2018 Riveted hinge on forward firewall Fuselage 2 $0.00    2   
216     Aug 05, 2018 Began work on upper firewall Fuselage 3 $0.00    2   
215     Aug 03, 2018 Section 29: Forward fuselage Fuselage 1 $0.00    1   
214     Aug 02, 2018 Completed brake lines Fuselage 1 $0.00    1   
213     Jul 31, 2018 Started making brake lines Fuselage 2 $0.00    0   
212     Jul 28, 2018 Drilled brake pedals Fuselage 2 $0.00    1   
211     Jul 25, 2018 Expensive brake pedal screwup Fuselage 2 $0.00    1   
210     Jul 23, 2018 Brake pedal drilling Fuselage 2 $0.00    1   
209     Jul 19, 2018 Ran fuel lines to the front Fuel System 2 $0.00    2   
208     Jul 16, 2018 Installed fuel valve Fuel System 1 $0.00    1   
207     Jul 04, 2018 Remade some fuel lines Fuel System 2 $0.00    1   
206     Jul 03, 2018 Started making fuel lines Fuel System 2 $0.00    5   
205     Jul 01, 2018 Section 27: Fit the fuel tank Fuel System 3 $0.00    3   
204     Jun 29, 2018 Testing of the fuel tank for leaks Fuselage 2 $0.00    3   
203     Jun 19, 2018 Finished sealing fuel tank Fuselage 3 $0.00    5   
202     Jun 16, 2018 Sealed fuel gauge Fuselage 2 $0.00    0   
201     Jun 15, 2018 Section 28: Rudder pedals Fuselage 2 $0.00    2   
200     Jun 11, 2018 Riveted bottom skin of fuel tank Fuselage 5 $0.00    5   
199     Jun 01, 2018 More fuel tank sealing Fuselage 2 $0.00    2   
198     May 28, 2018 Started sealing the fuel tank Fuselage 7 $0.00    5   
197     May 17, 2018 Nutplates and fuel tanks, oh my! Fuselage 3 $0.00    3   
196     May 12, 2018 Section 26: Started on the fuel tank Fuselage 1 $0.00    2   
195     May 10, 2018 Completed second seatback Fuselage 1 $0.00    0   
194     May 09, 2018 Started working on second seat Fuselage .5 $0.00    1   
193     May 08, 2018 Finished a seatback Fuselage 1 $0.00    1   
192     May 07, 2018 Seatback riveting Fuselage 1.5 $0.00    0   
191     May 06, 2018 Started on seatbacks Fuselage 2 $0.00    3   
190     May 05, 2018 Completed Section 24 Fuselage 2 $0.00    3   
189     May 03, 2018 Roll bar support Fuselage .5 $0.00    1   
188     Apr 26, 2018 Rear bulkhead Fuselage 4 $0.00    3   
187     Apr 21, 2018 Painted parts of rollbar assembly Fuselage .3 $0.00    1   
186     Apr 20, 2018 Removed rollbar Fuselage .5 $0.00    0   
185     Apr 19, 2018 Riveted support bracket Fuselage 2 $0.00    1   
184     Apr 18, 2018 Side rollbar support Fuselage 2 $0.00    1   
183     Apr 15, 2018 Prepping rollbar for riveting Fuselage 2 $0.00    3   
182     Apr 11, 2018 Deburred rollbar Fuselage 1.5 $0.00    2   
181     Apr 09, 2018 Finishing kit arrived Finishing 1 $12185.51    1   
180     Apr 06, 2018 Removed rollbar Fuselage 1 $0.00    0   
179     Apr 05, 2018 Finished drilling rollbar Fuselage 1.5 $0.00    0   
178     Apr 04, 2018 Started drilling rollbar Fuselage 1.5 $0.00    1   
177     Apr 03, 2018 Fit rollbar Fuselage 1.5 $0.00    1   
176     Apr 02, 2018 Section 24: Rollbar construction Fuselage 2 $0.00    2   
175     Apr 01, 2018 Completed Section 23 Fuselage 3 $0.00    3   
174     Mar 30, 2018 Assembled fuselage vent doors Fuselage 2 $0.00    2   
173     Mar 27, 2018 Riveted left side skin Fuselage 4 $0.00    1   
172     Mar 25, 2018 Added nutplates to left side skin Fuselage 1 $0.00    1   
171     Mar 24, 2018 Drilling right longeron Fuselage 3 $0.00    1   
170     Mar 22, 2018 Completed right side skin Fuselage 3 $0.00    1   
169     Mar 17, 2018 Began riveting side skin on right side Fuselage 3 $0.00    1   
168     Mar 16, 2018 Finished nutplates and primed right skin Fuselage 1.5 $0.00    2   
167     Mar 15, 2018 Deburred right side skin Fuselage 1 $0.00    0   
166     Mar 14, 2018 Drilled longeron holes Fuselage 3 $0.00    1   
165     Mar 07, 2018 Finished wing cutouts in side skin Fuselage 2.5 $0.00    2   
164     Mar 05, 2018 Longerons Fuselage 1 $0.00    2   
163     Mar 02, 2018 Riveted forward post Fuselage 1 $0.00    1   
162     Feb 28, 2018 Countersunk longeron Fuselage 1.5 $0.00    0   
161     Feb 27, 2018 Attached one bulkhead plate Fuselage 1 $0.00    1   
160     Feb 26, 2018 Countersunk wrong side of doubler Fuselage 1.5 $0.00    0   
159     Feb 25, 2018 Riveted on seatbat crosspiece Fuselage 3 $0.00    2   
158     Feb 24, 2018 Primed longerons Fuselage 1.5 $0.00    0   
157     Feb 23, 2018 Drilled top plates to longeron Fuselage 2 $0.00    2   
156     Feb 22, 2018 Twisting the longeron night away Fuselage 2 $0.00    2   
155     Feb 19, 2018 Completed mating of forward and mid fuselage Fuselage 3 $0.00    3   
154     Feb 18, 2018 Completed forward lower fuselage Fuselage 5 $0.00    2   
153     Feb 17, 2018 Bottom skin to firewall Fuselage 2 $0.00    3   
152     Feb 16, 2018 Completed firewall to bottom skin riveting Fuselage 1 $0.00    2   
151     Feb 12, 2018 Riveted bottom skin to ribs Fuselage 1 $0.00    1   
150     Feb 11, 2018 Firewall work Fuselage 4 $0.00    3   
149     Feb 08, 2018 Section 22: Firewall work Fuselage 2 $0.00    2   
148     Feb 03, 2018 Completed Section 21 Fuselage 1 $0.00    1   
147     Feb 02, 2018 The case of the missing rivets Fuselage 1.5 $0.00    1   
146     Feb 01, 2018 Prepped aft brackets Fuselage 1.5 $0.00    1   
145     Jan 30, 2018 Riveted forward floors Fuselage 1.5 $0.00    1   
144     Jan 29, 2018 Prepped remaining forward floor Fuselage 1.5 $0.00    1   
143     Jan 28, 2018 Completed riveting bottom skin to structure Fuselage 4 $0.00    2   
142     Jan 25, 2018 Riveting bottom skin Fuselage .7 $0.00    1   
141     Jan 24, 2018 Riveted doublers/stringers to superstructure Fuselage 1.3 $0.00    1   
140     Jan 21, 2018 Fit bottom skin Fuselage 4 $0.00    2   
139     Jan 18, 2018 Prepped bottom skin Fuselage 1 $0.00    2   
138     Jan 18, 2018 Prepped up angles Fuselage 1.5 $0.00    0   
137     Jan 17, 2018 Riveted shark gills Fuselage 1 $0.00    0   
136     Jan 16, 2018 Began work on 'shark gills' Fuselage 1.5 $0.00    1   
135     Jan 15, 2018 Riveted forward floor ribs Fuselage 3 $0.00    2   
134     Jan 13, 2018 More work on forward bulkhead Fuselage 2 $0.00    2   
133     Jan 10, 2018 More riveting on aft bulkhead Fuselage 1.7 $0.00    2   
132     Jan 09, 2018 Fuselage rear bulkhead Fuselage 2 $0.00    2   
131     Jan 07, 2018 Added center section bulkhead caps and rollers Fuselage 1.5 $0.00    2   
130     Jan 03, 2018 Riveted right side floor ribs to floor Fuselage 2 $0.00    1   
129     Jan 02, 2018 Riveted left side ribs to floor Fuselage 1.5 $0.00    2   
128     Jan 01, 2018 Started fitting floors Fuselage 2 $0.00    1   
127     Dec 31, 2017 Riveted brackets Fuselage 2.5 $0.00    3   
126     Dec 30, 2017 More rib prep Fuselage 2.5 $0.00    1   
125     Dec 29, 2017 More seat rib work Fuselage 6 $0.00    4   
124     Dec 28, 2017 Started on seat ribs Fuselage 4.5 $0.00    3   
123     Dec 27, 2017 Pulley assembly and flaperon mixture arm Fuselage 4 $0.00    3   
122     Dec 26, 2017 Stuck with Cherry rivets Fuselage 1 $0.00    1   
121     Dec 23, 2017 Finished attaching ribs to floor and bulkhead Fuselage 3 $0.00    2   
120     Dec 22, 2017 Finished riveting flooors Fuselage 1 $0.00    1   
119     Dec 21, 2017 Finished riveting floor/ribs to center section Fuselage 1.5 $0.00    2   
118     Dec 20, 2017 Attached left ribs to center section Fuselage 2 $0.00    1   
117     Dec 19, 2017 Finished right side baggage ribs Fuselage 1 $0.00    2   
116     Dec 18, 2017 Started riveting baggage ribs Fuselage 1.5 $0.00    2   
115     Dec 17, 2017 Attached nutplates to inspection holes Fuselage 1.5 $0.00    1   
114     Dec 16, 2017 Various puttering while waiting for backordered parts Fuselage 1 $0.00    2   
113     Dec 12, 2017 Riveted floors to center section Fuselage 1.5 $0.00    3   
112     Dec 10, 2017 Riveted ELT bracket to ribs; started riveting floors Fuselage 4 $0.00    5   
111     Dec 09, 2017 ELT bracket Fuselage 2 $0.00    3   
110     Nov 28, 2017 More center section work Fuselage 1.5 $0.00    3   
109     Nov 26, 2017 Adding more parts to the center section Fuselage 3 $0.00    3   
108     Nov 24, 2017 Finished drilling center section Fuselage 5 $0.00    2   
107     Nov 22, 2017 50 down. 74 to go Fuselage 1 $0.00    1   
106     Nov 20, 2017 Fit center section to bottom skin Fuselage 1 $0.00    2   
105     Nov 19, 2017 Started on center section Fuselage 1 $0.00    1   
104     Nov 18, 2017 Fuselage kit arrives Fuselage 1 $6323.00    2   
103     Aug 26, 2017 Finished right wing light fairing Lighting 3 $0.00    3   
102     Aug 25, 2017 Completed left light fairing Lighting 1.5 $0.00    2   
101     Aug 24, 2017 Started on right wing position light installation Lighting 1 $0.00    2   
100     Aug 23, 2017 Epoxied the lighting fair (left) Lighting 5 $0.00    5   
99     Aug 13, 2017 Cut access hole in left wing for outboard light Lighting 1.5 $0.00    5   
98     Aug 11, 2017 Finished work on left flaperon Wings 1 $0.00    1   
97     Aug 10, 2017 Completed right flaperon Wings 1.5 $0.00    1   
96     Aug 09, 2017 Flaperon skin riveting Wings 1.5 $0.00    1   
95     Aug 08, 2017 Riveted ribs etc to right flaperon Wings 1.5 $0.00    2   
94     Aug 07, 2017 Prep work on the right flaperon Wings 1.5 $0.00    2   
93     Aug 05, 2017 Started work on right flaperon Wings 3 $0.00    1   
92     Aug 04, 2017 Riveted skin to flaperon substructure Wings 1.5 $0.00    2   
91     Aug 03, 2017 Riveted ribs on flaperon Wings 1.5 $0.00    2   
90     Aug 02, 2017 Flaperon work Wings 1.5 $0.00    0   
89     Jul 31, 2017 Started on left flaperon Wings 1.5 $0.00    2   
88     Jul 30, 2017 Completed right wing Wings 5 $0.00    2   
87     Jul 29, 2017 Right wing closeout Wings 4.5 $0.00    6   
86     Jul 26, 2017 Riveted wing root doubler Wings 1 $0.00    1   
85     Jul 25, 2017 Started on wing root doubler Wings 2 $0.00    1   
84     Jul 24, 2017 Fit the top middle skin Wings 2 $0.00    0   
83     Jul 23, 2017 Finished landing light. Started out inboard top skin Lighting 5.5 $0.00    4   
82     Jul 22, 2017 Began installing landing light Lighting 5 $0.00    3   
81     Jul 21, 2017 Riveted bottom middle skin (right) Wings 2 $0.00    1   
80     Jul 19, 2017 Completed inboard out skin Wings 1 $0.00    0   
79     Jul 17, 2017 Completed inboard bottom skin (right) Wings 2 $0.00    1   
78     Jul 16, 2017 Began skinning right wing Wings 5 $0.00    2   
77     Jul 15, 2017 Finished the left wing Wings 5 $0.00    3   
76     Jul 14, 2017 Fluted and riveted wing tip frame Wings 2 $0.00    0   
75     Jul 13, 2017 Worked on wing tips Wings 1 $0.00    1   
74     Jul 12, 2017 Drilled out some rivets Wings 2 $0.00    1   
73     Jul 09, 2017 Completed top of left wing Wings 6.5 $0.00    1   
72     Jul 08, 2017 Started on top skins on left wing Wings 6 $0.00    3   
71     Jul 06, 2017 Completed bottom skin (left) Wings 1.5 $0.00    3   
70     Jul 05, 2017 Bottom left center skin Wings 2 $0.00    0   
69     Jul 04, 2017 Riveted inboard and outboard bottom skins (left) Wings 6 $0.00    2   
68     Jul 02, 2017 Began riveting wing skins Wings 3.5 $0.00    2   
67     Jul 01, 2017 Wiring runs Wings 2 $0.00    2   
66     Jun 30, 2017 Installed stall warning vane Wings 3 $0.00    2   
65     Jun 29, 2017 Completed rib installation on right wing spar Wings 2 $0.00    2   
64     Jun 28, 2017 Began installation of right wing main ribs Wings 2 $0.00    2   
63     Jun 25, 2017 Wing rib riveting Wings 4 $0.00    3   
62     Jun 24, 2017 Began mounting the ribs Wings 5.5 $0.00    1   
61     Jun 23, 2017 Completed nose ribs; worked on main ribs Wings 1.5 $0.00    1   
60     Jun 21, 2017 Started working on right ribs Wings 1 $0.00    0   
59     Jun 20, 2017 Finished W-1208L rib preparation Wings 2 $0.00    2   
58     Jun 19, 2017 Started prep work on the ribs Wings 1 $0.00    6   
57     Jun 17, 2017 Completed rear spar Wings 4 $0.00    8   
56     Jun 15, 2017 Countersinking and primng Wings 2 $0.00    1   
55     Jun 14, 2017 Rivet hinge bracket assembly Wings 1 $0.00    1   
54     Jun 13, 2017 Riveted brackets Wings 1 $0.00    1   
53     Jun 12, 2017 Primed spar stub doubler Wings 1 $0.00    1   
52     Jun 11, 2017 Began rear spar doublers Wings 2 $0.00    1   
51     Jun 10, 2017 Riveted wing doublers Wings 3 $0.00    5   
50     Jun 09, 2017 Started work on wings Wings 02 $0.00    0   
49     Jun 05, 2017 Wing kit arrives Wings 2 $11219.21    2   
48     Mar 28, 2017 Completed the empennage subkit Empennage 2 $1.77    3   
47     Mar 26, 2017 Assembled push rod for stabilator Empennage 4 $0.00    3   
46     Mar 25, 2017 Fit control surfaces to tailcone Empennage 3 $11.90    3   
45     Mar 24, 2017 Fit the vertical stabilizer to tailcone assembly Empennage .5 $0.00    2   
44     Mar 21, 2017 Completed tailcone Empennage 1.5 $0.00    1   
43     Mar 19, 2017 Began riveting top skin Empennage 3 $0.00    5   
42     Mar 18, 2017 Fit the top tailcone skin Empennage 1.3 $0.00    1   
41     Mar 17, 2017 Completed side skin riveting on tailcone Empennage 1.5 $0.00    2   
40     Mar 16, 2017 Completed right side of side skin riveting Empennage 1 $0.00    2   
39     Mar 15, 2017 More riveting of side skins Empennage .8 $0.00    1   
38     Mar 14, 2017 Riveted side skins Empennage 1 $0.00    2   
37     Mar 13, 2017 Prepped top corner skins Empennage 1.50 $0.00    3   
36     Mar 12, 2017 Installed some system runs Empennage 2.5 $0.00    3   
35     Mar 11, 2017 Completed riveting of tailcone bottom Empennage 3 $0.00    3   
34     Mar 10, 2017 More riveting of bottom skins Empennage 1.5 $0.00    2   
33     Mar 09, 2017 Riveted bottom skin halfs Empennage 3 $0.00    1   
32     Mar 02, 2017 Fit side skirts to tailcone Empennage 1 $0.00    0   
31     Feb 26, 2017 Started work on tailcone skin Empennage 1 $0.00    1   
30     Feb 25, 2017 Fit aft bulkhead to stabilator Empennage 2 $0.00    3   
29     Feb 24, 2017 Finished riveting aft bulkhead Empennage 1 $0.00    0   
28     Feb 23, 2017 Riveted aft bulkhead Empennage 1.5 $52.76    1   
27     Feb 22, 2017 Made tie-down bracket Empennage .5 $0.00    1   
26     Feb 20, 2017 Assembled bulkheads Empennage 5 $0.00    2   
25     Feb 19, 2017 Stabilator completed Empennage 1.5 $0.00    1   
24     Feb 18, 2017 Completed skinning the stabilator Empennage 6 $0.00    3   
23     Feb 17, 2017 Began riveting left skin on stabilator Empennage 1.5 $0.00    3   
22     Feb 16, 2017 Completed right stabilator skin Empennage 1 $0.00    0   
21     Feb 15, 2017 More riveting Empennage 1 $0.00    0   
20     Feb 14, 2017 Reamed holes Empennage 1.5 $0.00    2   
19     Feb 12, 2017 Fit skin on stabilator Empennage 1 $0.00    1   
18     Feb 11, 2017 Completed stabilator spar assembly Empennage 2 $0.00    5   
17     Feb 10, 2017 Riveted control brackets Empennage 2 $0.00    1   
16     Feb 09, 2017 Riveting platenuts Empennage 2 $0.00    1   
15     Feb 08, 2017 Spar box assembly Empennage 2 $0.00    3   
14     Feb 06, 2017 Stabilator spar box assembly Empennage .5 $0.00    2   
13     Feb 05, 2017 Stabilator parts prep Empennage 3 $0.00    4   
12     Feb 04, 2017 Completed right anti servo tab assembly Empennage 2 $0.00    3   
11     Feb 03, 2017 Started on right trim assembly -stabilzator Empennage 1 $0.00    0   
10     Feb 02, 2017 Completed left trim assembly Empennage 2 $0.00    0   
9     Jan 27, 2017 Completed rudder Empennage 4 $8.20    3   
8     Jan 26, 2017 Primed anad riveted rudder parts Empennage 3 $0.00    3   
7     Jan 23, 2017 Began work on rudder Empennage 3 $0.00    2   
6     Jan 22, 2017 Completed vertical stabilizer Empennage 5 $0.00    2   
5     Jan 21, 2017 Completed VS spar/rib assembly Empennage 4 $0.00    2   
4     Jan 20, 2017 Riveted upper spar caps to rear VSspar Empennage 1 $0.00    0   
3     Jan 17, 2017 Completed other half of VS spar doubler Empennage 1 $0.00    0   
2     Jan 16, 2017 First parts for vertical stabilizer Empennage 1 $0.00    1   
1     Jan 14, 2017 Kit inventory Empennage 2 $3059.49    3   
------------ -------------- -------------
Totals1053.2    $101616.09    1460   