Project: rtardiff   -  
            Listing for Category : interior finish
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Richard Tardiff   -  
Project:   Bearhawk - Patrol   -   VIEW REPORTS
Total Hours:2319.25
Total Flight Time:0.7
Total Expense:$39.00
Start/Last Date:Aug 10, 2019 - No Finish Date
Engine:Lycoming 0360
 
Friendly URL: https://eaabuilderslog.org?s=rtardiff

Home or Last Project Picture

Jul 11, 2023     Details - (5 hours)       Category: Interior Finish
Installed the pilot seat belt, added a knob to the trim control, and riveted the Plexiglas on the pilot door.


 
Jun 27, 2023     Panels, again - (6 hours) Category: Interior Finish
Continued fitting interior panels.
 
Jun 26, 2023     We're covered - (6 hours)       Category: Interior Finish
Installed seats over kit frames. Sourced from Sport Aircraft Seats.


 
Jun 23, 2023     Have a Seat! - (4 hours)       Category: Interior Finish
Prepped seat frames for cover.


 
Jun 16, 2023     Details - (1.5 hours) Category: Interior Finish
Reattached interior panels.
 
Jun 09, 2023     Trim - (2 hours) Category: Interior Finish
Fit interior trim pieces/
 
May 24, 2022     Right side fabric - (8 hours) Category: Interior Finish
Fit and glued fabric, right side.
 
May 23, 2022     Right rear panel, continued - (5 hours) Category: Interior Finish
More nut plates and Adel clamps to anchor panel.
 
May 18, 2022     Interior fabric. - (6 hours) Category: Interior Finish
Began shrinking fabric (250-300-350). Not satisfied with fabric in passenger area. Replaced and overlapped front piece. (2" overlap over tubing)
 
May 17, 2022     Interior Fabric - (4 hours) Category: Interior Finish
More fabric and glue. Fit is getting more precise as I learn, but I'll need to patch in a number of places where the fabric goes around tubes at odd angles.
 
May 16, 2022     More interior fabric - (7 hours)       Category: Interior Finish
Fit and glued fabric to interior, ceiling and lower sides, using Air Tech adhesive.


 
May 11, 2022     Dry-fit fabric - (8 hours)       Category: Interior Finish
Cut and dry-fit fabric prior to adhesive application.


 
May 09, 2022     Nut plates and fabric work. - (7 hours)       Category: Interior Finish
Mark, drill, deburr, etc. Attaching panels with machine screws and nut plates in order to facilitate inspection and adjustment of throttle & trim controls. Began fitting fabric to interior


 
May 05, 2022     Side panels - (11 hours) Category: Interior Finish
(Portions of 3 days) continued trimming and fitting the panels. it's not a lot of surface, but lots of stuff to cut around.
 
May 04, 2022     Side panels - (4 hours)       Category: Interior Finish
Continued fitting and trimming panels. Will acid etch and Alodine prior to painting.


 
May 03, 2022     Side panels - (8 hours)       Category: Interior Finish
Panels will be anchored to 3/4' aluminum angle. Sheet metal skills are improving, but very slowly. The new 36" brake is most helpful, though the sharp edges cry out for some file work.


 
May 02, 2022     Side panels - (6 hours)       Category: Interior Finish
Continued fitting the aluminum panels along the left side of the cockpit.


 
Apr 30, 2022     Design Changes Have Consequences - (33.5 hours) Category: Interior Finish
I learned to fly in a Citabria, which has the trim control on the left side, below the throttle. Mr. Barrows designed the Patrol with the trim control above and behind the pilot's head. Just didn't work for me, so I moved it. As a result, I have cables running along the left side of the cockpit, front and rear, all the way back through the baggage compartment. Seemed like a control jam situation waiting to happen. So, I've spent the last few weeks fabricating aluminum panels to protect the cables, and prevent a future inconvenience. Many re-dos, as the design develops. (photos to follow in a future post.
 
Mar 07, 2022     Protecting Controls.2 - (10 hours)       Category: Interior Finish
Continued fitting and adjusting the side panel that will protect the trim cables and rod connecting fore and aft throttle controls. (2 work days)


 
Mar 01, 2022     Protecting the Controls - (14 hours)       Category: Interior Finish
Continued work on the .025 panel on the left side . Fabricated several L-shaped brackets with nut plates attached. These were attached to fuselage tubing with Adel clamps. The shroud ended up a two-piece affair. The inner piece was bent at the edges to add stiffness, and will anchor the fabric at the bottom. the top piece will be covered with Ceconite to match the rest of the interior. Using a small router,mounted on a pivoting base, I cut an arc in the top piece to fit around the trim control. (3 work days)


 
Feb 28, 2022     Side Panel - (5 hours)       Category: Interior Finish
Made a couple adjustments to the original design to better accommodate removal for inspection. Cut and fit the panel. Will add inspection holes at quadrants, inside and out.


 
Feb 24, 2022     Pre-Cover preparation.2 - (6 hours) Category: Interior Finish
Fabricated a mockup of a .025 panel to protect throttle linkage and trim cables @ left side.
 