Feb 19, 2023     New door handles - (2.0 hours)       Category: Fuselage
Install new door latches, both sides. Left kick panel back on.


 
Dec 18, 2022     Rudder return - (2 hours)       Category: Fuselage
Finish rudder return system.


 
Dec 17, 2022     Rudder return cables - (1.5 hours) Category: Fuselage
Start on new rudder return cable installation. Just need to rivet plates to floor and adjust tensions.
 
Nov 28, 2022     Fuel tank migration issue - (2 hours) Category: Fuselage
Add aft fuel tank support from Rans to Right side tank. Left side not installed due to OAT probe in the way. Might re-locate in spring time.
 
Oct 23, 2022     Cowling install - (2 hours)       Category: Fuselage
Re-install cowling complete. Prepare for some ground test runs.


 
Oct 18, 2022     Cowling - (5.5 hours)       Category: Fuselage
Test fit cowling using finish fasteners. OK. Piano hinge keepers on. Start on baffling. Install outer prop spinner bulkhead, (Vans 13" Sensenich style). Torque and safety wire prop bolts.


 
Oct 17, 2022     Cowl - (7 hours)       Category: Fuselage
Nut plates for cowling all riveted onto fuselage. Air intake NACA scoop fit, bonded, and glassed in place.Oil dipstick door cut and hinge riveted in place


 
Oct 15, 2022     Cowling - (5 hours) Category: Fuselage
Final drill size and cleco upper cowl to fuselage. Drill and prep for nut plates
 
Oct 14, 2022     Cowling - (5.5 hours) Category: Fuselage
Fit upper cowling to fuselage. Install piano hinges between upper and lower.
 
Oct 13, 2022     Cowling - (6 hours)       Category: Fuselage
Trim upper and lower cowl pieces. Fit lower cowling to fuselage. Start on upper.


 
Oct 12, 2022     Cowling - (3 hours)       Category: Fuselage
Finish laying up lower cowling. De-mold.


 
Oct 11, 2022     Cowlings - (3 hours)       Category: Fuselage
De-mold top cowling. Good. Start lay-up of lower. 1/2 done.


 
Oct 10, 2022     Cowling top - (3 hours)       Category: Fuselage
Lay up top cowling part. 2 layers 1708, 2 layers 2x2 twill.


 
Oct 09, 2022     Mold-test run - (3.5 hours)       Category: Fuselage
PVA and Gelcoat on molds. Test run engine. Run up to WFO, and add boost. Get up to 113% power, 180 hp, 2650 static rpm, 14 GPH full rich.


 
Oct 08, 2022     Mold- W&B - (2 hours)       Category: Fuselage
De-mold lower cowling. Junk. Preliminary weigh plane to test scale and blocks. Nice.


 
Oct 07, 2022     Molds-scale - (5.5 hours)       Category: Fuselage
De-mold top. No good. Lay up lower. Same thing. Finish 1000# scale.


 
Oct 06, 2022     Glass work-scale - (4 hours)       Category: Fuselage
Lay up glass on top mold. Prep for lower. Resin attacking gelcoat. Junk. Start on 1000# scale


 
Oct 05, 2022     Molds - (2 hours)       Category: Fuselage
PVA and Blue gelcoat on molds


 
Sep 28, 2022     Mold work - (3 hours)       Category: Fuselage
Buff molds with two different grit compounds. Clean and apply one coat of mold release wax.


 
Sep 27, 2022     Cowl mold - (2.5 hours)       Category: Fuselage
Wet sand cowling molds with 1000 grit.


 
Sep 01, 2022     Cowling - (3.5 hours)       Category: Fuselage
More gelcoat patching. Wet sand. Make stand for lower mold.


 
Aug 30, 2022     Cowling - (2 hours) Category: Fuselage
Gelcoat patches on mold imperfections. Wet sand.
 
Aug 24, 2022     Cowling - (5 hours)       Category: Fuselage
Cut mold in half. Sand edges.Epoxy on edge voids. pull plug out and pitch.


 
Aug 21, 2022     Cowling - (2.5 hours)       Category: Fuselage
Glue wood to mold. Glass in place. To be used for stands.


 
Aug 17, 2022     Cowling - (5.5 hours)       Category: Fuselage
Layer of 2515 on most of mold over two days.


 
Aug 15, 2022     Cowling - (2 hours) Category: Fuselage
Layer of CSM on mold
 
Aug 14, 2022     Cowling - (2.5 hours) Category: Fuselage
1 layer of heavier glass on plug-mold
 
Aug 13, 2022     Cowling - (3.5 hours) Category: Fuselage
Veil and one coat layer of thin glass on plug
 
Aug 12, 2022     Cowling - (3 hours)       Category: Fuselage
3 coats of orange tooling gelcoat on plug


 
Aug 11, 2022     Cowling - (5 hours) Category: Fuselage
5 coats of wax on plug
 
Jul 19, 2022     Cowling - (2 hours)       Category: Fuselage
Primer on plug. Finish sand to 800


 
Jul 18, 2022     Cowling - (5 hours)       Category: Fuselage
Bondo-sand plug


 
Jul 14, 2022     Cowling - (3.5 hours)       Category: Fuselage
Sand, prime, spot putty


 
Jul 13, 2022     Cowling plug - (3 hours)       Category: Fuselage
Sand, mud and primer on plug


 
Jul 08, 2022     Cowling - (6 hours) Category: Fuselage
Mud and sanding on plug, repeat.
 
Jul 04, 2022     Cowling etc - (3 hours)       Category: Fuselage
More mud on cowling plug. Silicone on skylight. Trim tape on wing tips.


 
Jul 02, 2022     Plug work, safety wire - (4.0 hours)       Category: Fuselage
Sand and more mud on plug mold. Safety wire 3 turnbuckles. Make template, then cut dash cover material.


 
Jun 30, 2022     More plug work - (2 hours) Category: Fuselage
Sand on plug and add more mud, again.
 
Jun 30, 2022     Skylight bows - (4 hours)       Category: Fuselage
Re-form and rivet skylight bows on. More mud on cowl plug.Test fit windshield. Make skylight mating and trim strips.


 
Jun 28, 2022     Dash labels, sanding on plug - (2.5 hours)       Category: Fuselage
Make and install engine control dash labels. Sand on plug, add another layer of mud.


 
Jun 26, 2022     Skylight - (1.5 hours)       Category: Fuselage
Finish riveting of skylight mating strip. Silicone fillets on all exposed edges.


 
Jun 19, 2022     Windshield - (4.5 hours)       Category: Fuselage
Final rivet and bond windshield lower trim strip in place. Bond wing cuffs in place.


 
Jun 17, 2022     Windshield-Skylight - (2 hours)       Category: Fuselage
Final rivet skylight and Z strips on.


 
Jun 16, 2022     Windshield - (3.5 hours)       Category: Fuselage
Final fit of windshield and Z strips and cleco in place. Lifting lugs on axles. Gear fairings on.


 
Jun 15, 2022     windshield - (4.5 hours)       Category: Fuselage
Tinnermans on wing inspection holes. Install wing gap seal. Final install of flap gap seal. RE-do foam on some pieces using softer material. Install doors and door lift struts. Final rivet of rear door catch.


 
Jun 12, 2022     Windshield - Skylight - (3 hours)       Category: Fuselage
Move all painted trim parts to hanger. Foam tape on. Paint fiberglass lower windshield trim strip. Cleco skylight and trim strips on. Prep for full windshield fit-up.


 
Jun 10, 2022     Windshield-skylight - (6.5 hours)       Category: Fuselage
Remove skylight and windshield. Prep and paint all trim pieces. Paint black on windshield.


 
Jun 08, 2022     Windshield - (4 hours)       Category: Fuselage
Finish windshield fit-up. Lower trim drilled and clecoed in place. Fit, drill and cleco flap gap seals. More mud on cowling plug.


 
Jun 07, 2022     Windshield work - (4 hours)       Category: Fuselage
Trim windshield, Z trim strips fitted and clecoed, Cuffs cut and fitted.


 
Jun 06, 2022     Windshield and skylight - (3.5 hours)       Category: Fuselage
Cut, finish fit, drill and cleco skylight.


 
Jun 05, 2022     Windshield and skylight - (5 hours)       Category: Fuselage
Make and cleco skylight side trim and spacer strips. Make and fit skylight rear trim strip. Re-bend skylight bows, again. Install boot cowl top over dash. Run power wire for possible electric adj prop.


 
Jun 03, 2022     Cowl plug - (1.5 hours) Category: Fuselage
Sand cowling plug
 
May 27, 2022     Cowling plug - (1.5 hours) Category: Fuselage
Coat of joint compound on cowling plug
 
May 18, 2022     Mount H-stab + - (3 hours) Category: Fuselage
Mount H-stab back onto fuse. Needs final alignment. Moved plane from shop to hanger and moved all the associated parts also.
 
May 01, 2022     Plug work - (1.5 hours) Category: Fuselage
Try a layer of joint compound on front lower parts of plug. Takes too long to dry. Buy Evercoat Rage Gold filler.
 
Apr 26, 2022     Cowl plug - (3.5 hours)       Category: Fuselage
Add another 1/2" to cowl bottom air exit ramp, glass and epoxy in place.


 
Apr 25, 2022     cowl plug - (1.5 hours)       Category: Fuselage
Add second layer of glass to prop flange hole spacer.


 
Apr 24, 2022     Cowl plug - (2 hours) Category: Fuselage
Add spacer to inside of prop opening and one layer of glass
 
Apr 23, 2022     Cowl plug - (4 hours) Category: Fuselage
More glass on weak spots of cowl plug. Remove carb, intake plenum, throttle cable in prep for TBI.
 
Apr 22, 2022     Cowl Plug - (3.5 hours) Category: Fuselage
More glass on weak spots of plug.
 
Apr 19, 2022     cowl plug - (2 hours) Category: Fuselage
Epoxy and glass over rest of foam
 
Apr 18, 2022     Cowl Plug - (2.0 hours)       Category: Fuselage
Add foam to bottom of cowl making cooling exit ramp.


 
Apr 17, 2022     Cowl plug - (6.5 hours)       Category: Fuselage
Pull plug off fuselage. Make firewall jig and attach plug. Glass bottom portions of foam and cardboard.


 
Apr 16, 2022     Cowl plug - (2.5 hours)       Category: Fuselage
Epoxy and glass over foam and cardboard


 
Apr 15, 2022     Cowl plug - (5 hours)       Category: Fuselage
Finish rough shape of plug. Contour foam on top and sides. Add bump for exhaust stack


 
Apr 14, 2022     Cowl Plug - (4 hours)       Category: Fuselage
Cowl top, sides, top corners on


 
Apr 02, 2022     Cowling work - (6 hours)       Category: Fuselage
Cowl plug work.


 
May 28, 2021     Heat muff - (4 hours)       Category: Fuselage
Weld heat muff together as far as I can go without internal rods. Get permanent scavenge pump and make blast tube. Ready for install


 
May 27, 2021     Start on heat muff - (5 hours)       Category: Fuselage
Design and machine end pieces for heat muff.


 
Feb 04, 2021     Heat valve - (2 hours)       Category: Fuselage
Make heat valve from Vans kit. Make friction block for heat cable. Copied Rans design.


 
Jan 13, 2021     Oil cooler duct, kick panels - (4 hours)       Category: Fuselage
Finish fab of oil cooler duct, weld ends and weld on flapper valve. Install onto oil cooler with silicone. Fit kick panels. locate and install fuel valve placard.


 
Jan 12, 2021     oil cooler mount, etc - (6 hours)       Category: Fuselage
Fab oil cooler lower support and install, cut out sheet for cooler duct adapter. Bleed brakes, Fab primer solenoid, mini all fuse holder, and fuel flow firewall mounts. Run wires through firewall with firesleeve.


 
Jan 11, 2021     Tail closeout, etc - (8 hours)       Category: Fuselage
Fit and install tail cone closeout. Start on oil cooler mount. Pitot and AOA lines run to rear of cabin. Mount electrical firewall pass through fittings.Final torque and locktite of elevator rod ends and jamb nuts.


 
Jan 06, 2021     Misc - (6 hours)       Category: Fuselage
Make ground lugs for engine mount, more wiring, heat blanket on front side of firewall and silicone edges. Re-mount voltage regulator, parking brake valve, brake reservoir.


 
Jan 05, 2021     Interior wiring - (5 hours)       Category: Fuselage
Work on plane wiring, set screw stick grips, mount and wire voltage regulator.


 
Nov 17, 2020     Brake lines, etc - (3 hours) Category: Fuselage
Brake lines installed in front of pedals. Need two swivel elbows. O-320 case arrives from Divco. Order Overhaul parts from Aircraft specialties, Avionics and electrical parts orders placed.
 
Aug 26, 2020     rigging - (4 hours)       Category: Fuselage
Install front floorboard, rudder pedals, and control sticks


 
Aug 25, 2020     Paint silver on fuselage - (3 hours)       Category: Fuselage
Paint silver on top of fuselage


 
Aug 24, 2020     Mask for silver - (4 hours)       Category: Fuselage
Mask fuselage for silver color


 
Aug 22, 2020     Blue stripe painted on Fuselage - (3 hours)       Category: Fuselage
Paint blue stripe on fuselage and remove masking.


 
Aug 21, 2020     Flip fuse, engine misc - (6 hours)       Category: Fuselage
Flip fuselage, install main and tail gears. Mount engine on stand. Tape off fuse for blue stripe.


 
Jun 12, 2020     Firewall - rudder pedals - (5 hours)       Category: Fuselage
Fit rudder cable return pulley to firewall. Add firewall spacer strips and engine cowling mounting strips. Assemble rudder pedals. Fittings in rudder pedal master cylinders.


 
Jun 10, 2020     Boot cowl - (6 hours) Category: Fuselage
Remove boot cowl and add stringers. Rivet boot cowl bottom and sides to cage. Rivet Firewall on adding high temp silicone along flange.
 
Jun 09, 2020     Boot cowl - (6 hours)       Category: Fuselage
Finish fit up of boot cowl. Instrument panel visor, support angles. Remove, debur, prime parts.


 
Jun 08, 2020     Boot cowl - (7 hours)       Category: Fuselage
Fit floorboard, boot cowl sides, top and top sides. Fit instrument panel and panel frame. Fit firewall flange supports and engine cowling attach strips. Cleco all in place.


 
Jun 04, 2020     Cage sheetmetal - (6 hours)       Category: Fuselage
Rivet cage bottom and side sheet metal panels. Test fit main gear legs.


 
Jun 03, 2020     Cabin bottom and side skins - (7 hours)       Category: Fuselage
Fit, drill, deburr, cleco, prime cabin bottom, aft side and fwd side skins to cage. Ready for rivets. Fit, prime, rivnut and install seat slider stops.


 
Jun 02, 2020     Tailcone - (2 hours) Category: Fuselage
Final rivet top tailcone front skins to cage. Flip fuselage over on workbench.
 
Jun 01, 2020     Tailcone - (9 hours)       Category: Fuselage
Fit, cleco, remove, deburr, re-fit, rivet tailcone top forward skins on. Center row open to align tail to cage.


 
Jun 01, 2020     Tailcone - (9 hours) Category: Fuselage
Fit, cleco, remove, deburr, re-fit, rivet tailcone top forward skins on. Center row open to align tail to cage.
 
May 31, 2020     Aft baggage- S4 closeout - (5 hours)       Category: Fuselage
Locate and cleco holes for aft baggage floor. Fit S4 closeout, locate holes and cleco in place.


 
May 30, 2020     Tailcone - (4 hours)       Category: Fuselage
Rivet on top skins to tailcone. Re-fit aft baggage floor panels.


 
May 29, 2020     Tailcone - (2 hours)       Category: Fuselage
Make edge forming tool. Make extended baggage bulkhead support. Final fit of tailcone top skins.


 
May 28, 2020     tailcone - (3 hours)       Category: Fuselage
More fitting of top tailcone sheet metal. Stringers cut and clecoed in place. Final fitting of aft baggage sides.


 
May 27, 2020     Tailcone - (6 hours)       Category: Fuselage
Rivet tailcone to cage. Start on aft baggage panels. Start to fit top sheet metal. Rivet aft baggage floor supports on. Install rudder cables and trim servo wires.


 
May 26, 2020     Tailcone - (4 hours)       Category: Fuselage
Mate tailcone to cage. Match drill cage gussets to longerons. Make rear window supports. Make and prime skin doublers. Cleco tailcone to cage and double check alignment. Ready for riveting.


 
May 25, 2020     Tailcone - (2 hours)       Category: Fuselage
Make, fit, and prime longeron doublers. Match drill.


 
May 22, 2020     Tailcone - (3 hours)       Category: Fuselage
Rivet side skins to longerons and stringers.


 
May 21, 2020     Tailcone - (6.0 hours)       Category: Fuselage
Rivet longerons and stringers to tailcone bottom skin. Rivet bulkheads to skin. Prime side skin longerons and stringers. Cleco tailcone side skins, longerons and stringers.


 
May 20, 2020     Tailcone - (5 hours)       Category: Fuselage
Cut longerons, cleco to tailcone bottom skin. Prime edges of bulkheads. Cut up last of shipping crate. Finish inventory of Fuselage kit.


 
May 19, 2020     Tailcone - (4 hours)       Category: Fuselage
Prime Doublers. Rivet doublers on bulkheads S4-S11


 