Project: MikeYRansS21   -  
            Listing for Category : avionics
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Michael Yankaitis   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1400.5
Total Flight Time:
Start/Last Date:Oct 14, 2019 - No Finish Date
Panel:Apollo 80 GPS, GRT EFIS-AP
 
Friendly URL: https://eaabuilderslog.org?s=MikeYRansS21

Home or Last Project Picture

Jul 03, 2022     Magnetometer, pitot-static - (2.0 hours) Category: Avionics
Calibrate magnetometer. Tested good. Test Pitot and static systems for leaks and response in EFIS. Both OK.
 
May 17, 2022     Boost pressure-map sensor - (2 hours)       Category: Avionics
Install, wire, plumb, and program new GRT map sensor to be used as a boost pressure sensor.


 
Apr 11, 2021     GPS antenna - (2 hours)       Category: Avionics
Mount Gps antenna on top fuselage just aft of skylight. Visit by Tech advisor Conrad.


 
Feb 01, 2021     Pitch servo-cylinders - (2 hours)       Category: Avionics
Correct mounting bolts for pitch servo, saftied. Prep cylinders for install. Finish fuel sump drain fairing.


 
Jan 27, 2021     Ap servo mounts-engine assy - (5 hours)       Category: Avionics
Make and install auto pilot servo mounts. Prep rods and assemble on crankshaft. Not torqued yet.


 
Jan 25, 2021     Garmin 296 - (4 hours)       Category: Avionics
Wire serial #6 from GRT 10.1 to portable garmin 296 plug. Fine tune design of oil filter mount.


 
Jan 07, 2021     Headphone and panel wiring - (6 hours)       Category: Avionics
Finish power wiring from switches on panel to plane. solder and install headphone jacks and test. All working fine. Squelch on 480 needs adjustment.


 
Jan 03, 2021     Install panel, Mag mount - (6 hours)       Category: Avionics
Put panel in plane. Start on wiring. Make and wire magnetometer mount.


 
Dec 26, 2020     Mount antennas etc. - (8 hours)       Category: Avionics
Mount antennas for ELT, com, adsb, Com. Cut aluminum for ELT, battery trays, autopilot mounts.


 
Dec 21, 2020     Misc panel wiring - (6 hours) Category: Avionics
Misc panel wiring. 10 gage to main and avionics master buss, Fuel pump & AP eng-diseng wire run, etc.
 
Dec 20, 2020     AFR Aux 6 Eis input - (2 hours) Category: Avionics
Connect and program AFR output to EIS Aux 6 input. Now AFR readout is on EFIS, with limits.
 
Dec 16, 2020     Trig T-22 debug - (3 hours)       Category: Avionics
Figure issue with T-22. Now online and checks ok. Bulk of wiring done.


 
Dec 15, 2020     Programming EFIS - (5 hours)       Category: Avionics
Start programming EFIS. Fire up panel, + GPS.


 
Dec 14, 2020     Panel wiring - (8 hours)       Category: Avionics
More panel wiring. Switches, ARINC module, EIS, etc


 
Dec 13, 2020     Panel labels - (4 hours)       Category: Avionics
Put labels on all panel components, front and back.


 
Dec 11, 2020     Panel wiring - (10 hours)       Category: Avionics
Start wiring panel. Mount ARINC 429 module, Trig T22, USB powered hub,


 
Dec 07, 2020     .Carbon fiber on instrument panel - (5 hours) Category: Avionics
Put carbon fiber vinyl on instrument panel and cut out openings. Start installing components.
 
Dec 04, 2020     General electrical work - (15 hours) Category: Avionics
Electrical work for the past week. Investigate and buy avionics and electrical items such as trig T22 transponder, ARINC 429 GRT module, Wiring connectors, Back up battery, ADSB antenna, Panel switches, remote oil filter mount, instrument panel carbon fiber wrap, Brady heat shrink labels, Voltage regulator, com antenna, fuel shutoff valve, etc.
 
Aug 14, 2019     Work on panel stuff - (20 hours)       Category: Avionics
Buy Garmin 480 and audio panel from guy in Boca Raton. Buy a bunch of misc items for panel. Wire 480 to audio panel and mount ready for stack.


 