Project: N56BZ   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name: Craig Cousins   -  
Project:   Vans - RV-14A   -   VIEW REPORTS
Total Hours:1453.5
Total Flight Time:71
Start/Last Date:Dec 23, 2019 - Oct 10, 2021
Engine:Lycoming IO390
Panel:Dynon Skyview, Garmin 175
 
Friendly URL: https://eaabuilderslog.org?s=N56BZ

Home or Last Project Picture

Oct 13, 2021     First photo flight after painting - (1 hour)       Category: Photo Flight
We wanted some in-flight pictures


 
Sep 06, 2021     Side panels and seats final install - (20 hours)       Category: Interior Finish
Aero Classic Interior. Was quite a bit of work to install but I'm happy with the product.


 
Aug 17, 2021     Carpets - (6 hours)       Category: Interior Finish
Carpets installed. Seats ready. Need to work on the side panels next.


 
Apr 09, 2021     First flight - (10 hours)       Category: Photo Flight
Made some temporary seat cushions and installed quite a bit of sound deadening insulation. Waiting on the interior package to arrive in a few weeks. 8 month backlog. Photo's after the first flight. No snags, uneventful. Flew hands off.


 
Apr 05, 2021     Taxi tests - (1.5 hours)       Category: Inspection
Slow taxi, med speed run and full power run to 50 knots. All good


 
Apr 03, 2021     C of A time - (4 hours)       Category: Inspection
The DAR was Arnold Holmes put of Leesburg, FL. After reviewing the paperwork he proceeded with a mirror and flashlight to do a very thorough look at all critical points. Yes, he found a couple of items I needed to correct but they were small and I was able to do them while he continued his inspection. Pulled the plane out for the engine demo. All went well. It was a good experience.


 
Mar 25, 2021     Getting ready for the DAR - (24 hours)       Category: Fuselage
Not sure where to put this entry. Just working on a list of all small items and a detailed inspection preparing for the DAR next month


 
Mar 14, 2021     First run - (3 hours)       Category: Engine
After purging the fuel system and pre-oiling the engine, we brought it to life. Had a grounded P-lead on the left mag. Rectified that and all in the green.


 
NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.