Builder Name:Michael Yankaitis   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1400.5
Total Flight Time:
Start/Last Date:Oct 14, 2019 - No Finish Date
Panel:Apollo 80 GPS, GRT EFIS-AP
 
Friendly URL: https://eaabuilderslog.org?s=MikeYRansS21

Home or Last Project Picture

Feb 19, 2023     New door handles - (2.0 hours)       Category: Fuselage
Install new door latches, both sides. Left kick panel back on.


 
Feb 18, 2023     Carb work - (4.0 hours)       Category: Engine
Machine Carb for throttle shaft seals: In case I need to backtrack and swap the Rotec TBI back to the Marvel MA--4SPA.


 
Jan 01, 2023     Fuel return line - (1.5 hours)       Category: Engine
Make orifice for fuel return line. 1/16 npt plug with 5/64 drilled hole.


 
Dec 18, 2022     Rudder return - (2 hours)       Category: Fuselage
Finish rudder return system.


 
Dec 17, 2022     TBI cooling shroud on - (4.0 hours)       Category: Engine
Install TBI cooling shroud and Gascolator blast cooling shroud.


 
Dec 17, 2022     Rudder return cables - (1.5 hours) Category: Fuselage
Start on new rudder return cable installation. Just need to rivet plates to floor and adjust tensions.
 
Dec 16, 2022     Intake - door handle mods - (6 hours)       Category: Engine
Prep new door handles for install. Cut center shaft and spacers and fit to handles. Pin inside handle to shaft. Make templates and then aluminum pieces (4) for the TBI cooling shroud. Mount on engine and connect heater scat hose as a test. All looks good. Mount new compressor outlet temp sending unit into intake plenum. Re-seal fuel shutoff outlet fitting that was weeping fuel. Test and it seems sealed now.


 
Dec 10, 2022     Fuel return line - (3.5 hours) Category: Engine
Add fuel return line from TBI to Gascolator inlet.
 
Dec 06, 2022     Carb intake box - (1.5 hours) Category: Engine
Make micarta intake plenum extensions. 1.875" tall to improve flow into Rotec TBI. No noticeable difference.
 
Nov 28, 2022     Fuel tank migration issue - (2 hours) Category: Fuselage
Add aft fuel tank support from Rans to Right side tank. Left side not installed due to OAT probe in the way. Might re-locate in spring time.
 
Nov 23, 2022     First flight. - (.5 hour) Category: Test run
Fly plane to KCWA and put in hanger. First flight. Some radio issues to sort through, but overall uneventful.
 
Nov 16, 2022     Door latches - (2 hours)       Category: Interior Finish
Dremel door latch stops so latch goes overcenter further. Add bungies to secure latches for test flights.


 
Nov 14, 2022     Test runs - (2 hours)       Category: Test run
Test run engine, 62% for 5 minutes continuous. Taxi tests. Multiple passes with tail raised, verifying directional control. Door latches not secure. Both unlatched during taxiing.


 
Nov 10, 2022     Finishing up re-assembly - (3 hours) Category: Inspection
Cowling back on. Drain fuel and re-do W&B.
 
Nov 09, 2022     A/W inspection - (5.5 hours) Category: Inspection
A/W inspection from JN. All good and passed. Put plane back together, inspection panels, seats, etc.
 
Nov 05, 2022     More heat shield - (2 hours) Category: Engine
Add more heat shield on inside of cowl.
 
Oct 30, 2022     fire ext - (2.5 hours) Category: Interior Finish
Install fire extinguisher under engine controls.Ground run doing mag checks and 65% power LOP test. Emags fine, no go on LOP. Cowling gets warm/hot near turbo and exhaust. Order heat shield from Summit Racing.
 
Oct 26, 2022     Roll AP cable clamps, + - (2 hours)       Category: Controls
Install and torque new AP Roll cable clamps. Re-fit top cowling with new foam spacer blocks in place. Baffle seals much better now.


 
Oct 25, 2022     AP servo cable clamps - (3 hours)       Category: Controls
Machine new AP roll servo cable clamps out of steel, to replace the UHMW ones. A nice mill project.
Add foam blocks to upper cowl to block off large air gap on either side of flywheel near the top. 3 layers of glass to hold in place.


 
Oct 23, 2022     Cowling install - (2 hours)       Category: Fuselage
Re-install cowling complete. Prepare for some ground test runs.


 
Oct 22, 2022     squawk list - (3 hours) Category: Inspection
Finish items on inspection squawk list.
 
Oct 21, 2022     Airplane inspection and squawk list - (5 hours) Category: Inspection
Corey, A&P does a once over inspection on the plane. Spend some time going through items on his list.
 
Oct 20, 2022     Cowling - (3 hours) Category: Engine
Glass bridge on top cowling bump so seal fits better. Silicone gaps between baffle and engine.Do final W&B on airplane.
 
Oct 19, 2022     Baffle seal - (4 hours) Category: Engine
Install baffle seals, all. Turned out nice.
 
Oct 19, 2022     Baffles - (6 hours) Category: Engine
Finish baffle fit and installation
 
Oct 18, 2022     Cowling - (5.5 hours)       Category: Fuselage
Test fit cowling using finish fasteners. OK. Piano hinge keepers on. Start on baffling. Install outer prop spinner bulkhead, (Vans 13" Sensenich style). Torque and safety wire prop bolts.


 
Oct 17, 2022     Cowl - (7 hours)       Category: Fuselage
Nut plates for cowling all riveted onto fuselage. Air intake NACA scoop fit, bonded, and glassed in place.Oil dipstick door cut and hinge riveted in place


 
Oct 15, 2022     Cowling - (5 hours) Category: Fuselage
Final drill size and cleco upper cowl to fuselage. Drill and prep for nut plates
 
Oct 14, 2022     Cowling - (5.5 hours) Category: Fuselage
Fit upper cowling to fuselage. Install piano hinges between upper and lower.
 
Oct 13, 2022     Cowling - (6 hours)       Category: Fuselage
Trim upper and lower cowl pieces. Fit lower cowling to fuselage. Start on upper.


 
Oct 12, 2022     Cowling - (3 hours)       Category: Fuselage
Finish laying up lower cowling. De-mold.


 
Oct 11, 2022     Cowlings - (3 hours)       Category: Fuselage
De-mold top cowling. Good. Start lay-up of lower. 1/2 done.


 
Oct 10, 2022     Cowling top - (3 hours)       Category: Fuselage
Lay up top cowling part. 2 layers 1708, 2 layers 2x2 twill.


 
Oct 09, 2022     Mold-test run - (3.5 hours)       Category: Fuselage
PVA and Gelcoat on molds. Test run engine. Run up to WFO, and add boost. Get up to 113% power, 180 hp, 2650 static rpm, 14 GPH full rich.


 
Oct 08, 2022     Mold- W&B - (2 hours)       Category: Fuselage
De-mold lower cowling. Junk. Preliminary weigh plane to test scale and blocks. Nice.


 
Oct 07, 2022     Molds-scale - (5.5 hours)       Category: Fuselage
De-mold top. No good. Lay up lower. Same thing. Finish 1000# scale.


 
Oct 06, 2022     Glass work-scale - (4 hours)       Category: Fuselage
Lay up glass on top mold. Prep for lower. Resin attacking gelcoat. Junk. Start on 1000# scale


 
Oct 05, 2022     Molds - (2 hours)       Category: Fuselage
PVA and Blue gelcoat on molds


 
Oct 04, 2022     Engine-mold - (4 hours) Category: Engine
TBI back on. Intake all together and engine controls rigged and tested. Last coat of wax on molds.
 
Oct 03, 2022     TBI-mold work - (3.5 hours)       Category: Engine
Test TBi again. Polish seat to remove machining marks. Better but still leaks. More wax on molds.


 
Oct 02, 2022     TBI test - (2 hours)       Category: Engine
Bench test Rotec TBI. Leaking with any incoming pressure. Dis assemble unit and suspect needle and seat not working well. Another wax coat on molds.


 
Sep 30, 2022     TBI-cowling mold - (4.5 hours) Category: Engine
Remove Rotec TBI from engine. Wax molds
 
Sep 28, 2022     Mold work - (3 hours)       Category: Fuselage
Buff molds with two different grit compounds. Clean and apply one coat of mold release wax.


 
Sep 27, 2022     Cowl mold - (2.5 hours)       Category: Fuselage
Wet sand cowling molds with 1000 grit.


 
Sep 25, 2022     Test run - (3.5 hours)       Category: Fuel System
Test run with prop and Rotec TBI. Notice fuel leaking from spray bar with any positive pressure to carb. Remove intake plenum. Waiting on direction from Rotec.


 
Sep 24, 2022     A/W inspection - (2 hours) Category: Research
Fill out paperwork for A/W inspection.
 
Sep 23, 2022     Prop install - (4 hours)       Category: Propeller
Install and safety wire prop. Install spinner. Make and install shim blocks behind both wing tanks to prevent them from shifting rearward.


 
Sep 22, 2022     Spinner fit up - (3 hours)       Category: Propeller
Cut spinner for prop and fit to back plate. Install nut plates.


 
Sep 01, 2022     Cowling - (3.5 hours)       Category: Fuselage
More gelcoat patching. Wet sand. Make stand for lower mold.


 
Aug 30, 2022     Cowling - (2 hours) Category: Fuselage
Gelcoat patches on mold imperfections. Wet sand.
 
Aug 24, 2022     Cowling - (5 hours)       Category: Fuselage
Cut mold in half. Sand edges.Epoxy on edge voids. pull plug out and pitch.


 
Aug 21, 2022     Cowling - (2.5 hours)       Category: Fuselage
Glue wood to mold. Glass in place. To be used for stands.


 
Aug 17, 2022     Cowling - (5.5 hours)       Category: Fuselage
Layer of 2515 on most of mold over two days.


 
Aug 15, 2022     Cowling - (2 hours) Category: Fuselage
Layer of CSM on mold
 
Aug 14, 2022     Cowling - (2.5 hours) Category: Fuselage
1 layer of heavier glass on plug-mold
 
Aug 13, 2022     Cowling - (3.5 hours) Category: Fuselage
Veil and one coat layer of thin glass on plug
 
Aug 12, 2022     Cowling - (3 hours)       Category: Fuselage
3 coats of orange tooling gelcoat on plug


 
Aug 11, 2022     Cowling - (5 hours) Category: Fuselage
5 coats of wax on plug
 
Jul 19, 2022     Cowling - (2 hours)       Category: Fuselage
Primer on plug. Finish sand to 800


 
Jul 18, 2022     Cowling - (5 hours)       Category: Fuselage
Bondo-sand plug


 
Jul 14, 2022     Cowling - (3.5 hours)       Category: Fuselage
Sand, prime, spot putty


 
Jul 13, 2022     Cowling plug - (3 hours)       Category: Fuselage
Sand, mud and primer on plug


 
Jul 08, 2022     Cowling - (6 hours) Category: Fuselage
Mud and sanding on plug, repeat.
 
Jul 04, 2022     Cowling etc - (3 hours)       Category: Fuselage
More mud on cowling plug. Silicone on skylight. Trim tape on wing tips.


 
Jul 03, 2022     Magnetometer, pitot-static - (2.0 hours) Category: Avionics
Calibrate magnetometer. Tested good. Test Pitot and static systems for leaks and response in EFIS. Both OK.
 
Jul 02, 2022     Plug work, safety wire - (4.0 hours)       Category: Fuselage
Sand and more mud on plug mold. Safety wire 3 turnbuckles. Make template, then cut dash cover material.


 
Jun 30, 2022     More plug work - (2 hours) Category: Fuselage
Sand on plug and add more mud, again.
 
Jun 30, 2022     Skylight bows - (4 hours)       Category: Fuselage
Re-form and rivet skylight bows on. More mud on cowl plug.Test fit windshield. Make skylight mating and trim strips.


 
Jun 28, 2022     Dash labels, sanding on plug - (2.5 hours)       Category: Fuselage
Make and install engine control dash labels. Sand on plug, add another layer of mud.


 
Jun 26, 2022     Skylight - (1.5 hours)       Category: Fuselage
Finish riveting of skylight mating strip. Silicone fillets on all exposed edges.


 
Jun 22, 2022     Right wingtip re-work - (4.5 hours)       Category: Wings
Remove right wingtip. Try adding shims to give clearance to aileron. No go. Remove again, cut plastic support rib, re-position and bond in place. Trim inboard trailing edge of wingtip for clearance. Install. 3/16" clearance now. Put trim tape on wings, wingtips and dark grey-blue line. More mud on cowling plug.


 
Jun 19, 2022     Windshield - (4.5 hours)       Category: Fuselage
Final rivet and bond windshield lower trim strip in place. Bond wing cuffs in place.


 
Jun 17, 2022     Windshield-Skylight - (2 hours)       Category: Fuselage
Final rivet skylight and Z strips on.


 
Jun 16, 2022     Windshield - (3.5 hours)       Category: Fuselage
Final fit of windshield and Z strips and cleco in place. Lifting lugs on axles. Gear fairings on.


 
Jun 15, 2022     windshield - (4.5 hours)       Category: Fuselage
Tinnermans on wing inspection holes. Install wing gap seal. Final install of flap gap seal. RE-do foam on some pieces using softer material. Install doors and door lift struts. Final rivet of rear door catch.


 
Jun 12, 2022     Windshield - Skylight - (3 hours)       Category: Fuselage
Move all painted trim parts to hanger. Foam tape on. Paint fiberglass lower windshield trim strip. Cleco skylight and trim strips on. Prep for full windshield fit-up.


 
Jun 10, 2022     Windshield-skylight - (6.5 hours)       Category: Fuselage
Remove skylight and windshield. Prep and paint all trim pieces. Paint black on windshield.


 
Jun 08, 2022     Windshield - (4 hours)       Category: Fuselage
Finish windshield fit-up. Lower trim drilled and clecoed in place. Fit, drill and cleco flap gap seals. More mud on cowling plug.


 
Jun 07, 2022     Windshield work - (4 hours)       Category: Fuselage
Trim windshield, Z trim strips fitted and clecoed, Cuffs cut and fitted.


 
Jun 06, 2022     Windshield and skylight - (3.5 hours)       Category: Fuselage
Cut, finish fit, drill and cleco skylight.


 
Jun 05, 2022     Windshield and skylight - (5 hours)       Category: Fuselage
Make and cleco skylight side trim and spacer strips. Make and fit skylight rear trim strip. Re-bend skylight bows, again. Install boot cowl top over dash. Run power wire for possible electric adj prop.


 
Jun 03, 2022     Cowl plug - (1.5 hours) Category: Fuselage
Sand cowling plug
 
May 31, 2022     Misc wings - (3 hours) Category: Wings
Adjust throws on ailerons and elevator per specs in manual. Check flap throws, OK. Bend bows for skylight.
 
May 27, 2022     Cowling plug - (1.5 hours) Category: Fuselage
Coat of joint compound on cowling plug
 
May 25, 2022     Ailerons - Flaps - (5.5 hours)       Category: Wings
Install ailerons and flaps. Rig and adjust for neutral. Fit and silicone both landing light lenses. Install rear side windows, both.


 
May 24, 2022     More on wings - (7.0 hours)       Category: Wings
Tidy up wiring in fuse going to wings. Make pitot and AOA connections between fuse and left wing. Fit wingtip light lenses on. Aim landing-taxi lights. Bolt wingtips on and test lights. Upper strut fairing rivnuts in and fairings installed. Finish aligning and mounting of H-stab. Finish mount of elevator. Calibrate elevator trim indicator on the GRT EFIS.


 
May 23, 2022     Wire wings - (6.5 hours) Category: Wings
Make end connections for nav-strobe-landing lights in wings and in fuselage. Molex connectors to ease removal of wingtips and wings. Finish torque and torque seal on wing attach mount bolts.
 
May 22, 2022     rigging - (2.5 hours) Category: Wings
Rig aileron and flap cables in cockpit. Tension aileron AP cable.
 
May 21, 2022     Install wings - (3 hours)       Category: Wings
Install left and right wings, struts. Bolts need finish torque and torque seal.


 
May 18, 2022     Mount H-stab + - (3 hours) Category: Fuselage
Mount H-stab back onto fuse. Needs final alignment. Moved plane from shop to hanger and moved all the associated parts also.
 
May 17, 2022     Boost pressure-map sensor - (2 hours)       Category: Avionics
Install, wire, plumb, and program new GRT map sensor to be used as a boost pressure sensor.


 
May 06, 2022     Blast tube - (1.5 hours)       Category: Engine
Install blast tube for engine driven fuel pump.


 
May 05, 2022     Mixture control plus - (4.5 hours)       Category: Engine
Anchor mixture cable. Make anchor bracket. Tbi controls done. Remove turbo boost and afr gages from center stack. Remote mount afr gage, re-mount scavenge pump light and auto-on switch. Order grt map sensor for turbo boost sensing. Also order longer throttle cable from Vans.


 
May 04, 2022     Tbi controls - (3.5 hours)       Category: Engine
Mount throttle, primer lever, intake plenum. Then mount tbi to engine. Add primer cable mount standoff to wastegate. Enlarge prop control head panel hole from 2.0625 to 2.25" diameter.


 
May 03, 2022     Tbi controls - (5 hours)       Category: Engine
Fabricate throttle-tbi mount bracket. Make tbi primer anchor and lever. Make 1/4” thick micarta spacer to be used between sump and tbi.


 