Project: phowe   -  
            Listing for Category : fuel system
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Philip Howe   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1654.75
Total Flight Time:6
Total Expense:N/A
Start/Last Date:Oct 19, 2020 - No Finish Date
Engine:Rotax 915is
Propeller:Whirlwind
Panel:Dynon
 
Friendly URL: https://eaabuilderslog.org?s=phowe

Home or Last Project Picture

May 06, 2024     Trimmed Brackets Holding Header Tank - (1 hour)       Category: Fuel System
I removed the brackets under the huge hose clamps to trim the bottom sides near the aileron cables and turnbuckle. We were concerned that they might rub on the cables.


 
May 02, 2024     Attached Fuel lines to fuel tanks - (1 hour)       Category: Fuel System
Used the fittings and fuel line we attached the main fuel lines. For the vent line, we installed the connector and attached it to the left-wing fuel tank fitting. We are holding off on connecting all the lines to the header tank.


 
Sep 18, 2023     Electric Fuel Pump - (2 hours)       Category: Fuel System
Mounted the auxiliary electric fuel pump and filter on the tray with the pitch servo.


 
Sep 15, 2023     Installed Header Tank - (2 hours)       Category: Fuel System
Installed the header tank and repressure tested it. We did discover an issue. The tank interferes with the left side main gear brake fitting. We will reposition the brake line fitting later.


 
Sep 14, 2023     Header tank - (4 hours)       Category: Fuel System
We had to remove the nipple fittings in the rear to get the header tank to fit. We then drilled and installed the drain plug and drilled the hole in the fuselage. We need to go larger on the fuselage hole. We also bent the strap holders and notched them per instructions.


 
Sep 12, 2023     Header Tank - (1 hour)       Category: Fuel System
Riveted Header tank tray to the fuselage and put weather stripping tape to protect the tank from rivet heads plus reduce vibration and potential movement. We also pressure tested the tank - it passed.


 
Sep 11, 2023     Header Tank - (4.5 hours) Category: Fuel System
Son Chris mounted all of the fittings on the header tank. I worked on mounting the tray I riveted a small plate over the previous header tank's drain hole in the bottom skin.
 
Sep 01, 2023     Header Tank - (1 hour)       Category: Fuel System
Son Chris located all the remaining parts for the header tank and then watched a YouTube video of a builder assembling one to get a clear understanding of how to install all the fittings.


 
Aug 31, 2023     Looking for Parts for Header Tank - (2 hours) Category: Fuel System
Even with brother Chris' new inventory/location system son Chris spent 2 hours looking for all the parts for mounting and finishing out the header.
 
Aug 31, 2023     Looking for Parts for Header Tank - (2.9 hours) Category: Fuel System
 
Aug 30, 2023     Header tank - (12 hours)       Category: Fuel System
I spent most of the day working on the header tank. I drilled out the support from the smaller header tank and then match drilled the new tray to the support and the fuselage cage tab. I then measured the hole placement on the new header tank then drilled them out. Chris made a metal plate to cover the sump drain hole from the smaller tank. We will rivet it on before we rivet the header tank tray.


 
Feb 15, 2022     Header tank - (1 hour)       Category: Fuel System
A final pressure test, glued rubber strip around tray and then installed.


 
Feb 11, 2022     Header - (5 hours)       Category: Fuel System
Worked on placement so that the connections fit nicely and the placement of the mounting tray.


 
Feb 10, 2022     Header Tank - (5 hours)       Category: Fuel System
Worked on installing the connections in the header tank. Did a pressure test.


 
Dec 16, 2021     Header tank - (4 hours)       Category: Fuel System
Attached all the fittings to the header tank after working on the tank support needed to trim so that the support would clear one of the stiffeners.


 
Dec 15, 2021     Header tank - (1 hour) Category: Fuel System
Worked on the mounts for the header tank. Located on the parts in a sealed plastic bag.
 
Dec 14, 2021     Header Tank - (1 hour) Category: Fuel System
Drilled holes in the header tank. Started to look for the rest of the header tank parts.
 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.