Project: N64BN   -  
            Listing for Category : practice
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Bjorn Nilberg   -  
Project:   Vans - RV-7   -   VIEW REPORTS
Total Hours:2193.5
Total Flight Time:1
Start/Last Date:Aug 15, 2013 - No Finish Date
Engine:Superior IO-360
Panel:Garmin G3x
 
Friendly URL: https://eaabuilderslog.org?s=N64BN

Home or Last Project Picture

Aug 17, 2018     Assisted another builder Category: Practice
Assisted another builders first engine start. That was fun, but not without complications.
 
Oct 04, 2014     Pulling Engine Category: Practice
Pulled an engine off an friends plane. Good introduction to power plant mechanics.
 
Aug 29, 2013     Finishing Toolbox - (3.00 hours)       Category: Practice
Finished the first practice kit from Van's. Squeezing is easy, but I need a lot of more practice with the rivet gun before attacking real aircraft parts.


 
Aug 28, 2013     Riveting practice (Toolbox) - (3.00 hours) Category: Practice
Started to build Vans training project, the Toolbox. Using the pneumatic dimpler and squeezer was super easy. The rivet gun not so much. Definitely needed the rivet gun training.
 