Project: cbecker   -  
            Listing for Category : fuselage
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Charlie Becker   -  
Project:   Pirate Cub   -   VIEW REPORTS
Total Hours:103.5
Start/Last Date:Jan 30, 2011 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=cbecker

Home or Last Project Picture

Jul 07, 2020     Fabricated step - (1 hour)       Category: Fuselage
Fabricated rear step (stirrup) by bending and cutting and tack welding tubing. Followed the Wag Aero plans rather than PA-18 as it was easier to fabricate.


 
Jul 04, 2020     Brake pedal reinforcement bracket - (1 hour)       Category: Fuselage
Brake pedal reinforcement bracket Installed. Piper bolts this to the floorboard however I welded it to the fuselage frame. Next step is to drill the petal clamp holes.


 
Jul 04, 2020     Upper baggage compartment floorboard - (1 hour)       Category: Fuselage
Used template to cut and fit upper baggage compartment floorboard. Cut down the center and will install piano hinge later. The floorboard is very light weight since we made it out of composite materials.


 
Jun 28, 2020     Upper Baggage Shelf - (2 hours)       Category: Fuselage
Use template to determine the size of upper baggage shelf. Also added some piper channel reinforcement supports.


 
Jun 20, 2020     Rear shoulder harness attached point - (1 hour)       Category: Fuselage
Made template, cut material, deburred, and drilled holes for rear shoulder harness attach point fitting.


 
Jun 16, 2020     Finish welded front shoulder harness attached points - (.5 hour)       Category: Fuselage
Finish welded front shoulder harness attached points.


 
Jun 14, 2020     Fabricated fairlead holder - (1 hour)       Category: Fuselage
With the help of my friend Lee, fabricated 10 fairlead holders out of 7/8 x .058 tubing.


 
Jun 10, 2020     Nut plates - (1 hour)       Category: Fuselage
Drilled eight tabs for nut plates to attach rear fuselage plate


 
Jun 06, 2020     Shoulder harness attached points - (1 hour) Category: Fuselage
Determine where to attach shoulder harnesses. Use 10 inch center to center of hole spacing. Based on Bill Ross advice. He said that's what the Boeing he flies has. Tack welded in place
 
Jun 06, 2020     Shoulder harness attached points - (1 hour)       Category: Fuselage
Determine where to attach shoulder harnesses. Use 10 inch center to center of hole spacing. Based on Bill Ross advice. He said that's what the Boeing he flies has. Tack welded in place


 
Jun 03, 2020     Cut and fit floorboard for extended baggage compartment - (2 hours)       Category: Fuselage
Cut and fit plywood into the extended baggage compartment based on cardboard template. Used 1/4"" Baltic Birch plywood from Menards. The cuts were not one straight line as the fuselage curves back to the tail. We were able to use the straight edge but each side had to be divided into three straight cuts. Used a jigsaw and taped both sides of the plywood to limit breakout.


 
May 31, 2020     Seat belt bushings - (1 hour)       Category: Fuselage
Found bushing stock material at Fleet Farm to reduce the hole size from 1/2 to 3/8. Cut to size, deburred and press fit into place on seat belt attached fitting.


 
May 31, 2020     Extended baggage rivet nuts - (1 hour)       Category: Fuselage
Laid out, and drilled holes for rivet nuts needed to secure floorboards. Using 8-32 rivet nuts.


 
May 30, 2020     Installed floorboard tabs - (1 hour)       Category: Fuselage
Drilled holes, installed rivet nuts and tack welded floorboard tabs into place


 
May 24, 2020     Extended baggage floorboard - (2 hours)       Category: Fuselage
Create a template out of poster-board to determine size of extended baggage floorboard and then cut it out of thick cardboard to test it out.


 
May 23, 2020     Shoulder harness attach fittings - (1 hour)       Category: Fuselage
Fabricated shoulder harness attach fittings


 
May 22, 2020     Front Seat Belt       Category: Fuselage
Ordered RaceQuip 741001 Sportsman 5-Point Camlock Harness Set. These are 3 inch wide belts with a camlock. I'm going to use these in the front and then decide about the back. The belts are heavier duty than I was expecting.


 
Apr 19, 2020     Brake pedal support fabrication - (3 hours)       Category: Fuselage
Started on fabrication of the brake pedal reinforcement. Using the cutoff wheel on the Dremel tool. First drilled some holes in the corners with a step drill to provide a radius.


 
Apr 15, 2020     Upper Baggage Door Frame - (2 hours)       Category: Fuselage
Framed in upper baggage door.


 
Apr 08, 2020     Lower Baggage Door - (2 hours)       Category: Fuselage
Fabricated fit up and tack welded lower baggage door lower edge.


 
Apr 02, 2020     Rear Rudder Pedals - (2 hours)       Category: Fuselage
Wind rear rotor petals. Ready for tack welding.


 
Feb 28, 2020     Fabricated More Turtle Deck Tabs - (1 hour)       Category: Fuselage
Fabricated more of the turtle deck tabs; drilled, deburred and bent.


 
Feb 26, 2020     Turtle deck attachments       Category: Fuselage
Fabricated first of many attachments.


 
Jan 22, 2020     Welding Clean Up Category: Fuselage
Good to back in the shop. Spent the evening finishing off some welds; primarily on the door frame.
 
Nov 28, 2019     Left Upper Door       Category: Fuselage
Fabricated the upper left side door- I used two tools that may be of help to other builders. The first is this cheap little angle finder that is very useful for aircraft stuff given it's small size. The other is this digital angle finder. I used both depending on the area I was trying to fit the tool.


 
Nov 23, 2019     Hinges for upper door Category: Fuselage
 
Nov 23, 2019     Hinges for upper door       Category: Fuselage
Welded on the hinges for the upper door frame. If you look at the first photo, used a piece of angle iron to keep the hinge square. Also used washer under the door as a standoff to allow the hinge to stick out from the door frame.


 
Nov 19, 2019     Upper Door Frame Verticals       Category: Fuselage
Fitted and welded in verticals on the upper door frame that will attach the windshield to.


 
Nov 19, 2019     Upper Door Frame Verticals       Category: Fuselage
Fitted and welded in verticals on the upper door frame that will attach the windshield to.


 
Oct 27, 2019     Upper Door Frame       Category: Fuselage
Work continued on right upper door frame.


 
Oct 21, 2019     Upper Door Frame       Category: Fuselage
Cut and fit tubing for upper door frame on right side of fuselage. Ready for tacking. Used some strips of wood to provide the appropriate uniform spacing. At first I just eyeballed the joint, but after having problems with the fit up, I measured the angle, then divided by two to determine what angle I really wanted. This really helped dial in the fit up.


 
Oct 20, 2019     Starting on Upper Doors       Category: Fuselage
Using a sheet of particle board to provide a flat surface for the upper door frame.


 
Oct 15, 2019     Upper Door Frame Reinforcement       Category: Fuselage
Fit and tack welded some supports for the upper door frame. Used a wood template to determine where to place the supports to avoid any fuel lines.


 
Feb 16, 2019     Reinforced rear fuselage       Category: Fuselage
Added a couple of extra 1/2 tubes in an X pattern to reinforce the rear fuselage as it will get a lot of abuse.


 
Feb 03, 2019     Attached Rudder       Category: Fuselage
Spent quite a bit of time aligning the rudder and then a little time tack welding the hinges.


 
Jan 31, 2019     Welding Rudder Tabs       Category: Fuselage
Welded rudder and floor board tabs onto fuselage #1.


 
Aug 19, 2018     Extended Baggage       Category: Fuselage


 
Jun 29, 2018     Tail Wires       Category: Fuselage


 
Jun 27, 2018     Tail wire attachment       Category: Fuselage
Heat formed tail flying wire attachments.


 
Dec 05, 2017     Pulley Alignment       Category: Fuselage
Installation of forward pulley


 
Dec 16, 2016     Trying on the Fuselage for size       Category: Fuselage
Trying on the Fuselage for size


 
Dec 11, 2016     Lower Door Construction       Category: Fuselage
Lower Door Construction. Note: I made this out of square tubing from Menards. After building it, determined it was too heavy and did not use it.


 
Dec 04, 2016     Forward Tubing       Category: Fuselage
Fit up tubing in front of cockpit.


 
Dec 01, 2016     Fixturing up the motor mount fittings.       Category: Fuselage
Fixturing up the motor mount fittings.


 
Nov 28, 2016     Trimming the Longerons       Category: Fuselage
Always leave the longerons longer than you need for welding and then come back and trim to size. Your welder will thank you. I'm now getting ready to fit the motormount attach fittings.


 
Nov 25, 2016     Cathedral Baggage       Category: Fuselage
Fixturing the baggage area bump out.


 
 
Jul 08, 2011     Fuselage       Category: Fuselage


 
Jun 18, 2011     Reverse Dogleg       Category: Fuselage


 
Jun 12, 2011     Rosette Weld       Category: Fuselage
The lower longeron transition from 3/4"" tube to a a 5/8"" tube. A rosette weld is used along with welding the end of the tube to secure it in place.


 
Apr 20, 2011     Fuselage Sides       Category: Fuselage


 
Mar 28, 2011     Layout       Category: Fuselage


 