Builder Name:Joseph Millette   -  
Project:   Zenith   -   VIEW REPORTS
Total Hours:1151
Total Flight Time:
Start/Last Date:Jul 30, 2020 - Mar 31, 2022
Engine:Viking 130
Propeller:Whirlwind
Panel:GRT 10.1 Sport
 
Friendly URL: https://eaabuilderslog.org?s=JMillette

Home or Last Project Picture

Jul 25, 2021     Cowl Continued - (5 hours)       Category: Engine
Since i cut the cowl too short. I had to correct the mistake and remount the lower cowl. The space between the spinner backplate and the cowl is not increased to 20mm. I plan on doing some bodywork to decrease the space. Started upper cowl.

While installing the lower hinge system for the cowling, the rivets need up close to the edge. I measured and determined while close, I was within the minimum of 1.5mm but not within the suggested 10mm from the edge on the skin. I had my friend (A&P Robert McCoy) inspect the issue and he determined that it will be safe.


 
Aug 21, 2021     First Start of Viking Engine - (4 hours) Category: Engine
Today I performed the first start of the Viking 130 engine. This was completed without the prop installed to make sure wiring was installed properly and also to make sure there were no leaks in the cooling system. All went smooth. I followed Viking Aircraft Engines' recommended start checklist.
 
Aug 01, 2021     Electrical of Engine/circuit breakers - (8 hours)       Category: Engine
Completed wiring the circuit breakers for the engine power. Wired switches for engine controls. Installed dual throttle. Installed engine sensor wiring.


 
Aug 07, 2021     Electrical completion for Engine - (8 hours)       Category: Engine
Painted radiator shroud and installed fuel line from the header tank to engine.
I painted the new 2in longer nose strut and completed installing the fuel line from header to Engine.


 
Aug 14, 2021     Cowl Work - (16 hours)       Category: Engine
Completed some bodywork on the cowling to correct the gap between the cowling and the spinner. I also shortened the exhaust pipe to the recommended 2in length.
Pick foam was used to mold the front of the cowling to match the spinner then 2 layers of 2oz fiberglass and epoxy resins were used to bond.


 
May 25, 2021     Corrected Radiator plumbing - (2 hours)       Category: Engine
I made the following corrections to the Radiator plumbing.
Mounted overflow is lower than the cap.
Installed clamps.


 
May 23, 2021     Radiator Plumbing - (4 hours)       Category: Engine
Installed radiator hose and mounted ECU. Installed GRT Engine sensors. Coolant Temp, Oil Pressure, Gearbox temp.


 
 
Apr 22, 2021     Ordered Eng. and Firewall forward kit Category: Engine
Ordered Engine and FWF kit from Viking Aircraft Engines.
 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.
OurChapter.org is a FREE website to help you manage your chapter, organization, group or family functions. Totally free; not a trial; with no ads or marketing!   Management functions include:
Roster Management, Send Email Campaigns, Reports / PDFs, Photos/Newsletters Viewing, Forums, Calendar, Sign-in, Dues, Attendence, Event Mgmt., Resource Schedule, Finance and Survey.
ChapterPlace.com is a FREE website to help you manage your chapter, organization, group or family functions. Totally free; not a trial; with no ads or marketing!   Management functions include:
Roster Management, Send Email Campaigns, Reports / PDFs, Photos/Newsletters Viewing, Forums, Calendar, Sign-in, Dues, Attendence, Event Mgmt., Resource Schedule, Finance and Survey.