Project: NewtonRV-14A   -  
            Listing for Category : 18:fuel tank
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Dustin Newton   -  
Project:   Vans - RV-14A
Total Hours:1178.7
Total Flight Time:
Start/Last Date:Apr 09, 2021 - No Finish Date
Engine:Lycoming IO-390-119EXP
Propeller:TBD
Panel:AFS/Dynon/Avidyne
 
Friendly URL: https://eaabuilderslog.org?s=NewtonRV-14A

Home or Last Project Picture

Feb 25, 2023     Fuel Tank: Fitting tank to left wing - (5.3 hours) Category: 18:Fuel Tank
 
Feb 18, 2023     Fuel Tank: final fitting of right tank - (3.8 hours) Category: 18:Fuel Tank
 
Feb 16, 2023     Fuel Tank: right tank cont fitting - (1.0 hour)       Category: 18:Fuel Tank


 
Feb 17, 2023     Fuel Tank: fitting of right tank - (2.3 hours) Category: 18:Fuel Tank
 
Feb 15, 2023     Fuel Tank: fitting right tank - (1.5 hours) Category: 18:Fuel Tank
The locations where the skins butts up takes a lot of time to adjust correctly.
 
Dec 31, 2022     Fuel Tanks: Machine countersink fuselage attach brackets - (2.5 hours)       Category: 18:Fuel Tank
5 holes per tank have to be machine countersink and primed. This completes the tank construction.


 
Dec 30, 2022     Fuel Tanks: Pressure Testing - (3.5 hours)       Category: 18:Fuel Tank
Completed pressure testing both tanks. No leaks were detected.


 
Dec 26, 2022     Fuel Tanks: install baffle rivets that were intentionally skipped during construction - (1.0 hour)       Category: 18:Fuel Tank
This completes construction of the tanks. Only thing remaining is pressure testing them.


 
Dec 16, 2022     Fuel Tanks: prepping for baffle installation - (4.0 hours) Category: 18:Fuel Tank
 
Dec 03, 2022     Fuel Tanks: Water Testing Right Tank - (2.8 hours)       Category: 18:Fuel Tank
Rebuilt cradles to support the additional weight of the water. Filled the right tank with water & mild dish soap.


 
Dec 04, 2022     Fuel Tanks: Right Tank passed, drained right tank and filled left tank - (2.0 hours) Category: 18:Fuel Tank
Only leak in right tank was through the filler cap flange. After tightening the latch and retesting, no leak was observed.
 
Nov 16, 2022     Fuel Tank: fitted sender for left tank - (1.0 hour)       Category: 18:Fuel Tank


 
Nov 10, 2022     Fuel Tanks: Finish sealing right tank j-stiffener - (.7 hour) Category: 18:Fuel Tank
 
Nov 09, 2022     Fuel Tanks: Riveting j-stiffener right tank - (2.3 hours) Category: 18:Fuel Tank
 
Nov 07, 2022     Fuel Tanks: Continue riveting ribs in the right tank (2) - (3.2 hours) Category: 18:Fuel Tank
 
Nov 06, 2022     Fuel Tank: installed three ribs in right tank - (6.5 hours)       Category: 18:Fuel Tank
This is a slow process!!!!!


 
Nov 04, 2022     Fuel Tanks: begin riveting ribs left side (2) - (4.0 hours)       Category: 18:Fuel Tank


 
Nov 03, 2022     Fuel Tank: Dimple Ribs, Finish Prepping Final Rib - (1.5 hours) Category: 18:Fuel Tank
 
Oct 31, 2022     Fuel Tank: Drill out 3/16 rivets filling machine holes - (2.0 hours)       Category: 18:Fuel Tank
After thinking for several weeks about the rivets that I had installed to plug the machining holes in the end ribs for the fuel tanks, I decided that I just wasn't satisfied with them. I decided to drill them all out and order replacements. The biggest problem was the rivets were simply too long to properly set. Installing using a couple of different methods into a piece of scrap ultimately led to the right procedure. New rivets are on order.

Finally was able to use the new rivet removal tool from Cleaveland Aircraft Tool...awesome.


 
Oct 29, 2022     Fuel Tank: Finish prepping interior ribs (6) - (5.5 hours) Category: 18:Fuel Tank
 
Oct 26, 2022     Fuel Tanks: Prepping Interior Ribs (2) - (1.2 hours) Category: 18:Fuel Tank
 
Oct 25, 2022     Fuel Tanks: prepping interior ribs (2) - (1.5 hours)       Category: 18:Fuel Tank


 
Sep 15, 2022     Fuel Tank: Continued riveting stiffeners (4 completed) - (1.0 hour) Category: 18:Fuel Tank
 
Sep 14, 2022     Fuel Tank: continue riveting stiffeners on left tank (3 completed) - (.8 hour) Category: 18:Fuel Tank
 
Sep 12, 2022     Fuel Tank: Begin riveting stiffeners for left tank (3 completed) - (1.2 hours) Category: 18:Fuel Tank
 
Sep 06, 2022     Fuel Tank: mounted right root rib flanges. - (1.1 hours)       Category: 18:Fuel Tank
This was my first time working with tank sealant. It'll get better but this is satisfactory.


 
Sep 02, 2022     Fuel Tank: dimple screw holes in right tank - (1.2 hours) Category: 18:Fuel Tank
 
Aug 31, 2022     Fuel Tank: right tank, begin scuffing for ribs and stiffeners - (.7 hour) Category: 18:Fuel Tank
 
Aug 30, 2022     Fuel Tank: debur rivet holes right tank skin - (1.0 hour)       Category: 18:Fuel Tank


 
Aug 27, 2022     Fuel Tank: prepping tank skins and j stiffeners - (6.5 hours) Category: 18:Fuel Tank
- drilled and deburred all screw holes to final size
- break trailing edges of tank skins
- deburr edges of tank skins
 
Aug 24, 2022     Fuel Tank: Continue countersinking rear baffle skin holes - (.7 hour) Category: 18:Fuel Tank
 
Aug 22, 2022     Fuel Tank: Debur rear baffles, cleco them to tank skin. - (.5 hour) Category: 18:Fuel Tank
 
Aug 19, 2022     Fuel Tank: debur, scuff and prime z brackets - (2.0 hours)       Category: 18:Fuel Tank


 
Aug 17, 2022     Fuel Tanks: cut, debur, countersink z-brackets - (1.2 hours)       Category: 18:Fuel Tank


 
Aug 16, 2022     Fuel Tank: scuff, clean, and dimple tank stiffeners - (1.3 hours) Category: 18:Fuel Tank
 
Aug 13, 2022     Fuel Tank: prep root and tip ribs, drill root rib webs for ventline fitting. - (4.0 hours) Category: 18:Fuel Tank
There were so many parts back ordered from the wing kit, I'm just trying to do what I can with the parts that I have.
 
Aug 14, 2022     Fuel Tank: Prepping tank stiffeners - (4.2 hours) Category: 18:Fuel Tank
 