Total Hours:1400.5
Total Flight Time:
Start/Last Date:Oct 14, 2019 - No Finish Date
Panel:Apollo 80 GPS, GRT EFIS-AP
 
Friendly URL: https://eaabuilderslog.org?s=MikeYRansS21

Home or Last Project Picture

Oct 26, 2022     Roll AP cable clamps, + - (2 hours)       Category: Controls
Install and torque new AP Roll cable clamps. Re-fit top cowling with new foam spacer blocks in place. Baffle seals much better now.


 
Oct 25, 2022     AP servo cable clamps - (3 hours)       Category: Controls
Machine new AP roll servo cable clamps out of steel, to replace the UHMW ones. A nice mill project.
Add foam blocks to upper cowl to block off large air gap on either side of flywheel near the top. 3 layers of glass to hold in place.


 
Jan 19, 2021     Misc - (4 hours)       Category: Controls
Send 1 piece engine nose bearings back. Control stick boots on, finish fuel line standoffs, start on door latches


 
Jan 18, 2021     control stick throws - (2 hours)       Category: Controls
Re-do elevator control stick throws. Move rod end bolt location. Make engine assembly jigs.


 
Jan 17, 2021     Control cables, 480 knob - (5 hours)       Category: Controls
Replace concentric knob on 480. Modify knobs to fit. Test, all ok. Remove push pull cable sub panel and make provisions for install cables next to AFR gage. Install oil cooler shutter and parking brake cable.


 
Jun 16, 2020     Misc - (6 hours)       Category: Controls
Finish pedals, control sticks, flap handle sup assembly. Add forward aileron cable and pulleys.


 