Entry #CreatedTitleCategoryHours     Cost # Pictures
103     Apr 26, 2023 Ready for flight? Wings 2.5 $0.00    1   
102     Apr 19, 2023 Post Hanger Trip Rudder 2 $0.00    3   
101     Apr 12, 2023 Baby's first steps! Landing Gear 0.5 $0.00    3   
100     Apr 05, 2023 Greasing parts Landing Gear $0.00    1   
99     Apr 05, 2023 Frontal landing gear support Rudder $0.00    1   
98     Apr 05, 2023 Flap crank assembly Rudder $0.00    1   
97     Mar 22, 2023 Vans RV-7 Rudder Rudder 3.5 $0.00    1   
96     Mar 22, 2023 Engine mount Engine 3.5 $0.00    0   
95     Mar 22, 2023 Flaperon pushrod Wings 3.5 $0.00    1   
94     Mar 22, 2023 Hinges for lower cowl Fuselage 3.5 $0.00    1   
93     Mar 22, 2023 Roll Bar Fuselage 3.5 $0.00    1   
92     Mar 08, 2023 Assembled rear bulkhead Fuselage $0.00    1   
91     Mar 08, 2023 F1202 B firewall panelbase Fuselage $0.00    0   
90     Mar 08, 2023 Attaching the rollbar Fuselage $0.00    1   
89     Mar 01, 2023 canopy rib Fuselage 3.5 $0.00    1   
88     Mar 01, 2023 flap crank Fuselage 3.5 $0.00    1   
87     Mar 01, 2023 roll bar Fuselage 3.5 $0.00    1   
86     Mar 01, 2023 control stick rod Controls 3.5 $0.00    1   
85     Feb 22, 2023 Sealing the Deal (Deal = Firewall) Fuselage 3.5 $0.00    8   
84     Feb 22, 2023 More exciting photos of our work on the fuselage (+ rudder)! Workshop 3.5 $0.00    8   
83     Feb 08, 2023 2/8/23 Assorted Projects! Fuselage 3.5 $0.00    5   
82     Jan 18, 2023 First day working with the new spring team! Fuselage 1.5 $0.00    6   
81     Dec 07, 2022 Last Day! Fall 2022 Workshop 3 $0.00    3   
80     Nov 30, 2022 Riveting is riveting! Workshop 3 $0.00    5   
79     Nov 16, 2022 Build Update! Workshop $0.00    5   
78     Nov 02, 2022 Working on the airplane! Fuselage 3 $0.00    6   
77     Oct 12, 2022 Fuselage update Fuselage 3 $0.00    3   
76     Sep 21, 2022 Progress Journal 09/21/33 Empennage 3 $0.00    4   
75     Sep 14, 2022 Fuselage Updates Fuselage 3 $0.00    0   
74     Sep 07, 2022 First Aerolab of Fall 2022! Workshop 3 $0.00    4   
73     Apr 27, 2022 Empennage Complete Empennage $0.00    0   
72     Mar 23, 2022 Riveting Stiffening Clips Wings $0.00    1   
71     Mar 23, 2022 Pushrod to actuator to stabilator Wings $0.00    1   
70     Mar 23, 2022 Riviting wing tips skins Wings $0.00    2   
69     Mar 02, 2022 Wing Fairing Electrical Wings 2 $0.00    1   
68     Mar 02, 2022 Electrical Work on Wings Wings 2 $0.00    1   
67     Mar 02, 2022 Positional Lights Installed Wings 2 $0.00    2   
66     Feb 23, 2022 Empennage tip fairings Empennage 5 $0.00    1   
65     Feb 23, 2022 Wing lights Wings 3 $0.00    1   
64     Feb 23, 2022 Wing tip Wings 2 $0.00    1   
63     Feb 23, 2022 Stabilator Fairings Stabilator 3 $0.00    1   
62     Dec 08, 2021 Stabilator Assembly Stabilator 2 $0.00    1   
61     Dec 08, 2021 Wing Lights Wings 2 $0.00    2   
60     Dec 08, 2021 Building the Servo Empennage 1.5 $0.00    1   
59     Dec 08, 2021 Tailcone Assembly Tailcone 3 $0.00    2   
58     Dec 01, 2021 Light covers Lighting 3 $0.00    1   
57     Dec 01, 2021 Clevis alignment Empennage 1 $0.00    1   
56     Dec 01, 2021 Fitting the stabilator assembly to the tailcone Empennage 2 $0.00    2   
55     Dec 01, 2021 Riveting install doublers to servo tray Tailcone 1.5 $0.00    1   
54     Dec 01, 2021 Gluing felt into the tool cabinet Tools 0.5 $0.00    1   
53     Nov 17, 2021 Riveting skins to stabilator Stabilator 3 $0.00    1   
52     Nov 17, 2021 Riveting the skins to the wing Wings 3 $0.00    1   
51     Nov 17, 2021 Riveting skins to tailcone Tailcone 3 $0.00    1   
50     Nov 03, 2021 Stabilator-- mass riveting Stabilator 2.5 $0.00    0   
49     Nov 03, 2021 Attaching skin, wires to tailcone Tailcone 2.5 $0.00    1   
48     Nov 03, 2021 Wing Light Installation Wings 2.5 $0.00    1   
47     Nov 03, 2021 Stripped Bolt Extraction Process V Stabilizer 2.5 $0.00    2   
46     Oct 27, 2021 Vertical Stabilizer Skins V Stabilizer 1.5 $0.00    1   
45     Oct 27, 2021 Stabilator skins Stabilator 1.5 $0.00    2   
44     Oct 27, 2021 Wing skins Wings 1.5 $0.00    1   
43     Oct 27, 2021 Installing the static air system Tailcone 1.5 $0.00    3   
42     Oct 20, 2021 Stabilator Ribs Stabilator 2.5 $0.00    3   
41     Oct 20, 2021 Tailcone fuselage bulkhead and skins Tailcone 2.5 $0.00    3   
40     Oct 20, 2021 Prepping and attaching V Stabilizer Skin V Stabilizer 2.5 $0.00    2   
39     Oct 20, 2021 Wing Tips Wings 2.5 $0.00    2   
38     Oct 13, 2021 Bending tabs on wing tips Wings 2.5 $0.00    1   
37     Oct 13, 2021 Constructing tailcone-fuselage bulkhead Tailcone $0.00    1   
36     Oct 13, 2021 Assembling tailcone Tailcone $0.00    1   
35     Oct 13, 2021 aft spar for stabilator Stabilator $0.00    1   
34     Oct 13, 2021 Fore spar for stabilator Stabilator 2.5 $0.00    1   
33     Oct 13, 2021 Riveting spar caps (v. stabilizer) V Stabilizer 2.5 $0.00    1   
32     Oct 06, 2021 Assembling ribs for vertical stabilizer V Stabilizer 3 $0.00    1   
31     Oct 06, 2021 Assembling spar cap assembly Stabilator 3 $0.00    1   
30     Oct 06, 2021 Match drilling Fuselage bulkhead Tailcone 3 $0.00    1   
29     Oct 06, 2021 Priming and sealing the Wing Walks Wings 3 $0.00    1   
28     Oct 06, 2021 Assembling Tailcone Skins Tailcone 3 $0.00    1   
27     Sep 29, 2021 Deburring Tailpieces Tailcone 3 $0.00    1   
26     Sep 29, 2021 Affixing Rudder Skin Rudder 3 $0.00    1   
25     Sep 29, 2021 Match Drilling Piano Hinges AntiServoTab 3 $0.00    1   
24     Sep 29, 2021 Inspecting wing ribs Wings 3 $0.00    1   
23     Sep 29, 2021 Assembling vertical stabilizer hinges V Stabilizer 3 $0.00    1   
22     Sep 29, 2021 Attatching spar caps to the spars Stabilator 3 $0.00    1   
21     Sep 22, 2021 Riveting the wings Wings 3 $0.00    2   
20     Sep 22, 2021 Riveting the rudder Rudder 3 $0.00    2   
19     Sep 22, 2021 Riveting Anti-Servio Tab AntiServoTab 3 $0.00    2   
18     Sep 22, 2021 Fabricating the skid bracket for the tail cone Tailcone 3 $0.00    2   
17     Sep 22, 2021 Assembling the spar cap for the stabilator Stabilator 3 $0.00    1   
16     Sep 22, 2021 Preparing the spar for the vertical stabilizer V Stabilizer 3 $0.00    1   
15     Sep 15, 2021 Hinge Angle and Horn Attach Angle for Stabilator Stabilator 3 $0.00    1   
14     Sep 15, 2021 Rudder Spar Assembly Rudder 3 $0.00    2   
13     Sep 15, 2021 Drill bit holder — drilling holes for bits DrillBitHold 3 $0.00    3   
12     Sep 15, 2021 Attaching Wig Skins (left wing) Wings 3 $0.00    2   
11     Sep 15, 2021 Riveting Anti-Servo Tab ribs AntiServoTab 3 $0.00    1   
10     Sep 15, 2021 Fluting tailcone ribs Tailcone 3 $0.00    1   
9     Sep 15, 2021 Assembling Spar Cap for Vertical Stabilizer V Stabilizer 3 $0.00    3   
8     Sep 08, 2021 Bit Holder DrillBitHold $0.00    0   
7     Sep 08, 2021 Hinge Angle Preparation Stabilator 2.5 $0.00    1   
6     Sep 08, 2021 Preparing AST Skin AntiServoTab 2.5 $0.00    1   
5     Sep 08, 2021 Hinge Bracket and Spar Cap Preparation V Stabilizer 2.5 $0.00    2   
4     Sep 08, 2021 Final Drilling and Deburring and Match Drilling Rudder 2.5 $0.00    1   
3     Sep 08, 2021 Left Wing Riveting and flaperons Wings 2.5 $0.00    3   
2     Sep 08, 2021 Breaking edges of the top and bottom skins of the tailbone Tailcone 2.5 $0.00    2   
1     Sep 01, 2021 First Build Day: Riveting the Wings Wings 1 $0.00    4   
------------ -------------- -------------
Totals235.5    $0.00    179   