EAA Builders Log Website
EMail address:
Password:
- Lost my password
close
EAA Builders Log
(An EAA website).
Help
Contact Us
About
Sign Up
Login
Project:
MikeYRansS21
-
Listing for Category : fuselage
(Please mouse-over any icon to get a description of that function).
Categories
Show All Entries
- (354)
Research
- (2)
Workshop
- (3)
Empennage
- (7)
Fuselage
- (102)
Firewall
Tail Feathers
- (12)
Wings
- (39)
Controls
- (6)
Avionics
- (19)
Lighting
Instrument Panel
- (5)
Landing Gear
- (3)
Engine
- (100)
Propeller
- (2)
Fuel System
- (3)
Interior Finish
- (26)
Paint / Decals
- (17)
Inspection
- (5)
Tools
Test run
- (3)
Builder Name:
Michael Yankaitis
-
Project:
Rans - S-21 Outbound
-
VIEW REPORTS
Total Hours:
1400.5
Total Flight Time:
Start/Last Date:
Oct 14, 2019 - No Finish Date
Panel:
Apollo 80 GPS, GRT EFIS-AP
Friendly URL:
https://eaabuilderslog.org?s=MikeYRansS21
Home or Last Project Picture
Feb 19, 2023
New door handles
- (2.0 hours)
Category: Fuselage
Install new door latches, both sides. Left kick panel back on.
47069BA9-8C10-4CCA-97BD-254565D0774D.jpeg
9329F5DE-2D5E-4219-9347-D563A39A8377.jpeg
Dec 18, 2022
Rudder return
- (2 hours)
Category: Fuselage
Finish rudder return system.
IMG_4289.jpg
IMG_4290.jpg
IMG_4291.jpg
8251E0E6-E50A-4BBA-A610-FD35CF21075D.jpeg
Dec 17, 2022
Rudder return cables
- (1.5 hours)
Category: Fuselage
Start on new rudder return cable installation. Just need to rivet plates to floor and adjust tensions.
Nov 28, 2022
Fuel tank migration issue
- (2 hours)
Category: Fuselage
Add aft fuel tank support from Rans to Right side tank. Left side not installed due to OAT probe in the way. Might re-locate in spring time.
Oct 23, 2022
Cowling install
- (2 hours)
Category: Fuselage
Re-install cowling complete. Prepare for some ground test runs.
IMG_4121.jpg
Oct 18, 2022
Cowling
- (5.5 hours)
Category: Fuselage
Test fit cowling using finish fasteners. OK. Piano hinge keepers on. Start on baffling. Install outer prop spinner bulkhead, (Vans 13" Sensenich style). Torque and safety wire prop bolts.
IMG_4112.jpg
IMG_4114.jpg
IMG_4119.jpg
Oct 17, 2022
Cowl
- (7 hours)
Category: Fuselage
Nut plates for cowling all riveted onto fuselage. Air intake NACA scoop fit, bonded, and glassed in place.Oil dipstick door cut and hinge riveted in place
IMG_4109.jpg
IMG_4110.jpg
IMG_4111.jpg
Oct 15, 2022
Cowling
- (5 hours)
Category: Fuselage
Final drill size and cleco upper cowl to fuselage. Drill and prep for nut plates
Oct 14, 2022
Cowling
- (5.5 hours)
Category: Fuselage
Fit upper cowling to fuselage. Install piano hinges between upper and lower.
Oct 13, 2022
Cowling
- (6 hours)
Category: Fuselage
Trim upper and lower cowl pieces. Fit lower cowling to fuselage. Start on upper.
IMG_4087.jpg
IMG_4088.jpg
IMG_4089.jpg
IMG_4092.jpg
Oct 12, 2022
Cowling
- (3 hours)
Category: Fuselage
Finish laying up lower cowling. De-mold.
IMG_4084.jpg
IMG_4085.jpg
Oct 11, 2022
Cowlings
- (3 hours)
Category: Fuselage
De-mold top cowling. Good. Start lay-up of lower. 1/2 done.
IMG_4083.jpg
Oct 10, 2022
Cowling top
- (3 hours)
Category: Fuselage
Lay up top cowling part. 2 layers 1708, 2 layers 2x2 twill.
IMG_4072.jpg
Oct 09, 2022
Mold-test run
- (3.5 hours)
Category: Fuselage
PVA and Gelcoat on molds. Test run engine. Run up to WFO, and add boost. Get up to 113% power, 180 hp, 2650 static rpm, 14 GPH full rich.
IMG_4057.jpg
IMG_4058.jpg
Oct 08, 2022
Mold- W&B
- (2 hours)
Category: Fuselage
De-mold lower cowling. Junk. Preliminary weigh plane to test scale and blocks. Nice.
IMG_4054.jpg
Oct 07, 2022
Molds-scale
- (5.5 hours)
Category: Fuselage
De-mold top. No good. Lay up lower. Same thing. Finish 1000# scale.
IMG_4052.jpg
IMG_4053.jpg
Oct 06, 2022
Glass work-scale
- (4 hours)
Category: Fuselage
Lay up glass on top mold. Prep for lower. Resin attacking gelcoat. Junk. Start on 1000# scale
IMG_4047.jpg
IMG_4049.jpg
IMG_4050.jpg
Oct 05, 2022
Molds
- (2 hours)
Category: Fuselage
PVA and Blue gelcoat on molds
IMG_4040.jpg
Sep 28, 2022
Mold work
- (3 hours)
Category: Fuselage
Buff molds with two different grit compounds. Clean and apply one coat of mold release wax.
IMG_4020.jpg
IMG_4021.jpg
Sep 27, 2022
Cowl mold
- (2.5 hours)
Category: Fuselage
Wet sand cowling molds with 1000 grit.
IMG_4016.jpg
IMG_4017.jpg
Sep 01, 2022
Cowling
- (3.5 hours)
Category: Fuselage
More gelcoat patching. Wet sand. Make stand for lower mold.
IMG_3974.jpg
IMG_3975.jpg
IMG_3976.jpg
Aug 30, 2022
Cowling
- (2 hours)
Category: Fuselage
Gelcoat patches on mold imperfections. Wet sand.
Aug 24, 2022
Cowling
- (5 hours)
Category: Fuselage
Cut mold in half. Sand edges.Epoxy on edge voids. pull plug out and pitch.
IMG_3931.jpg
IMG_3932.jpg
IMG_3933.jpg
IMG_3934.jpg
IMG_3935.jpg
Aug 21, 2022
Cowling
- (2.5 hours)
Category: Fuselage
Glue wood to mold. Glass in place. To be used for stands.
IMG_3929.jpg
Aug 17, 2022
Cowling
- (5.5 hours)
Category: Fuselage
Layer of 2515 on most of mold over two days.
IMG_3914.jpg
IMG_3915.jpg
Aug 15, 2022
Cowling
- (2 hours)
Category: Fuselage
Layer of CSM on mold
Aug 14, 2022
Cowling
- (2.5 hours)
Category: Fuselage
1 layer of heavier glass on plug-mold
Aug 13, 2022
Cowling
- (3.5 hours)
Category: Fuselage
Veil and one coat layer of thin glass on plug
Aug 12, 2022
Cowling
- (3 hours)
Category: Fuselage
3 coats of orange tooling gelcoat on plug
IMG_3905.jpg
IMG_3907.jpg
Aug 11, 2022
Cowling
- (5 hours)
Category: Fuselage
5 coats of wax on plug
Jul 19, 2022
Cowling
- (2 hours)
Category: Fuselage
Primer on plug. Finish sand to 800
IMG_3814.jpg
IMG_3822.jpg
Jul 18, 2022
Cowling
- (5 hours)
Category: Fuselage
Bondo-sand plug
IMG_3813.jpg
Jul 14, 2022
Cowling
- (3.5 hours)
Category: Fuselage
Sand, prime, spot putty
IMG_3806.jpg
Jul 13, 2022
Cowling plug
- (3 hours)
Category: Fuselage
Sand, mud and primer on plug
IMG_3804.jpg
Jul 08, 2022
Cowling
- (6 hours)
Category: Fuselage
Mud and sanding on plug, repeat.
Jul 04, 2022
Cowling etc
- (3 hours)
Category: Fuselage
More mud on cowling plug. Silicone on skylight. Trim tape on wing tips.
IMG_3768.jpg
IMG_3769.jpg
Jul 02, 2022
Plug work, safety wire
- (4.0 hours)
Category: Fuselage
Sand and more mud on plug mold. Safety wire 3 turnbuckles. Make template, then cut dash cover material.
IMG_3756.jpg
IMG_3757.jpg
IMG_3769.jpg
Jun 30, 2022
More plug work
- (2 hours)
Category: Fuselage
Sand on plug and add more mud, again.
Jun 30, 2022
Skylight bows
- (4 hours)
Category: Fuselage
Re-form and rivet skylight bows on. More mud on cowl plug.Test fit windshield. Make skylight mating and trim strips.
IMG_3670.jpg
IMG_3671.jpg
Jun 28, 2022
Dash labels, sanding on plug
- (2.5 hours)
Category: Fuselage
Make and install engine control dash labels. Sand on plug, add another layer of mud.
IMG_3755.jpg
Jun 26, 2022
Skylight
- (1.5 hours)
Category: Fuselage
Finish riveting of skylight mating strip. Silicone fillets on all exposed edges.
IMG_3745.jpg
Jun 19, 2022
Windshield
- (4.5 hours)
Category: Fuselage
Final rivet and bond windshield lower trim strip in place. Bond wing cuffs in place.
IMG_3736.jpg
IMG_3737.jpg
IMG_3740.jpg
Jun 17, 2022
Windshield-Skylight
- (2 hours)
Category: Fuselage
Final rivet skylight and Z strips on.
IMG_3731.jpg
IMG_3732.jpg
Jun 16, 2022
Windshield
- (3.5 hours)
Category: Fuselage
Final fit of windshield and Z strips and cleco in place. Lifting lugs on axles. Gear fairings on.
IMG_3727.jpg
IMG_3728.jpg
IMG_3730.jpg
Jun 15, 2022
windshield
- (4.5 hours)
Category: Fuselage
Tinnermans on wing inspection holes. Install wing gap seal. Final install of flap gap seal. RE-do foam on some pieces using softer material. Install doors and door lift struts. Final rivet of rear door catch.
IMG_3722.jpg
IMG_3723.jpg
IMG_3725.jpg
Jun 12, 2022
Windshield - Skylight
- (3 hours)
Category: Fuselage
Move all painted trim parts to hanger. Foam tape on. Paint fiberglass lower windshield trim strip. Cleco skylight and trim strips on. Prep for full windshield fit-up.
IMG_3721.jpg
Jun 10, 2022
Windshield-skylight
- (6.5 hours)
Category: Fuselage
Remove skylight and windshield. Prep and paint all trim pieces. Paint black on windshield.
IMG_3719.jpg
IMG_3720.jpg
Jun 08, 2022
Windshield
- (4 hours)
Category: Fuselage
Finish windshield fit-up. Lower trim drilled and clecoed in place. Fit, drill and cleco flap gap seals. More mud on cowling plug.
IMG_3711.jpg
IMG_3712.jpg
Jun 07, 2022
Windshield work
- (4 hours)
Category: Fuselage
Trim windshield, Z trim strips fitted and clecoed, Cuffs cut and fitted.
IMG_3709.jpg
Jun 06, 2022
Windshield and skylight
- (3.5 hours)
Category: Fuselage
Cut, finish fit, drill and cleco skylight.
IMG_3701.jpg
Jun 05, 2022
Windshield and skylight
- (5 hours)
Category: Fuselage
Make and cleco skylight side trim and spacer strips. Make and fit skylight rear trim strip. Re-bend skylight bows, again. Install boot cowl top over dash. Run power wire for possible electric adj prop.
IMG_3696.jpg
IMG_3697.jpg
IMG_3698.jpg
IMG_3699.jpg
Jun 03, 2022
Cowl plug
- (1.5 hours)
Category: Fuselage
Sand cowling plug
May 27, 2022
Cowling plug
- (1.5 hours)
Category: Fuselage
Coat of joint compound on cowling plug
May 18, 2022
Mount H-stab +
- (3 hours)
Category: Fuselage
Mount H-stab back onto fuse. Needs final alignment. Moved plane from shop to hanger and moved all the associated parts also.
May 01, 2022
Plug work
- (1.5 hours)
Category: Fuselage
Try a layer of joint compound on front lower parts of plug. Takes too long to dry. Buy Evercoat Rage Gold filler.
Apr 26, 2022
Cowl plug
- (3.5 hours)
Category: Fuselage
Add another 1/2" to cowl bottom air exit ramp, glass and epoxy in place.
IMG_3562.jpg
Apr 25, 2022
cowl plug
- (1.5 hours)
Category: Fuselage
Add second layer of glass to prop flange hole spacer.
IMG_3560.jpg
IMG_3561.jpg
IMG_3563.jpg
Apr 24, 2022
Cowl plug
- (2 hours)
Category: Fuselage
Add spacer to inside of prop opening and one layer of glass
Apr 23, 2022
Cowl plug
- (4 hours)
Category: Fuselage
More glass on weak spots of cowl plug. Remove carb, intake plenum, throttle cable in prep for TBI.
Apr 22, 2022
Cowl Plug
- (3.5 hours)
Category: Fuselage
More glass on weak spots of plug.
Apr 19, 2022
cowl plug
- (2 hours)
Category: Fuselage
Epoxy and glass over rest of foam
Apr 18, 2022
Cowl Plug
- (2.0 hours)
Category: Fuselage
Add foam to bottom of cowl making cooling exit ramp.
IMG_3546.jpg
Apr 17, 2022
Cowl plug
- (6.5 hours)
Category: Fuselage
Pull plug off fuselage. Make firewall jig and attach plug. Glass bottom portions of foam and cardboard.
IMG_3543.jpg
IMG_3544.jpg
Apr 16, 2022
Cowl plug
- (2.5 hours)
Category: Fuselage
Epoxy and glass over foam and cardboard
IMG_3541.jpg
Apr 15, 2022
Cowl plug
- (5 hours)
Category: Fuselage
Finish rough shape of plug. Contour foam on top and sides. Add bump for exhaust stack
IMG_3537.jpg
IMG_3538.jpg
IMG_3539.jpg
IMG_3540.jpg
Apr 14, 2022
Cowl Plug
- (4 hours)
Category: Fuselage
Cowl top, sides, top corners on
IMG_3536.jpg
Apr 02, 2022
Cowling work
- (6 hours)
Category: Fuselage
Cowl plug work.
IMG_3499.jpg
IMG_3500.jpg
IMG_3515.jpg
May 28, 2021
Heat muff
- (4 hours)
Category: Fuselage
Weld heat muff together as far as I can go without internal rods. Get permanent scavenge pump and make blast tube. Ready for install
IMG_2196.jpg
IMG_2197.jpg
IMG_2198.jpg
IMG_2200.jpg
IMG_2202.jpg
May 27, 2021
Start on heat muff
- (5 hours)
Category: Fuselage
Design and machine end pieces for heat muff.
IMG_2194.jpg
IMG_2195.jpg
Feb 04, 2021
Heat valve
- (2 hours)
Category: Fuselage
Make heat valve from Vans kit. Make friction block for heat cable. Copied Rans design.
20210206_082033.jpg
20210206_082049.jpg
Jan 13, 2021
Oil cooler duct, kick panels
- (4 hours)
Category: Fuselage
Finish fab of oil cooler duct, weld ends and weld on flapper valve. Install onto oil cooler with silicone. Fit kick panels. locate and install fuel valve placard.
20210113_163849.jpg
20210113_175607.jpg
20210113_175624.jpg
Jan 12, 2021
oil cooler mount, etc
- (6 hours)
Category: Fuselage
Fab oil cooler lower support and install, cut out sheet for cooler duct adapter. Bleed brakes, Fab primer solenoid, mini all fuse holder, and fuel flow firewall mounts. Run wires through firewall with firesleeve.
20210112_122709.jpg
20210112_122736.jpg
20210112_142414.jpg
20210112_142418.jpg
20210112_142425.jpg
20210112_170128.jpg
20210112_173843.jpg
Jan 11, 2021
Tail closeout, etc
- (8 hours)
Category: Fuselage
Fit and install tail cone closeout. Start on oil cooler mount. Pitot and AOA lines run to rear of cabin. Mount electrical firewall pass through fittings.Final torque and locktite of elevator rod ends and jamb nuts.
20210111_173507.jpg
20210111_173538.jpg
20210111_173553.jpg
20210111_173606.jpg
20210111_181645.jpg
Jan 06, 2021
Misc
- (6 hours)
Category: Fuselage
Make ground lugs for engine mount, more wiring, heat blanket on front side of firewall and silicone edges. Re-mount voltage regulator, parking brake valve, brake reservoir.
20210106_153549.jpg
20210106_162303.jpg
Jan 05, 2021
Interior wiring
- (5 hours)
Category: Fuselage
Work on plane wiring, set screw stick grips, mount and wire voltage regulator.
20210106_122853.jpg
20210106_152401.jpg
Nov 17, 2020
Brake lines, etc
- (3 hours)
Category: Fuselage
Brake lines installed in front of pedals. Need two swivel elbows. O-320 case arrives from Divco. Order Overhaul parts from Aircraft specialties, Avionics and electrical parts orders placed.
Aug 26, 2020
rigging
- (4 hours)
Category: Fuselage
Install front floorboard, rudder pedals, and control sticks
20200828_131028.jpg
Aug 25, 2020
Paint silver on fuselage
- (3 hours)
Category: Fuselage
Paint silver on top of fuselage
20200825_110626.jpg
20200825_160335.jpg
Aug 24, 2020
Mask for silver
- (4 hours)
Category: Fuselage
Mask fuselage for silver color
20200825_110615.jpg
Aug 22, 2020
Blue stripe painted on Fuselage
- (3 hours)
Category: Fuselage
Paint blue stripe on fuselage and remove masking.
20200822_135247.jpg
Aug 21, 2020
Flip fuse, engine misc
- (6 hours)
Category: Fuselage
Flip fuselage, install main and tail gears. Mount engine on stand. Tape off fuse for blue stripe.
20200821_105346.jpg
20200821_174724.jpg
Jun 12, 2020
Firewall - rudder pedals
- (5 hours)
Category: Fuselage
Fit rudder cable return pulley to firewall. Add firewall spacer strips and engine cowling mounting strips. Assemble rudder pedals. Fittings in rudder pedal master cylinders.
20200617_084423.jpg
Jun 10, 2020
Boot cowl
- (6 hours)
Category: Fuselage
Remove boot cowl and add stringers. Rivet boot cowl bottom and sides to cage. Rivet Firewall on adding high temp silicone along flange.
Jun 09, 2020
Boot cowl
- (6 hours)
Category: Fuselage
Finish fit up of boot cowl. Instrument panel visor, support angles. Remove, debur, prime parts.
20200609_101949.jpg
20200609_101954.jpg
Jun 08, 2020
Boot cowl
- (7 hours)
Category: Fuselage
Fit floorboard, boot cowl sides, top and top sides. Fit instrument panel and panel frame. Fit firewall flange supports and engine cowling attach strips. Cleco all in place.
20200608_130018.jpg
20200608_184423.jpg
Jun 04, 2020
Cage sheetmetal
- (6 hours)
Category: Fuselage
Rivet cage bottom and side sheet metal panels. Test fit main gear legs.
20200604_135610.jpg
20200604_135624.jpg
Jun 03, 2020
Cabin bottom and side skins
- (7 hours)
Category: Fuselage
Fit, drill, deburr, cleco, prime cabin bottom, aft side and fwd side skins to cage. Ready for rivets. Fit, prime, rivnut and install seat slider stops.
20200604_112132.jpg
Jun 02, 2020
Tailcone
- (2 hours)
Category: Fuselage
Final rivet top tailcone front skins to cage. Flip fuselage over on workbench.
Jun 01, 2020
Tailcone
- (9 hours)
Category: Fuselage
Fit, cleco, remove, deburr, re-fit, rivet tailcone top forward skins on. Center row open to align tail to cage.
20200601_123142.jpg
20200601_145107.jpg
20200601_174246.jpg
20200601_174309.jpg
20200601_193058.jpg
Jun 01, 2020
Tailcone
- (9 hours)
Category: Fuselage
Fit, cleco, remove, deburr, re-fit, rivet tailcone top forward skins on. Center row open to align tail to cage.
May 31, 2020
Aft baggage- S4 closeout
- (5 hours)
Category: Fuselage
Locate and cleco holes for aft baggage floor. Fit S4 closeout, locate holes and cleco in place.
20200531_085729.jpg
20200531_141003.jpg
May 30, 2020
Tailcone
- (4 hours)
Category: Fuselage
Rivet on top skins to tailcone. Re-fit aft baggage floor panels.
20200530_183610.jpg
May 29, 2020
Tailcone
- (2 hours)
Category: Fuselage
Make edge forming tool. Make extended baggage bulkhead support. Final fit of tailcone top skins.
20200529_091545.jpg
20200529_110624.jpg
May 28, 2020
tailcone
- (3 hours)
Category: Fuselage
More fitting of top tailcone sheet metal. Stringers cut and clecoed in place. Final fitting of aft baggage sides.
20200528_111347.jpg
20200528_111352.jpg
May 27, 2020
Tailcone
- (6 hours)
Category: Fuselage
Rivet tailcone to cage. Start on aft baggage panels. Start to fit top sheet metal. Rivet aft baggage floor supports on. Install rudder cables and trim servo wires.
20200527_095627.jpg
20200527_153948.jpg
20200527_153959.jpg
20200527_172025.jpg
20200527_175608.jpg
20200527_175616.jpg
May 26, 2020
Tailcone
- (4 hours)
Category: Fuselage
Mate tailcone to cage. Match drill cage gussets to longerons. Make rear window supports. Make and prime skin doublers. Cleco tailcone to cage and double check alignment. Ready for riveting.
20200526_191111.jpg
20200526_191118.jpg
20200526_191128.jpg
May 25, 2020
Tailcone
- (2 hours)
Category: Fuselage
Make, fit, and prime longeron doublers. Match drill.
20200525_130626.jpg
May 22, 2020
Tailcone
- (3 hours)
Category: Fuselage
Rivet side skins to longerons and stringers.
20200522_124556.jpg
May 21, 2020
Tailcone
- (6.0 hours)
Category: Fuselage
Rivet longerons and stringers to tailcone bottom skin. Rivet bulkheads to skin. Prime side skin longerons and stringers. Cleco tailcone side skins, longerons and stringers.
20200521_100551.jpg
20200521_101812.jpg
20200521_145447.jpg
20200521_145510.jpg
20200521_190719.jpg
20200521_190730.jpg
May 20, 2020
Tailcone
- (5 hours)
Category: Fuselage
Cut longerons, cleco to tailcone bottom skin. Prime edges of bulkheads. Cut up last of shipping crate. Finish inventory of Fuselage kit.
20200520_200128.jpg
20200520_201132.jpg
May 19, 2020
Tailcone
- (4 hours)
Category: Fuselage
Prime Doublers. Rivet doublers on bulkheads S4-S11
20200519_183413.jpg
NOTE: This information is strictly used for the EAA Builders Log project within the
EAA organization
.
-
Policy
-
© Copyright 2024 Brevard Web Pro, Inc.