Project: Toby   -  
            Listing for Category : tail feathers
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Toby Tremble   -  
Project:   PA-18 SQ2   -   VIEW REPORTS
Total Hours:926.5
Start/Last Date:Jan 30, 2022 - No Finish Date
Engine:Lycoming 0-360
 
Friendly URL: https://eaabuilderslog.org?s=Toby

Home or Last Project Picture

Sep 28, 2023     Elevators and rudder - (3 hours)       Category: Tail Feathers
Installed elevators and rudder. Cables and control links torqued, tensioned, and cotter keyed.


 
Sep 23, 2023     Horizontal stabilizers - (2 hours)       Category: Tail Feathers
Mounted horizontal stabilizers and drag wires. Squared tail and set tension on drag wires. Everything is torqued and torque sealed


 
Sep 19, 2023     Paint prep - (3 hours)       Category: Tail Feathers
Wet sanded and washed tail feathers. Prepped the spray booth for top coat after everything dries out.


 
Sep 18, 2023     Primer - (3 hours) Category: Tail Feathers
Quick sand and applied the second coat of primer on all the tail surfaces
 
Sep 17, 2023     Primer - (4 hours)       Category: Tail Feathers
Prepped all my tail surfaces and sprayed the first cross coat of superflight primer.


 
Sep 10, 2023     Covering - (10 hours)       Category: Tail Feathers
Horizontal stabilizers, elevators, and rudder are ready to prime and paint.


 
Sep 04, 2023     Covering - (5 hours)       Category: Tail Feathers
Shrank and surfaces to 350 and started rib stitching.


 
Aug 31, 2023     Covering - (7 hours)       Category: Tail Feathers
Elevators and Rudder covered and shrink to 250.


 
Aug 30, 2023     Covering - (6 hours)       Category: Tail Feathers
Horizontal stabilizer's covered and shrink to 250. Started working on an elevator.


 
Apr 03, 2023     Tail - (3 hours)       Category: Tail Feathers
Installed tail surfaces and drilled attachment bolt holes. Checked and adjusted control deflection.


 
Nov 18, 2022     Powder coating - (1 hour)       Category: Tail Feathers
Dropped the tail surfaces and slats off to get powder coated.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.