Project: EAbel   -  
            Listing for Category : fuselage
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Elliot Abel   -  
Project:   Bearhawk 5   -   VIEW REPORTS
Total Hours:618
Total Flight Time:
Total Expense:N/A
Start/Last Date:Sep 18, 2022 - No Finish Date
Engine:Lycoming
 
Friendly URL: https://eaabuilderslog.org?s=EAbel

Home or Last Project Picture

Mar 11, 2024     Covering Category: Fuselage
Two coats Polyspray on Fuse
 
Mar 10, 2024     Covering - (6 hours) Category: Fuselage
 
Mar 09, 2024     Covering - (6 hours) Category: Fuselage
 
Mar 08, 2024     Covering - (6 hours) Category: Fuselage
 
Mar 06, 2024     Covering - (6 hours) Category: Fuselage
 
Mar 05, 2024     Covering - (5 hours) Category: Fuselage
 
Mar 04, 2024     Covering - (6 hours) Category: Fuselage
 
Mar 03, 2024     Covering (sanding) - (7 hours) Category: Fuselage
 
Mar 02, 2024     Covering - (5 hours) Category: Fuselage
 
Mar 01, 2024     Covering started Fuse Silver - (6 hours) Category: Fuselage
 
Feb 29, 2024     Covering - (6 hours) Category: Fuselage
 
Feb 28, 2024     Covering - (6 hours) Category: Fuselage
 
Feb 24, 2024     Covering - (4 hours) Category: Fuselage
 
Feb 23, 2024     Covering (silver) - (5 hours) Category: Fuselage
 
Feb 22, 2024     Covering - (6 hours) Category: Fuselage
 
Feb 17, 2024     Covering - (7 hours) Category: Fuselage
 
Feb 16, 2024     Covering - (5 hours) Category: Fuselage
 
Feb 15, 2024     COvering (silver) - (6 hours) Category: Fuselage
 
Feb 10, 2024     covering - (6 hours) Category: Fuselage
 
Feb 08, 2024     Covering - (5 hours) Category: Fuselage
 
Feb 07, 2024     Covering finish work - (6 hours)       Category: Fuselage
Sprayed silver polyspray on flaps and year legs


 
Feb 05, 2024     Covering finish work - (6 hours) Category: Fuselage
 
Feb 04, 2024     Covering finish work - (5 hours) Category: Fuselage
 
Feb 03, 2024     Covering finish work - (6 hours)       Category: Fuselage
Sprayed polybrush


 
Jan 24, 2024     Fabric on flap - (7 hours) Category: Fuselage
Fabric and rib stitching
 
Jan 22, 2024     Fabric cont. - (6 hours) Category: Fuselage
 
Jan 21, 2024     Fabric - (6 hours)       Category: Fuselage
Fabric on fuse


 
Jan 12, 2024     Fabric tapes - (6 hours) Category: Fuselage
 
Jan 11, 2024     Fabric tapes - (8 hours) Category: Fuselage
Tape on fuse
 
Jan 10, 2024     Fabric misc parts - (5 hours) Category: Fuselage
 
Jan 08, 2024     Fabric - (8 hours) Category: Fuselage
Fabric misc parts
 
Dec 05, 2023     Left fabric - (8 hours)       Category: Fuselage
Installed fabric left side of fuse.


 
Nov 30, 2023     Misc - (6 hours)       Category: Fuselage
Installed rivenuts for fuse to wing intersection. Installed door opener posts. Fabric a few interior areas


 
Oct 22, 2023     Fabric tapes on side panels - (5 hours)       Category: Fuselage
Fabric tapes around corners and ends


 
Oct 21, 2023     Seat back - (3 hours)       Category: Fuselage
Fabric seat back. Test fit


 
Oct 15, 2023     Installed fabric on interior - (6 hours)       Category: Fuselage
Installed medium weight fabric on interior. Outside of front seats. Polyfiber process


 
Oct 15, 2023     Glued inspection panels - (4 hours)       Category: Fuselage
Glued inspection panels to tubing using DP 190 structural adhesive


 
Oct 14, 2023     Fabricated inspection panel - (6 hours) Category: Fuselage
Fabricated inspection panel under tail.
 
Apr 06, 2023     Doilies for interior fabric - (6 hours)       Category: Fuselage
Cut and polybrushed doilies on interior fabric. Cleaned tubing around. Attached fabric to outside of window to pull both sides down at same time.


 
Apr 05, 2023     Interior fabric - (8 hours)       Category: Fuselage
Glued fabric for interior. Shrunk and polybrushed.


 
Mar 20, 2023     Door latch guide - (1 hour)       Category: Fuselage
Fabricated for latch guide and primed


 
Mar 20, 2023     Kydex door panel - (2 hours)       Category: Fuselage
Cut and formed kydex interior panel for rear cargo door. Trimmed left interior panel kydex to fit. Bent 90 to make riged in rear of interior piece.


 
Mar 20, 2023     Rear left window frame - (1.5 hours)       Category: Fuselage
Permanently installed left rear window frame onto fuse using bucked rivets.


 
Mar 20, 2023     Front window skins - (3 hours)       Category: Fuselage
Riveted front window skins both sides after interior paint.


 
Mar 14, 2023     Painted interior panels - (8 hours)       Category: Fuselage
Painted interior frames and everything visible from within before interior install. Matched the tubing color.


 
Mar 03, 2023     Cable guards around pulleys - (3 hours)       Category: Fuselage
Installed Teflon guards to keep cable from contacting pulleys.


 
Feb 27, 2023     Doors cargo window - (5 hours)       Category: Fuselage
Riveted door skins on with 3/32 counter sink rivets. Counter sunk alumium skins 3/4 easy through. Rivet had barely sticks up but looks good and still grabs well. 2 inch spacing.


 
Feb 22, 2023     Windows and frames - (6 hours)       Category: Fuselage
Installed for frames and left windows. Installed stab inspection rings.


 
Feb 08, 2023     Primed Aluminum - (6 hours)       Category: Fuselage
Setup paint booth, primed aluminum panels and pieces.


 
Feb 07, 2023     Etched Aluminum - (5 hours)       Category: Fuselage
"Prekote" etched half alumium pieces with prekote and Scotch Brite.


 
Jan 31, 2023     Aft baggage cont. - (4 hours)       Category: Fuselage
Built sides , top and aft baggage pieces from alumium. Requires riveting and securing.


 
Jan 30, 2023     Aft baggage mod - (7 hours)       Category: Fuselage
Cut, Fabricated, and demurred aft bulkhead panel. Built aft baggage floor. Tested floor to 80 lbs limit. Slight deformation. Will limit aft baggage to 20 lbs at 4 g's. Complete aft baggage enclosure will increase strength. Total additional weight to build, 6lbs. Total enclosure size, 30 inches long, 5 wide on floor, 18 wide at top, 20 inches tall.


 
Jan 29, 2023     Deburring - (4 hours) Category: Fuselage
Deburred and removed plastic from Fuselage alumium pieces.
 
Jan 28, 2023     Deburring - (4 hours)       Category: Fuselage
Removed aluminum from Fuse, started deburring.


 
Jan 28, 2023     Deburring - (1 hour) Category: Fuselage
Started deburring all aluminum skins for primer prep.
 
Jan 28, 2023     Window frame - (2 hours)       Category: Fuselage
Drilled window frame. Fit plexi in window.


 
Jan 26, 2023     Window frame drilling - (1 hour) Category: Fuselage
Drilled holes for window frame , left side
 
Jan 20, 2023     Right window frame - (4 hours)       Category: Fuselage
Drilled holes for frame work on window. Cut plexi to fit inside window frame.


 
Jan 19, 2023     Right window frame - (3 hours)       Category: Fuselage
Fit and trimmed right window frame to airplane


 
Jan 14, 2023     Rear windows front strip - (2.5 hours)       Category: Fuselage
Fabricated leading edge strip in rear window to attach to door frame. Riveted 5 nutplates for future window replacement.


 
Jan 13, 2023     Plexi back windows - (4 hours)       Category: Fuselage
Cut out .100 plexi glass for cargo and back left windows


 
Jan 11, 2023     Front door bottom - (2 hours)       Category: Fuselage
Bent bottom of front doors inward to sit tight against airframe.


 
Jan 11, 2023     Cargo door gas strut - (3 hours)       Category: Fuselage
Installed gas strut on forward cargo door. Fabricated ear for strut end and drilled hole in door frame.


 
Jan 10, 2023     Door skins - (5 hours)       Category: Fuselage
Fit and trimmed front door skins.


 
Jan 09, 2023     Door skins - (2 hours)       Category: Fuselage
Fit door skins to front right and left sides


 
Jan 05, 2023     Right door - (4 hours)       Category: Fuselage
Bent for skin, positioned and drilled. Built stiffner


 
Jan 05, 2023     Plexi reinforcement - (2 hours) Category: Fuselage
Fabricated front of plexi reinforcement.
 
Dec 30, 2022     Cargo doors and windows - (3 hours)       Category: Fuselage
Trimmed and drilled cargo door skin to frames. Fitted window frame, drilled in place.


 
Dec 29, 2022     Cargo door skins - (4 hours)       Category: Fuselage
Adjusted and trimmed cargo door skins.


 
Dec 29, 2022     Front stab tube covering holes - (3 hours)       Category: Fuselage
Fabricated and installed front stab tube fabric inspection holes.


 
Dec 28, 2022     Front stab mount holes - (3 hours) Category: Fuselage
Installed fabric covering rings for leading edge stab adjustment.
 
Dec 17, 2022     Cargo door - (2 hours)       Category: Fuselage
Installed cargo door frame. Aligned, fit and installed latch mechanism.


 
Dec 17, 2022     Trimming alumium - (2 hours) Category: Fuselage
Installed bottom stringers permanently and trimmed around door seals
 
Dec 15, 2022     Gussets doors - (2 hours) Category: Fuselage
Installed aluminum gussets inside door frames
 
Dec 10, 2022     Stringers - (2.5 hours)       Category: Fuselage
Installed final underbelly stringers


 
Dec 02, 2022     ELT and remote com mount - (2 hours) Category: Fuselage
Fabricated ELT/Remote com mount aft of baggage.
 
Dec 01, 2022     Rivnuts finished installed - (2 hours)       Category: Fuselage
Rivnuts aft of baggage and other places complete. Installed nut plates for floor board cover below flap handle.


 
Dec 01, 2022     Skylights - (3 hours)       Category: Fuselage
Installed Skylight framework. Clecoed in place, awaiting riveting. Pieces are primed white.


 
Nov 30, 2022     Drilled floor boards - (4 hours)       Category: Fuselage
Finished drilling and triming all the floor boards.


 
Nov 29, 2022     Floorboards - (4 hours)       Category: Fuselage
Drilled holes for front floor boards to mount. Cut hold for fuel valve. Fabricated floorboard below flap handle.


 
Nov 28, 2022     Pulley covers - (1 hour)       Category: Fuselage
Fabricated 4 pulley covers


 
Nov 28, 2022     Brake reservoirs - (1 hour)       Category: Fuselage
Installed A-600 brake reservoirs


 
Nov 28, 2022     Nutserts holes - (4 hours)       Category: Fuselage
Drilled and filed nutserts (rivnuts) for floor boards


 
Nov 19, 2022     Floor Boards - (3 hours)       Category: Fuselage
Installed floor boards. Needs slight adjustment.


 
Nov 03, 2022     Top Stringers - (1 hour) Category: Fuselage
Clear coated and installed top stringers. Used avex pulled rivets
 
Nov 01, 2022     Riveted Stringers - (2 hours)       Category: Fuselage
Riveted stringers Right side


 
Oct 27, 2022     Stringers primed - (3 hours)       Category: Fuselage
Primed stringers where they meet the chromoly tubing to limit galvanic corrosion. Painted stringers where seen in the fuselage.


 
Oct 20, 2022     Flap handle cleaning - (1 hour)       Category: Fuselage
Cleaned inside flap handle to allow piston to move free.


 
Oct 18, 2022     Stringers - (2 hours)       Category: Fuselage
Cut and bent left and right side stringers


 
Oct 18, 2022     Stringers - (2 hours) Category: Fuselage
Cut and bent left and right side stringers
 
Oct 17, 2022     Stringers - (1 hour) Category: Fuselage
Drilled holes in mounts on top stringers
 
Oct 17, 2022     Pedal springs - (1 hour)       Category: Fuselage
Installed new 2.5 inch rudder pedal springs


 
Oct 13, 2022     Started installing stringers - (2 hours) Category: Fuselage
Installed top 2 stringers.
 