Project: LincolnSport   -  
            Last 10 Project Activities / Entries :
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Paul Isakson   -  
Project:   Plans Built   -   VIEW REPORTS
Total Hours:487.5
Total Flight Time:
Total Expense:N/A
Start/Last Date:Nov 16, 2017 - No Finish Date
Engine:Mosler CB-40
Propeller:St Croix
 
Friendly URL: https://eaabuilderslog.org?s=LincolnSport

Home or Last Project Picture

Jun 25, 2023     New engine prep - (12 hours)       Category: Engine
Picked. Up double-throw crankshaft modified Lawrence A3 in Brodhead from the Keelch Aviation Museum. Modified existing stand A3 stand to accept the modified engine. Plumbed the oil pressure, oil temp, tach and ignition switch. Set the valves at .010 and timing at 29.5 degrees TDC. Drained oil. Ready for prelube and oil. Adjusted hub on prop to fire at horizontal position. Good spark and compression.


 
Nov 21, 2019     Glued cowl mounting blocks on - (6.00 hours)       Category: FWF
This is the forward firewall. Cut and fit 3/4" X 1" spruce to forward firewall for mounting 8-32 brass inserts to mount the cowling.


 
Nov 17, 2019     fabricated rear firewall - (4.00 hours)       Category: Research
Creased fire wall material to increase rigidity. Layed out, mounted, cut to shape, and installed.


 
Nov 16, 2019     cut SS 0.018 cover for engine backer - (5.00 hours)       Category: FWF
Finished plywood engine mounting backer plate. Covered with SS 0.018 material and mounted.


 
Nov 14, 2019     Fabricated front firewall - (6.00 hours)       Category: FWF
Fabricated front firewall out of 3/8" birch plywood. Will be covered with 0.018 SS.


 
Aug 14, 2019     fabricated tabs to weld to fuse - (8.00 hours)       Category: FWF
Fabricated brackets for the fuse to anchor corners. Fabricated brackets for hold down strap.
Welded in place.


 
Aug 13, 2019     Fuel Tank Fabricatio - (6.00 hours)       Category: FWF
Mocked up fuel tank with tag board and cut out aluminum. Pics show mocked up tank and sump ready for welding. Fabricated fuel tank tabs to mount to fuse.


 
Mar 27, 2019     made fuel tank add on for extra capacity - (5.00 hours)       Category: FWF
used tagboard template to create add on capacity of fuel out of aluminum 5052. it took longer than I thought, but is correct the first try.


 
Mar 26, 2019     cut hole for filler and mocked up add on - (4.00 hours)       Category: FWF
mocked up fuel tank add on for more capacity. cut hole for for filler neck.


 
Mar 23, 2019     rewelding of engine mounting ring do to mistake - (5.00 hours)       Category: FWF
after welding motor mount and mounting engine, found out I did not have the engine plumb with the fuselage. Cut off engine mounting ring and replumbed and is ready for the welder. Also made 4 gussts to weld in the corners.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.